Need a single point of view on date selections for Delta and Full load IP's

Hi Experts,
Every year we are facing issues on date selections for data extraction, for example the Delta or Full selections for particular IP is like 2005 to 2008 , in this situation, for the year 2009, this IP is picking 0 records as the selections are upto 2008 only.
My requirement is, I need to check the selections of all the IP's in the system and want to change on need base if the selections are getting expired instead of going and checking manually to each and every IP as the system is having around 3000 IP's, which is a tedious job.
Guys, please let us know if there exits a Table/Program or any other way to check it.
Inputs appreciated.
Regards
Nandu

Hi
Persistent through module RSSM_SHIP_PSEUDO_DVERSION_WRI
Primary table RSLDPIOSH
RSLDPIO Links datasource to infopackages
RSLDPIOT InfoPackage Text Description
RSLDPRULE ABAP source code for InfoPackages
RSLDPSEL Hardcoded selections in InfoPackages
RSMONICDP Contains the request-id number by data target
RSPAKPOS List of InfoPackage Groups / InfoPackages
http://help.sap.com/saphelp_nw70/helpdata/en/2e/20d704d45be7458582cdfcc5487090/frameset.htm
Hope it helps

Similar Messages

  • Delta and Full load from a single Delta ODS

    I have delivered 0DS 0GT_DS01 that is being loaded from R/3 as a delta update. This ODS is then loaded to a delivered InfoCube 0GT_C01 as a delta.
    My question is this, can I create update rules and a Infopackage to do a full load from 0GT_DS01 ODS to my custom ODS ZGT_DS01?
    I kind of remember from my BW310 class that in release 3.5,  if I have an ODS to InfoCube Delta update all other updates from that ODS must be a delta also.
    Regards,
    Mike...

    Siva,
    I created my update rule without a problem.
    I created the Infopackage with my ZGT_DS01 ODS at the target, the update mode as FULL and I saved the InfoPackage. After SAVE I went to the drop-down menu, Scheduler ==> Initialization For This Datasource and there is a Delta present.
    The Infopackage works OK when I run is from RSA1, but when I put the Infopackage in Process ChainI get and error "Delta upload is only possible after successful initialization". What I see in the Manage screen for my ZGT_DS01 ODS is a request for a full load followed by a request for a Delta.
    Any Ideas why the infopackage works in RSA1 but not in a process chain?
    Regards,
    Mike...

  • Need a JavaScript to enable/view Multi-line option for Text fields.

    Hello All,
    I need a JavaScript to enable/view Multi-line option for all the Text fields in PDF Form.
    Assume that I have a PDF form of Fields from F1 to F100 and it contains 25 Checkboxes, 25 Combo Box and 50 Text Fields. Now i need a javascript for which i need to enable Multiline for only Text Fields. So Is there any JS for which i can enable the Multiline option for only Text fields and not for ComboBox or Checkbox.

    Hi timo,
    Thanks for your help. iam trying to use the iteraor approch to do this. but i don't know how to fetch the data entered in the form that was built by the iterator. can you please tell me .
    thanks

  • No data selected for printing  message no 8I000

    Dear All
    At the  time of printing J1INCHLN certificate getting error NO DATA SELECTED FOR PRINTING MESSAGE NO 8I000 , where we have data in vendor's A/C and TDS is deducted at vendor's A/C .
    Some vendor under the same section allow us to print the certificate, but the in case of few vendors we r
    facing the problem.
    As we need to send the same to vendors help is needed.
    VG.

    we sorted out the issue

  • No data selected for printing in production server t.code J1INCERT

    Dear Gurusl,
    I am facing a issue to tds certificate printout through t.code J1INCERT in production server. My client has booked the invoice in the month of march 2011 & remittance, bank updation is done in the month of 30th Apr. 2011. But while taking the printing out it the error No data selected for printing 8000I. So I need some permanent solution.
    For invoice booking fiscal year is 2010 & remittance, bank updation it is 2011.
    Regards
    Sachin Patil

