MRP type V1

Dear All,
Please let me know the settings in material master for MRP type V1. I have enetred lot size as MB. Minimum lot size 200, reorder point 100. After MRP run we received purchase requisistion of 200. Then we created sales order due to which now there is requirement of 300 pcs for that material but system is not considering the shortage of 100 pcs. please let me know the reason.
Regards,
SAP CONS

Dear
MRP Type V1 consider the re-order point quanity  and generate the requirement after MRP run .In your case , it frist consider the Re-Order point , then Minimum Order Quantity  and do not consider the Sales Order .But it will also consider the Sales Order as demand on priority if the Sales Order Quantity is more than the Re-Order Point .
Let , say you do not have stock .U have Sales Order Quanity 2000 pc  and re-order point in Material Master 1800 pc , Mini Lot Size 1000 .If you run MRP-MD03,  the result will be  based on the MRP Type-V1 considering the re-order point qty after calculating Net Requirement and generate PR with 1000PC  and rest .
More over , you are using MB-Monthly Lot size , it will club all the Monthly requirement as  PR in the Planning Horizon based on your MRP  run  date .
So if you use , MRP Type PD , i hope it will consider your Sales Order Requirement along with your PIR
Regardss
JH

Similar Messages

  • MRP Type P1 and late firm schedule lines

    Hello All,
         We are using MRP Type P1 which firms our schedule agreement schedule lines within the planning time fence (as desired).  However, sometimes the supplier is late on delivery and the firm schedule line goes into the past.
         Is it possible to have MRP move the firm schedule line delivery date to today instead of going into the past?
         Thank you,
         Jerry

    Hi ,
    Bring process forward (reschedule in)
    Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
    It does not take in to account the GR processing time and it is purely based on the stock requirement date , parameters in Procurement and Scheduling in the Material Master
    So it will consume the requirement  backward scheduling and bring the Process forward.
    Kumar which  strategy are you using ?  scheduling agreement is of weekly , daily or monthly bucket ?
    How many days SA bring to Production and How many days SA for forecast you are doing ?
    Are you using any Program to convert these SA in to PIR and upload ( using any program ) .
    Regards,
    Jayavimal
    Edited by: jaya vimal on Jun 16, 2010 1:33 PM

  • Error msg when changing the MRP type in ME22N

    Hi,
    When i change MRP type from MRP to Manual  in ME22N, it will come out the error msg:Purchase request mandatory for MRP generated Purchase order (Application area: ME Message no. ME901)!  My question is how to change this error msg to warning msg?
    From SPRO-Material Management-Purchasing-Environment Data-Define Attributes of System Messages ,i can not find the entry regarding this issue.
    Any suggestion!
    Thanks!

    Hi,
    Sometimes end user want to add some item without PR under MRP PO.
    As before system will only indicate the warning msg that we change to error msg three month ago, but i forgot how to change!
    thanks!

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • MRP Type V1 - How to take open Purchase Orders into consideration

    hi I'm having a problem with a material which is setup as MRP type V1.
    When running MRP using NEUPL a purchase requisition is created as expected based on re-order point on the material master. At this point the Purchase Req is converted to a PO, but the delivery date maybe pushed out before saving. Running MRP after pushing out the deliver date on Purchase Orer generates another Purchase Requistion with a delivery date before the PO. Is there a way to get MRP to take the open PO into consideration rather than suggesting another PO ?
    Our planning horizon is set to 365 days.
    Is it possible to get MRP to see the PO and not suggest a req ?
    Thanks for any help

    I have checked the availability check and we are using one that is ticked to include purchase orders. this does not seem to have any effect.
    The lead time on the item is 5 on the material master and 15 on the infor rec which is not that high ?
    and when running MB02 for the item I am running with Create Purchase Requistion = 1
    is it that what I'm expecting is unrealistic? i.e that for re-order point materials MRP is only going to take into account the lead times and if there is a Purchase Order with a delivery date outside of the leadtime the system will see that we need to reorder and generates a Req within the leadtime without looking out futher to see what's on order ?

