Open a Sales Order on statistical WBS element. How?

Hi,
I tried to open a sales order on a statistical WBS element but the system shows me an error saying I can't open it because the WBS is statistical.
Could it be a problem of Controlling Area or Operating Cornern?
Is there a setting that allow me to open a sales order on statistical WBS element?
Thanks,
Diego

To best of my knowledge, WBS is only a search criteria if u wish u take a doc as ref. in sales order. this ref. will happen only if the previous doc is prepared with ref to WBS. may be at header or item level. but i wonder how will it track the doc if there are multiple WBS in previous doc. u can assign WBS in account assignment tab page.
I wonder if i have helped u with my answer.

Similar Messages

  • COPA - Multiple Sales Order with one wbs element.  COPA does not reference

    COPA - Multiple Sales Order with one wbs element.  COPA does not reference of reference of sales order.
    Hi All
    Currently we are in process of implementation of project related to Club Service for one of the client.
    Concept of this project is - there is "X" company engaged in supporting the different shared services for their client e.g. Client IBM - Shared Support Services of IBM is
    u2022     IDM
    u2022     Software Installation
    u2022     Help Desk
    u2022     Maintenance
    Co.. "X' is performing these services for IBM.    So for Co. "X" - IBM is one engagement. Like this way Co. X is performing such activities for many companies e.g. microsoft, HP, ABN AMRO etc.
    Objective - Get the consolidate report from COPA (Customer wise/services wise/sales order wise e.g. IBM/HelpDesk/10002/10).
    We propose a solution to create a project for each engagement and with WBS element. Each WBS element of different services e.g.
    Project IBM Inc.  100.100
    WBS Element    100.100.IDM 
    WBS Element    100.100.SoftIns
    WBS Element    100.100.HelpDesk
    WBS Element    100.100.Maintainance
    For this engagement (IBM), we are creating a sales order with line items (for services) and account assignment is WBS element.  In a sales order, there may be two lines for one services.   In a particular period, there are many such sales orders for this engagement... Milestone billing/period billing is used depending upon the services rendered.
    Now Cost Object will be WBS Element. So cost and revenue will posted to WBS and from this it goes to COPA.  In a month of May 2009 two - sales order is booked with three different line items with account assignment is WBS element.
    Sales Order Line Item No.....Item                  Account Assignment                      Revenue
    10000          100     IDM      100.100.IDM              1000
    10000          200     HELPDESK      100.100.HelpDesk              2000
    10000          100     Maintenance      100.100.Maintainance         3000
    Another Sales order booked with two different line items
    10000          100      IDM     100.100.IDM          3000
    10000          200      HELPDESK     100.100.HelpDesk          4000
    Cost will be booked directly against WBS element.
    In sales order level, there is no profitability segment, as cost object is WBS element.
    Billing, revenue will be posted directly to wbs element, from this revenue and cost of sales goes to COPA.
    Now in COPA,
    1.There is only one line for WBS element ex. 100.100.IDM with revenue 4000 (combing both the sales order)
    2.There is only one line for WBS element ex. 100.100.HelpDesk with revenue 6000 (combing both the sales order)
    3.There is only one line for WBS element ex. 100.100.Maintainance with revenue 4000
    In above case 1 & 2 we will not have reference of sales order and sales order line item in COPA table. There is only one line for this.  So we can not have reporting to sales order level.
    Is there any way by this the reference of sales order and sales order line will come in COPA for case 1 & 2.
    Please help in this issue.
    Regards
    Abhay Dev
    Ph:- 91-22-67782229
    Cell:- 91-9819175185

    Hi,
    For these case (multiple materials with different characteristics); have you consider going to next level of WBS Elements. Meaning; lets say currently you are assigning WBS "Engineering (which is a level 2 WBS)" to all the items in SO. Instead under "Engineering" create 2 or 3 level 3 WBS Elements as E1, E2 etc and assign them 1:1 to your sales order line items. This would eliminate the exit as welll as complex development option. And also will let you get all the data in COPA and in turn you can pull to BW as well for reporting. Just a thought.
    Regards
    Sreekanth

