No costs visible for statistical WBS element

Hi,
The followin steps are the setup:
- Project with a statistical WBS element and a network below
- Create a PO with Account category "Fixed Asset"
- Fill in a fixed asset, but also a (statistical) WBS element (put field 'project' optional in customizing)
- execute a MIGO to book costs
Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
kindest regards
bert

Is this necessary?
Because in the end I want to book these costs as actual costs on my fixed asset...

Similar Messages

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • Purchasing for statistical wbs element

    Hello SAP experts,
    Could you please advise if it is possible to create a purchase requisition with regard to a statistical WBS element? If so, please let me what the assignment category should be used, so both cost center & wbs element number could be used.
    Thanks!!!

    not possible
    statistical means not account assigned - no commitments (PR) can be raised against these

  • No costs visible statistical WBS element

    Hi,
    The followin steps are the setup:
    - Project with a statistical WBS element and a network below
    - Create a PO with Account category "Fixed Asset"
    - Fill in a fixed asset, but also a (statistical) WBS element (put fields 'project' and 'network' optional in customizing)
    - execute a MIGO to book costs
    Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
    HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
    Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
    kindest regards
    bert

    It is normal

  • Report: Statistical WBS elements with assets assigned to them - actual cost

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Hi
    There is not a standard report which can cater to your requirements. You need to develop one.
    You can take the refernece from CNS41 report for development. Some of the fields you need are PRPS-XSTAT for statistical WBS and will have to use tables ANLA and ANLC to fetch asset master data.
    Regards

  • We want to post actual cost through statistical WBS elements.

    when we do the posting on Costcenter assigned to a Statistical WBS element (2nd level), I was in the opinion that, the actual cost posted on the Costcenter of statistical WBS (2nd level) will reflect to the top WBS element (which is non-statistical in 1st level).
    But, I cannot able to see the actual cost in the 1st level WBS which also a Billing element (with this, finally we want to  do the Resource Related Billing).
    So expalin me how to bring actual cost posted on the costcenter of a Statistical WBS, to top WBS element which is non-statistical.

    U can book the actual cost from Procurement Cycle or by direct Invoice posting using FI transaction.
    Procurement Cycle:
    When you create PR or PO user Account Assignment Q or P and maintain WBS element. When u do GR or service entry actual cost is captured on the Project (WBS element).
    Using FI Transaction:
    When there is no PO and to book the cost u can use  F-43  to post actual cost (via Invoice) and mention WBS element.
    U can check the Actual Cost using Line item report CJI3 or S_ALR_87013532.
    Venkat

  • Reports to see cost in statistical WBS elements

    Hi,
    Is there any standard SAP report available to see cost in statistical WBS element?
    Aman

    Closing the thread. Got answer.

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • Project System Cash Management in combination with statistical WBS element

    Hi,
    within  a customer project, we have to solve the following issue:
    Customer runs projects and statistical projects in combination with internal orders.
    We want to use the PS Cash Management for planned and actual payments.
    With statistical projects we have the following problem:
    Invoice and actual payments will be processed with the transaction CJFN.
    Actual payments are shown only on the internal order (transaction CJIA), but not on the statistical WBS element.
    We want the information about the actual payments with in the project system reporting (S_ALR_87013574).
    Projects, not flagged as statistical will deliver the expected results.
    Many thanks for your ideas, to solve this problem.
    Steffen

    are u posting to some other cost object also. normally they wud have to be posted to a COPA also with the cost element being 11 category.
    the wbs will receive the statistical posting, so there needs to be a real object also.
    see whether the real object is getting derived.
    the system is nt finding the real object and trying to post with the WBS in real, but since its statistical, the error.
    any other calrifications. plz post.
    regards
    anantha

  • PM Budget - Statistical WBS element

    Hello,
    My intention is monitoring the PM budget for a plant by linking every PM order to a statistical WBS element.
    After posting on the PM order and performing costplanning via CJ40 i get a overview in transaction: S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %.
    However. Not every PM order shows up in the report. I thought it had something to do with the moment you assign the WBS element to the PM order but this didn't prove to be a valid statement (before or after actual postings on PM order).
    I can probably find out by extensive testing, but i was wondering if anybody knows if there are specific rules regaring the usage of statistical WBS elements in PM orders? More specificaly, when the assignment will NOT work and the actual costs will not show up in S_ALR_87013543.
    Kind regards,
    Peter Hageman

    Settling was done towards a Costcenter. The WBS element used is a statistical WBS element, that only can be used for reporting purpose. how the settlement rule is set up doesn't matter in this case.
    Issue no longer exists.
    Solution was evident. WBS element in the order was stored on the location tab, and in order to use CJI3, you have to link it on the additional data tab...