  • Schedule Lines not generated for MRP Type PD

    HI All,
    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement. 
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Please help
    Regards,
    Vikas

    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement.
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Hi Vikas,
                      After being thru with your query,i would like to reply your ultimate question"I want delivery schedules based on MRP Type PD"
    Simple answer:put parameter 'delivery schedule line' as '3'(schedule lines in opening period) without simulation mode.
    Please make sure you  don't make any change with previous settings(custom)
    please get it done and revert.
    Regards
    Chandra

  • MRP Type P1 & Lot size PK

    Dear All,
    This is REM scenario,
    Client is going scheduling agreements
    material master Settings
    MRP Type - P1
    Planning time fence - 10
    Lot Size - PK
    Procurement type - F
    GR Processing time - 2 days, No plad delevery time maintained.
    in planning calendar we are going with only one day as Friday
    and we made previous day is working day if friday is holiday.
    After MRP system is proposing dates for schedule lines as
    16/06/2010 ( wednesday ) Rescheduling date as 07/06/2010 ( Monday ) ( Rescheduling in i.e 10 )
    How system is proposing this dates
    Please share your views or if required more info then revert back
    i cannot upload Docs as my company policy is not allowing
    Regards
    Madhu

    Hi ,
    Bring process forward (reschedule in)
    Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
    It does not take in to account the GR processing time and it is purely based on the stock requirement date , parameters in Procurement and Scheduling in the Material Master
    So it will consume the requirement  backward scheduling and bring the Process forward.
    Kumar which  strategy are you using ?  scheduling agreement is of weekly , daily or monthly bucket ?
    How many days SA bring to Production and How many days SA for forecast you are doing ?
    Are you using any Program to convert these SA in to PIR and upload ( using any program ) .
    Regards,
    Jayavimal
    Edited by: jaya vimal on Jun 16, 2010 1:33 PM

  • Planning with Re-order point considering external requirements(MRP type V1)

    Dear  all,
    We are working for a scenario as mentioned below,
    We procure some marterial from our vendors, stock it and then sell to other customers.
    Here we want to use Re order point planning considering external requirements , i.e. MRP type V1.
    We have maintained following master data
    MRP type = V1
    Re order point quantity
    Lot size = HB
    Maximum stock level
    Planned delivery time.
    We have also created source list,Info record and scheduling agreement
    We also maintained setting of schedule agreement in source list as 2 (Record relevant to MRP schedule lines generated automatically)
    By doing above mentioned things when we run MRP we are getting schedule lines generated through MRP, for the lot size arrived by considering re order level,max. stock level etc.
    My requirement is the schedule line that is coming through MRP should get firmed up, whcih is not happening currently.
    Pl. guide as what other setting is required for getting firmed schedule lines.
    Regards,
    Sandeep

    Hi
    Automatic firming of Schedule lines only possible with the settings of Planning time Fence (PTF) in MRP-1 view with MRP type which allows firming . With Standard MRP type V1 it is not possible.
    As per my idea , better to create new MRP type in SPRO by copying V1 settings and give Firming type as 1  additionally. Use this new MRP type in the MRP-1 view and give Planning Time Fence say 30.
    When u run MRP then the requirements falling within the PTF get firmed Automatically.
    Pl try and revert back
    Regards
    Brahmaji

  • Want to set Min Max for a material for PD MRP type

    Hi,
    I know Maximum stock level field in Material master MRP 2 view ? but where do i maintain minimum stock level? not procured?
    My client wants to set up his inventory with Min Max levels using MRP PD?
    Thanks and Apprecaites help.
    Regards,
    Siva

    Hi,
    If you want to maintain a Max and Min stock level, Maximum stock is shown straight away, you cannot find the Minimum field directly.
    if you want to use MRP type PD then go for safety stock that will be your minimum stock level
    or else use Re-order point planning, re-order point will be your minimum and Max-level as maximum.
    Thanks
    Satya

  • MRP Type V1, VB, or PD.

