Multiple PR's generating for same material after MRP

Hi Guru's,
As per my business scenario, i am creating project with WBSE, Activities and BOM.
By using the reference points, i am transferring the BOM to Project, then executing MRP run.
But after MRP run i found that multiple PR's generated for the same Material.
Please find my BOM structure
BOM-->Assembly + raw material
Assembly is consists of
Sub-Assembly+ 2 raw materials
Sub-Assembly consists of
1 Raw Material.
as per this i should have 4 PR's after MRP but system is generating 8 PR's.
Please tell me where i am doing wrong
Regards,
Bhadra

Hi,
I find the reason why it is creating the multiple PR's for the same component.
It is because of the BOM status. Please find the attached scree shots for the BOM structure and BOM status.
As per my requirement the Planned Orders should be created for "BOM" and "Assembly" and 3 PR's should be generated for Components.
Initially i maintained BOM status as "4" for "BOM" due to that system is exploded the BOM twice i.e., for "BOM" and "Assembly" and generated PR's twice and two planned orders for "BOM" and "Assembly" along with their components.
Now to avoid the duplicates PR generation, i have maintained BOM Status as "5" for "BOM"and run MRP.
This time system is generated 3 PR's and 2 Planned Orders.
As per as PR's is concerned there is no issue. Coming to the Planned Orders there is a issue that, the components are not copied into order which is generated against "BOM" (BOM Status-5) and components are copied into order which is created against "Assembly"(BOM tatus-4)
But as per my requirement, the components should copied in both the orders.
So please tell where is the wrong in this..
Regards,
Rao

Similar Messages

  • Purchase requisition not generate for dependent requirement after MRP run

    Hello PP expert,
      In our MTO scenario after MRP run planned order generate for header material but no PR generate for BOM components, (BOM not explode) when we run MRP component level in MD02 PR generate, system showing message "40- No coverage not provided by master plan" in MD04 order tree. this problem coming after when we DIMP applied. I checked some OSS note also.
    Can any one provide right solution.
    thanks in advance.....its urgent as client requirement.
    regards,
    Amit Awasthi.

    Hi Amit
    You must select the green star for the correct answer, in order to close the thread.
    You may also select the yellow start for the helpful answers, in order to award points for those who helped you. See the blog below for more details:
    How to close a discussion and why
    I can see that most of your old threads are still open, therefore, I'd like to ask you to review and close them, by selecting the correct answer.
    BR
    Caetano

  • Create inbound delivery for same material with multiple batches

    Hi Experts,
    An ASN( advanced shipping notification) contains multiple batch numbers for same material or line item.An IDOC has different segments with batch numbers but in SAP while creating Inbound delivery(VL31N) only batch number ( segment) get posted automatically in SAP other batches are need to post manuaaly.
    I am using IDoc type : Delivery03 ,Message type: DESADV
    How to resolve this problem?
    Thanks,
    Anil

    Hi Anil,
    Welcome to SCN for your first post. Did you check with your functional people about this.
    Regards,
    Madhu.

  • Multiple physical inventory document active for same material-storage locat

    hi experts,
    I am using transaction code MI31 for creating physical inventory document for all materials at a particular warehouse(storage location). User is selecting direct generation of of PI documents in the transaction. If by mistake he presses execute button more than once system is creating as many copies of physical inventory documents. As per ERP system logic it sound very wrong to have multiple physical inventory document active for same material-storage location ( no batches or special stocks exist ).
    Is there a message number or some standard setting to prevent such occurrence.
    regards
    Avinash

    Hi,
    Syetem won't create again physical inventory document, if allready PI is active for the same part number,  plant, storage location & batch/valuation type.
    Check your PI documnets
    Regrads
    KRK

  • Muliple inspection plan for same material and same usage

    Hi,
    I need to create multiple inspection plans for same material with same usage.during the inspection lot creation i need to select any one inspection plan.
    In standard SAP its not possible.Any user exits available for this..
    Regards,
    S.P.Selvathangam

    Dear Selvathangam Palanisamy ,
                                                       My Dear Shayamal is absolutely correct and we are corrently using this SAP facility. You can create 'N' number of inspectio plans for a material and then whenever the inspection lot will created ( Thru a process order or Manual) then you will get the Inspection Lot Status 'CRTD' (Created mode) then you have to select your Inspection Task list manually by two way...
    Either go to QA02 and then select it from the list of multiple plans.
    Or you can directly go from QA32 ...select your inspection lot row and directly click on the Inspection Lot icon to go directly to the inspection lot window to slect the Task list.
    Further there is no need to remove the Automatic Assignment from the QM View of the Material Master as if there is only one task List then system will automatically assign the TASK LIST, if you deselect it then you have to select in every case.
    Thanks