  • Statistical WBS elements-Budgeting and Use

    Hi Guys,
    Need some KT from you all regarding Statistical WBS Elements.My queries are
    1.Can a statistical WBS element be budgeted? If yes how are the Budget  distributed to those below.
    2..If a level 2 WBS is marked statistical and it has 3 WBS under it which are Acc asignment element then how is the budget distributed.
    3.can you provide some good example of the use of Statistical WBS element?
    Thanks in Advance
    ssk

    Hi Shourya,
    1. As mentioned above Statistical WBS can be budgeted like any operative project and the budget can further be divided into lower level WBS elements and Availaility Control can be activated on these.
    2. Again as stated above the budget distribution is normal. For ex- If a level 2 WBS is statistical and level 2's underneath that are real WBS.
    3. We can use the Statistical WBS for capital projects. For ex- We can assign a Statistical WBS in Master record of AUC for Availability control of budget for Capital spending. And then when we create a PO with Account Assignment category A with same AUC, budget control (Availability control) is activated through the statistical WBS.
    Someone might ask but why we want to use WBS for budget control why not I/O? It's because it provides more visibility over different departments (divided by structure). And via this process we can see all our PO's on AUC directly from Asset Explorer (AW01N).
    Hope it helps.
    Thanks,
    BS

  • Statistical WBS Element - do we need to set as Account Assignment Element?

    Hi,
    I would like to know if I define the WBS element to be statistical (statistical ticked in Control tab) and would want to have posting.  Do I need to set it as account assignment element?  (I noticed system is not allowing me to post if I do not set it as account assignment element).  I want to make sure the actual cost would be be posted to the WBS element as the WBS element should just be statistical in nature.
    Please also confirm if I always need to specify actual cost center posted if the statistical field is ticked PRPS-KOSTL.
    Thanks!

    Yes, so the account assignment should always be ticked if I want to post actual to STATISTICAL WBS Element.  Now I would like to confirm if I always need to specify actual cost center posted if the statistical field is ticked PRPS-KOSTL.
    Also, I understand that if I run CJI3, for statistical Actuals posted, its value type will be 11 - Statistical Actual instead of 4 - Actual.
    Thanks!
    Vivian

  • Line item report on Statistical WBS element.

    Hi All,
    I need to extract Line report on statistical WBS element. I tried CJI3 and end up with the message No costs, revenues or finances were selected.
    can some one help me on this.
    Thanks and Regards,
    Vinod

    Hi,
    Please check below:
    Table PRPS: Select OBJNR and pass to RPSCO and check if any value exists there. Note down the Value type, Year.
    While in CJI3, please check if any dynamic Selection is active, remove all.
    if mutliple selection shows any exclusions, remove all.
    Posting Data: Remove the values. (Or put from 01.01.1900 to 31.12.9999)
    Select the standard SAP Layout (Starting with 1SAP)
    Value type=11 should be selected by default (Ensure it is checked)
    Hope it helps!
    Thank you and Regards,
    Varshal Kachole

  • ACTUAL COSTS:REPORT WITH STATISTICAL WBS AND ASSETS ASSIGNED TO THEM

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
        Assets assigned to each WBS
              Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    An statistical WBS element is an SAP object . Statistical means that you need another object to post the cost or income, let's say,an asset.
    Actual costs are the real postings you have in an object, coming from MM, SD, GL ... (just the contrary as budget or planned values).

  • Change WBS's statistical WBS element

    Hello;
    We use the SAP PS module. I create the WBS and WBS's statistical WBS element (XSTAT) set the true.
    I need the change WBS's statistical WBS element and set the false. But WBS's statistical WBS element read only on the screen.
    How is change WBS's statistical WBS element?
    Thanks.

    Hello
    Set a substitution rule for a particilar proj profile/type, to set the WBS as statistical on saving.
    Sarang

Maybe you are looking for