    Dear:
               Check whether you have selected the relevant tax types for invoice posting while posting the vendor invoice. If its correct then Vendor Master data, Section/Business Place code Address data. Check tables in SE11
    J_1IEWT_CERT_N
    J_1IEWTCALID_N
    J_1IEWTNUMGR_N
    In these tables section codes might have been maintained directly. Please check these for any discrepancies.
    Regards

  • Message No: 8I000 - No data selected for printing

    Dear All,
    I need inputs for resolving this.....please help me out...
    Issue Description:
       When i am doing J1INCERT, for one company code it is working properly...but for one specific company code it is giving the error that No data selected for priting (message no 8I000) that to specifically in one client only....where for the same company code in another client it is working.
    I've checked all the settings, and tables which are client specific, and finally i didnt succeded in finding the route cause of the error.
    Can someone have any idea why this error is coming.....and can give some insight abt this to resolve.
    Thanks
    Raja

    we sorted out the issue

  • When I set black point on windows, the image switches between blank and full image, why?

    when I set black point using windows, the image switches between blank and full image, why?

    I set black point with alt button down while I move sllider. When black
    dots show, I stop and back off a bit.  That's the normal result. Normally a
    white screen appears until I release the alt key. In my case, sometimes the
    screen goes from white to full image. It's not all the time. I view my
    power and ram use as I work and it doesn't spike when this happens.  It's
    as if the alt key command is not holding.  I've used both alt keys with
    same results.
    Thanks for responding.  I hope you have some ideas.

  • Create withholding tax data subsequently for reconciled and open items in c

    Hi All,
    Mine is a US co code and I have a  vendor for which invoice and payment documents are posted. After posting the invoice i found that the vendor is subjected to classic withholding tax which i did not calculate when posting invoice, making payments.
    Now i have changed the vendor master data with relevant withholding tax details.
    I know the program RFWT0020 allows us to create withholding tax data subsequently for reconciled and open items in cases where vendors or customers become liable for withholding tax with a tax rate of 0 %.
    It is not working out for me.
    Can any body help me on this.
    Thanks in advance.

    Dear all,
    by se38 --> report documentation, You can read carefully the following:
    The auxiliary program makes it possible to convert both classic and extended withholding tax data. However, with classic withholding tax, ONLY VENDOR data can be converted.
    In addition, the program enables the withholding tax code to be changed for reconciled and open items with existing withholding tax data. For this, the tax rate of the existing withholding tax data as well as the tax rate of the new withholding tax code must be 0%. The new withholding tax codes are taken from the customer or vendor master data. In the case of extended withholding tax, the withholding tax code is only changed if the related withholding tax categories are the same.  The withholding tax base amount is not changed by this procedure.
    Recreating or changing the withholding tax data requires that the program first be executed for INVOICES and then executed for PAYMENTS in a subsequent step.
    I hope this helps You.
    Mauri

  • How to go about multiple inclination with different data selection in Delta

    We have to copy large amount of data ( more than 42lak of recodes) selectivly from on ODS to other ODS. in delata load ( BW 3.5 enverioment)
    I thought of loading data in slices through delta loading with selection condition.
    step 1> Do The initialization with selection condition as for calyear =2001 ( Init without data transfer )
    step 2> Take the delta load .. it will take all delta record with same selection
    step 3> Now I want to do Initialization with selection condition as for calyear =2002
    step 4> take the delta now it will take delta for year 2001 and 2002 both Right ?
    Here what problem I am facing.. while doing 2nd time initialization it prompt me to delete the last  initialization request form scheduler menu.
    if i delete the last request .. will it take the delta  for previous initialization selection  and new initialization selection. ?
    Please advice how to go about multiple inclination with different data selection in delta loading.
    Looking forward your reply.