  • For same material hoe to avoid and do QI to UR as well as qaulity trecodin

    Hi Guys ,
    I have a senario like for same materialagainst production order ,  i want to post the quality stock in QI stock and after result recording and quantity transfer to UR mvt 321. for same material some time i want to post direct UR avoide 321 mvt but Quality inspection and result recoding we want . kindly suggest the way how to do step by step .and what are the master data & config required to do ?
    regards
    s

    Dear Sush,
    you can use "Early Inspection for a Goods receipt".
    You have to activate inspection types 03 and 04 both in QM material Master.
    once a process order is released , the system creates two inspection lots (inspection lot origins 03 and 04).
    you can post a partial quantity to UR.
    refer this very helpful link.
    http://help.sap.com/saphelp_470/helpdata/en/60/64cae6d9b311d1953a00a0c930e04c/content.htm
    regards,
    Amol

  • Unit Conversion issue for same material with Diff KPI

    Hi,
    i have a report with multiple key figures which form a structure.
    Unit conversion for this report and all the key figures are defined at report level.
    Below are the settings in place
    Source currency:    Data record from target
    Target Currency:    From variable ( Input variable in BeX report)
    Conversion  factor: Dyanamic Determination of conversion factor
                                   Using Reference Infobject if available otherwise use T006
                                   Reference Infobject: 0Material
    Issue: For 1 Key figure conversion to TO is happening, however for other Key figure conversion is not happening for the same material.
    Note: Conversion to TO is defined in BEX settings for Info object 0material and stored in DSO UOM0MATE.
    Why for same material some key figures convert to target unit correctly and not the others?
    See the attached screenshot. Sales Quantity is convertin to "TO" while Volume third party shows figue in"ERR" for same material.
    Thanks
    Nayab

    Hi,
    Following reasons cause to your issue,
    1. Unit Conversion is not maintained for that particular material  in source system Material itself, so that  conversion data data may not updated in DSO (UOM0MATE).
    2. For particular transnational data record key figure value don't have any base unit or units measures, that case also  you may get that error.
    Request check the transnational data in your InfoProvider and 0Material Master data and DSO data (UOM0MATE) . Correct the data based on that.
    Check the Master data test in RSRV for 0Material, if any SID generations was missed or not.
    I hope this can be help to find the cause of error , based on that you can resolve problem.
    Thanks & Regards,
    Leela Krishna.

  • Two Purchase Info Records for Same Material & Plant Combination

    Hi,
    2 Purchase Info Records are there for Same Material & Plant for 2 Different Vendors & Net Price is maintained in both Info Records
    1. Material M1 - Plant 1000 - Vendor A - Net Price Rs.4
    2. Material M1 - Plant 2000 - Vendor B - Net Price Rs.3
    Vendor A is Regular Vendor
    (Tick as Regular Vendor is his Purchase Info Record)
    It is observed that Rs.3 is picked up for Costing Purposes
    Requirement is that - Net Price within Pur. Info Record of Regular Vendor i.e Rs. 4 must be picked up always for Costing Puposes.
    Is this possible???
    What Logic system uses while picking up the Price in case where there are 2 Pur. Info Records for same Material & Plant???
    Thanks & Regards...
    Ameya...

    Hi,
    1. Material M1 - Plant 1000 - Vendor A - Net Price Rs.4
    (Validity - 28.04.2008 To 31.12.2008)
    2. Material M1 - Plant 1000 - Vendor B - Net Price Rs.3
    (Validity - 01.01.08 To 31.12.2008)
    Thanks & Regards...
    Ameya...

  • Multiple web catalog files for same rpd

    Is there any way to run multiple web catalog files for same rpd in OBIEE?

    Why do you want to do that? Why not merge them into one? You run seperate presentation servers againt the same RPD.
    Regards
    John
    http://obiee101.blogspot.com/

  • Cost Estimation Through Two PIR valid for same material

    Hello Everyone
    I am trying to costing strategy with PIR (Purchase Info Record). Just to check whether its working right or not i have only choosen sub strategy 'Effective Price from Quotation'. My problem is we have got more than one PIR for the same material from different vendors (both have valid dates). My first question is how system will calculate if both PIRs for same material is valid with different prices.
    My expectation was that system should pick up the price from PIR which has regular vendor flag ticked in PIR master record but this is not the case. System is picking up the price from the other PIR although i don't know the logic. I am observing system is picking the lower price (as i tested two materials) in both cases. Can anybody guide me how can i make sure that system picks up the price from PIR which has regular ticked or can anybody suggest something elsethat which is right sub strategy to use for PIR?
    Thanks in advence

    Hi Young Sun
    The link really helped me a lot to understand the process how system is picking up price. We don't use source list and quota requirement. I have noticed that system will not consider regualr flag tick in PIR for costing unless you you configure at backend in
    Material Logistics->Purchasing->Source Determination->Define Regular Vendor
    Once i have activated that tick system is working fine and picking up the price from regular vendor flag. If regular vendor is not ticked system will go vendor with lower price.
    @Imdad: Thanks for your kind help as well and input.
    Many thanks again.
    Regards

  • How to Maintain two different prices for same material in different qty?