    I am loking to maintain MM02 MRP Type and maintain re-order point at 0.
    MRP Type V1 & VB are not allowing me to enter 0 as a re-order point value.
    I am in a simple distribution environment where finished goods are purchased and issued with no sales or production requirements.
    I would like to run MRP and generate Purchase Requisitions for items with re-order points.
    I am also looking to maintain the Material Master for items that are not required to have re-order points but may need to be ordered in future.
    The current MRP Type is: V1 with Lot Size: HB.
    Therefore I am unable to change Re-Order point to 0.
    What is the best setting for this enviroment to maintaint the Material Master and have re-order point of 0?
    Thank you,
    Tim

    Hi Tim!
    Your question is related to MRP module of ERP, however, this space is dedicated to SAP ME and MII solutions. Thus you'd rather re-post the question to a proper forum - this might help you find the right one.
    Regards,
    Sergiy

  • MRP TYPE for  Periodic planning in the material master.

    Dear gurus,
    i need planned the materials in the periodic modality, are there the type MRP in the material master for create the planned file ( table MDVM) one once a month or in the specific period chose ?
    Example :
    I need that the material master don't create a file planned ( MD20- TABLE MDVM) for a change of the requirement situation new , but i would like that the flag in the table ( MDVM) or file of the planning MRP created when the today date is in the period specific.
    31.3.2011  (or period 1.4.2011- 10-4-2011)Date for the create a file MRP and after when run MRP planned the material, for others scenary the system must not planned the material.
    Are there the MRP type for my problem? Or the customizing setting?
    Thanks a lot
    Dani

    Dani,
    Not sure if MRP type or customizing can help here. And even if we are able to achieve this requirement it will be applicable at plant level.
    However, try exploring option of periodic lot size (weekly, monthly, etc). This will work according to period you've set and should give you the results you are looking for.
    Regards,
    Himanshu

  • MRP type for two different types requirments( Sale order and PIRs)

    Dear All,
    We have requirment  some materials we have sales order and PIRs. For sales order we want to consider with "MRP type" as PD and PIR we want to consider "MRP type" as VB manual reorder point planning.
    Is there any stadard  solution.
    If standard solution not possible also poivde some inputs on enhancement.
    Regards
    Sailendra
    Edited by: nivedita yadav on May 7, 2010 2:31 PM

    Sailendra,
    your post is confusing, how you want to different MRP type for same material?
    and why its needed?
    1) you can use MRP type PD , and incoming sales order will search in existing stock or will create procurement proposal ( depends upon what strategy you are using)
    2) If you  are using VB then when ever you stock will fall below the reorder point you maintained in material master , system will create new procurement proposal, here the manual means the value you need to maintained manualy for reorder point and safety stock.
    In automatic reorder point planning, both the reorder level and the safety stock level are determined by the integrated forecasting program.
    The system uses past consumption data (historical data) to forecast future requirements. The system then uses these forecast values to calculate the reorder level and the safety stock level, taking the service level, which is specified by the MRP controller, and the material's replenishment lead time into account, and transfers them to the material master.
    hope it will help you.
    Regards
    Ritesh

  • Running MPS also runs MRP type PD materials

    Hello experts,
    In ECC 6.0, we have certain critical FINI materials to run with MPS ( ie type M0) while there are other FINI materials ( non critical) to run on MRP ( ie type PD).
    The issue we are finding is that ECC running MPS even for other MRP driven FINI materials in Tcode : MD40 ( with the Process MRP materials field checked). What we actually need is that MPS run for only those FINI materials that have MPS (ie type M0) & it's direct subassemblies of those materials which are MRP type PD.
    We do not want the MPS run to drive MRP for other FINI materials that have MRP type PD.
    I have checked SAP notes and they had similar issue & hence have a resolution note for earlier versions of SAP ( 3.0 to 4.6 versions). So this issue seems to be occouring again in ECC.
    Has anyone else come across this issue in ECC 6.0? If yes how it was resolved.
    Appreciate your feedback.
    Thanks,
    Ram

    Hi Ram,
    Just to understand the query better, can you let me know why you dont want the MPS run to drive the MRP run for other finished parts which are marked for MRP run? Is it that these parts are not to be planned?
    Regards,
    Vivek
    Added
    Also which SAP notes did you refer to?
    Edited by: Vivek on Mar 18, 2009 11:26 AM