    Hi,
    step 1> Do The initialization with selection condition as for calyear =2001 ( Init without data transfer )
    step 2> Take the delta load .. it will take all delta record with same selection
    step 3> Now I want to do Initialization with selection condition as for calyear =2002
    step 4> take the delta now it will take delta for year 2001 and 2002 both Right ?
    You are correct with this scenario normally. The message you mentioned normally comes up when you open a infopackage and don't change the selection first or in case you have overlapping selections with an already done init.
    regards
    Siggi

  • Need help getting new printer hp deskjet 3520 setup for eprint and wireless

    need help getting new printer hp deskjet 23520 stup for eprint and wireless

    Hi Pastorlee7,
    I see that you're having problems setting up your printer.  I would take a look at the document below.
    Hp deskjet 3520
    Let me know how it goes.  

  • Upon transferring to the cloud, all my previous mail says the same date, except for today and yesterday.  The rest says it came in on the same date I had to replace the hard drive 3 years ago.  Totally stumped.  It didn't do this on my mac...

    Upon transferring to the cloud, all my previous mail says it entered my box on the same date, except for today and yesterday.  Everything else says it came in on the same date on which I had to replace the hard drive 3 years ago.  Totally stumped.  It didn't do this on my mac...only when I moved.  I have bad feelings about being to fix this...Any suggestions?

    Get the new keyboard at eBay and replace by yourself may be cheaper way, though you're required higher skill and well know about MacBook Air.
    http://www.ebay.com/sch/i.html?_from=R40&_trksid=p2050601.m570.l1313.TR0.TRC0.H0 .Xmacbook+air+2011+keyboard&_nkw=macbook+air+2011+keyboard&_sacat=0
    https://www.youtube.com/watch?v=gLbasVD69xo

  • Hey guys need help regarding iTunes U. My school is moving for iOS and Mac in the classroom and I have been appointed Junior Administrator for the schools technical department and integrating these devices into the classroom.

    Hey guys need help regarding iTunes U. My school is moving for iOS and Mac in the classroom and I have been appointed Junior Administrator for the schools technical department and integrating these devices into the classroom.
    I have an appointment with a director on Tuesday. I want to demo iTunes U. Problem is I have never used it before and have no idea how to set it up and even if I should sign up.
    Please help any ideas regarding iTunes U and how I should direct the meeting tomorrow.
    Please please post here.
    Thanks
    Tiaan

    Greetings fcit@!A,
    After reviewing your post, it sounds like you are not able to select none as your payment type. I would recommend that you read this article, it may be able to help the issue.
    Why can’t I select None when I edit my Apple ID payment information? - Apple Support
    Thanks for using Apple Support Communities.
    Take care,
    Mario

  • Asking for data connectivity for settings and Photo gallaery. Why?

    Asking for data connectivity for settings and Photo gallaery. Why?

    sounds good to me. suggest it here!
    apple.com/feedback

  • Wat should be data type for  negative and decimal values (eg: -1.2222)

    What should be data type for  negative and decimal values (eg: -1.2222)

    Hi
    U can use the data type DEC while creating the DOMAIN and in the domain u  have sign check box at the left corner of the screen, click that check box , u can assign negative values for the field which refers this domain.
    REWARD IF HELPFULL
    Anees.

  • - Differences between delta and full uploads of transactional data

    Hi All,
    This is with refrence to the loading transactional data into the cube.
    I know that delta and full uploads of transactional data into the cube is done for the following reasons.
    1. Delta upload allows change in transactional data (add/delete/modify) for the particular period selected but this is not the same in full upload.
    2. Full upload takes less time compared to delta upload for the particular period.
    Please let me know whether my understanding is correct. Otherwise, please explain these two concepts with examples taking loading transactional data  into the cube.
    Regards,
    Ningaraju

    hi,
      full upload is done to avoid more time to load the data .if u use initilallization then it will take more time to laod the same amount of data when compared to full load.
    however your statement about the delta is correct.
    u can perform delta only after sucessful initiallization.
    so
    1.first full load(to avoid more time0
    2. inirtilallization with zero recored.
    3. delta
    regards