    Dear all,
    How to maintain two different prices for same material in different batch quantities in purchase order(ie.,info record)?
    (Vendor is supplying quantities in 2 different batches & also in different prices)
    Expecting valuable reply.
    Jeyakanthan

    In a PO you can create 2 items, and each item can be maintained with a different price in the conditions.
    In info record it is not possible to have different prices for the same period, except for scales.
    so if you have a price of e.g. 2 USD for 1000 kg and 1,90 USD for 2000 kg then you can maintain this in scales, but you still have to have 2 items in the PO so that each one can individually find its price.
    Alternative you can create contracts (as well with more than one item) to reflect the different prices and batches.

  • How to arrive same day two difference prices for same material/customer

    how to arrive same day two difference prices for same material/customer.pls give the solution
    thanks in advance
    Aravinthan.K

    Hi
    This is possible through some careful customization
    In your condition table you need to bring the field PRICE LIST
    That is customer/ Material/ Price list
    That is customer  ABCD / Material X / Price list 01---Price is Rs 10
    That is customer  ABCD / Material X / Price list 02---Price is Rs 20
    The condition records to be maintained like this
    So same material and same customer with price list 01 price is Rs 10 and with  price list 02 price is Rs 20
    Now in sales order you will find  price list field in item details SALES B tab
    Through incompletion log you can make this field as an mandatory field
    Now in sales order same material and same customer according to the price lists different price is picked
    In img-sd-basic functions-Maintain Price-Relevant Master Data Fields--here you can define different price lists
    Regards
    Raja

  • Maintain diffrent prices for same material

    How to maintain different prices for same material (assume that the price of the the material is varying frequently that to with high margin)
    But my req is need to maintain N  values for same material .Is it possible??
    For ex,
    3 Jul Purchasing 20 Pc with 20 INR
    5 Jul Purchasing 10 Pc with 10 InR
    7 jul Purchasing 20 pc with 2 Inr .... like that price is changing freq. But i dont want to use MAP .Whatever price i purchased will be used for cost calculation.Any suggestion??
    Message was edited by:
            velmurugan s

    Hi,
    If your Purchase price changes frequently and you want your MAP or STD price to match the purchase price then you will have to write a simple ABAP that will read the last price paid for each item and automatically post an MR21 to change the MAP or STD price to that price.
    I have seen this used in other implementations and it is the only real way to get the MAP or STD price to relate to the last price paid.
    I would question why you need to do this  though as the two "prices" are designed to be different and there is no accounting reason why they should always be hkept in line.
    Steve B

  • 2 Prices for same material

    Dear All
    Is it possible to maintain 2 prices for same material.this is the requirement from our client  the base price some times has 2 values based on the price on which the product is purchased from supplier.
    Can we maintain the credit limit at ship to party level.
    Regards
    Mohammed
    Edited by: Raeesuddin Mohammed on Jan 20, 2011 8:21 PM

    Yes.
    -If you are talking about Purchase price, you maintain 2 diffrent info records in ME11 for each vendor.
    - If you are talking about selling price you maintain 2 pricing records in VK11.

  • GATP/ATP Check for Different Order Types for same material

    Hi :
    I have a material code X for which 2 different type of Sales Order (Say A and B )needs to be created.
    For Sales Order Type A the atp check needs to be done in APO through GATP for material code X.
    For Sales Order Type B the atp check needs to be done in SAP R/3 ECC 6.0 through availabilty check functionality for same material code X.
    It is not possible to create seperate material codes to carry out atp/gatp check seperately in R/3 and in APO.
    In real time the atp and cumulative atp position should be same in R/3 and in APO.
    Please let me know solution for this issue.
    With Regards
    Ashish Gupta

    Hi Ashish,
    Can you share with us as to how you were able to solve this issue. I have a similar issue like yours and I am totally clueless as to what needs to be done..
    My scenario goes this way:
    I have to modify the Schedule line dates for a GATP material according to a newly created date which I calculate based on the Route Schedule id (VL51, VL52) and display the same in the Sales Order schedule line items.
    Also can I get a new set of schedule line dates from the APO system for a date which I calculate based on the Goods Issue date - VALW-AULWE in any exit using a FM or a BAPI?? so that I can get these dates and populate the same in the Sales Order Schedule line??
    Thanks in advance,
    Susanth