  • Delivery Schedules not created after MRP Run for MRP Type PD

    HI All,
    I have created Schduling Agreement, maintained Source List with MRP Relevant - 2 option and maintained Vendor as Fix, maintained info record.
    I have created a material with MRP type as PD and lot size as EX, and strategy group as MTS. Now when i enter requirement through MD61 and do MRP Run through MD02, system is generating PR instead of Del Schdule line inspite of schduling agreement.
    But If i change MRP type to VB and maintain reorder point and maintain min lot size, then system generates Del Schdule lines for the same material.
    What could be the reason. I want delivery schedules based on MRP Type PD.
    Where I am wrong in MRP Views or in any cutomization. It seems that purchasing part is fine since it creats scudles line so no problem in SA or in Source List.
    Please help
    Regards,
    Vikas

    Hi Vikas,
    Go through this link you will able to customize correctly
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/3b/66596eda7b11d1b6330000e8a738dc/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
    Cheers
    Kris

  • Discontinued parts with MRP type VB

    We have scenario as below :
    1.       We have material A with stock 100, open PO 50.
    2.       The material A is now planned to be phased out by replacing it with a new material B
    3.       Material A had MRP type VB now we will change it to ND
    4.       Material B will have MRP type VB
    5.       So when we run MRP for materil B it should consider stock of material A & Open PO of Material A for calculation during the MRP run and the new requirement calculation should be
    Example :
    Material B is set up with RO point 100 and max stock of 150
    So when we run MRP for Material B even though stock for material B is zero it should not generate any new requirement as stock & open PO of material A exists.

    Hello
    Please take a look on the following note, which explains the general restrictions of the discontinuation process:
    43636 - Discontinued parts
    The note provides the following explanation regarding the MRP type:
    The material is planned using an MRP procedure, for example, MRP type PD.
    Therefore, since you are using MRP type VB, which uses a reorder point procedure, the discontinuation will not happen and your system is working as designed.
    BR
    Caetano

  • MRPgenerated requisitions and MRP type =VB

    Hi Gurus,
    I have the following question.
    IF a material has the MRP type VB=manual reorder point planning, then when the stock falls below the reorder point, MRP generates purchase  requisitions. For eg, on May 1st, MRP generated a requistion of 100 units of one material. Now, if no PO is created or no goods receipt done on May 1st of that material, will MRP run on the next day will create one more requistion of 100 units? Or there will be no requistion generated by MRP, as there is already a requistion of required qty sitting there?
    Thanks,
    Kumar

    Dear Kumar,
    MRP run is as per the business requirements and it can be run daily or weekly or monthly (or individually for a material using
    MD02.).In your case since already one PR for the required quantity has been existing in the system,when MRP is run on
    the next day the system does not create any additonal PR for 100 quantity,and if you run with a MRP control parameter with
    value 3 for planning type - delete and recreate planning data,then the system will delete the old PR and generates a new PR for
    the same 100 quantity.
    Check and revert
    Also check this link to explore more,
    Reorder point planning
    Regards
    Mangalraj.S

Maybe you are looking for

  • Missing images in photo books

    When I try the print or PDF preview of my photo book, there are several missing images or part missing images. Each time I preview the book different images appear to be corrupt or partly missing. They book appears to be fine in the viewer of Apertur

  • HT1526 Deleting files in my trash

    When I delete the files in my trash, all the files restore to their original location instead of deleting. I have no idea why this is happening as it's never happened before. I haven't been able to delete anything for weeks now. Help?

  • Listing Skype Number in local telephone directory ...

    What is the process for getting a listing in the local (Ireland, in my case) telephone directory (phonebook) using my Skype Number (which is a geographic Dublin number, where I reside). The publishers of the directory (which is available online and d

  • Only plays part of first song.

    i have everything updated and everything but after the first part of a song it goes back to home screan

  • KeystoreException : Cannot overwrite own certificate

    Hi, I am trying to import reply for request certification, but i have the following exception: "Cannot overwrite own certificate" The code to create the keystore is as follow : keyStore = KeyStore.getInstance(keyStoreType, provider); keyStore.load(nu