  • Sales order assignment to WBS element

    Can somebody tell me Where a Sales order is assigned to a WBS element?
    I am aware that it is assigned to WBS element Field in Item details>>Account assignment Tab. But in this tab page on Sales Order screen, I am not able to see WBS Element field. I am able to see the WBS element field for FERT items but not for DIEN.
    Can somebody tell me where exactly is this done so that I get the WBS element field populated in SO?
    Rgds

    Hi
    Hope the following will fulfill u r requirement
    1) What is WBS element?
    2) What is the Tcode to get to that screen?
    3) What is the need and pupose of WBS element?
    4) Do we happen to work on Functional module during our implementaion project? 5) In what scenario/situation we will be working on WBS?
    WBS is nothing but Work Breakdown Structure. It is mainly used in Project System (PS) module. Tcode : CJ20N
    For any project defined we must have atleast one WBS. Within this WBS we can have networks. Networks are nothing but the series of activities. Material are used to perform the activities.
    To explain in detail just consider one example:
    Govt of india wants to have Roads to be build through out the india. So Project can be defined in sap as “Connectivity”.
    WBS can be roads within different states like Roads for Gujarat, Karnataka etc.. i.e. WBS Gujarat, WBS Karnataka etc.
    We can define different networks for these WBS like Road Between Ahmedabad to Surat or Between Bangalore to Belgham.
    For this network we can have many activities like Land selection, Land Preparation, Road Building, Final finishing etc etc.
    Hemal’s example was a good example. Project Systems comes into play only when the industry’s business is based on projects like… Construction companies, Engineer to Order scenarios. You may not see anyone using PS module for retail business. As Hemal explained in that example, you have a main project which is broken down into WBS elements. You can use the TC CJ20N to create the project and the WBS elements. Each WBS may have mutiple Networks associated and each Network may have multiple Network Activities as explained in the example by Hemal.
    On the Sales Order, if your client is implementing PS module, you may have to attach the Sales Order to the WBS element it belongs to. WBS element is nothing but a bucket where all the activities belonging to that particular part of the project are captured. In the example, WBS Gujurat will tell you how many Sales Orders were created for the Gujurat sector, howmuch was spent on raw materials, what’s the currect stock ([roject stock) available. How many Production Orders have been confirmed and howmany of them are getting confrmed in the future. How many invoices have been generated or how much revenue has been generated for that particular sector. How many deliveries have been made, what deliverables are still not accomplished.
    So as you can see, PS is the center stage for all the modules that are being implemented like FI/CO, SD, MM, PP in this example. You can have cost centers and work centers defined. You can also have profit centers assigned at the plant level and get reports on varius selection criteria.
    In a complete cycle of PS, like in reality, you initiate a project, you confirm/release the WBS/activities as per requirement, you execute the project and you close it.
    One cannot initiate an activity unless it has been released by the project manager. Everything is accountable here and every dime is counted and at the end you know howmuch did you spend or make on each sector (WBS). Dont get confused with the term sector here… I am using it just for the explaination purposes.
    In one typical example, the company I was working with until not too long ago, had Deliveries from the Project (TC: CNS0). We never used VL01N. We used CNS0 to create a delivery and then used VL02N for confirming the picking quantity for the already created delivery document.
    I hope this should help you at least a bit. I’m not a PS consultant so I may not know a whole lot but trying going to CJ20N and you will see a lot yourself.
    PS concultants are one of the highest paid consultants. Their supply is less and so is the demand. They are expected to understand real world business processes very well and they are generally the center stage of a project.

  • Sales Order creation with WBS Element

    Hi Friends,
       I tried to create a sales order with each line item being associated with a WBS Element based on the material. But when i try to save the document its throwing an error saying that 'WBS element <elt_name> is not a billing element'. What does this mean?
    Prompt replies would be rewarded.
    Thanks in advance.
    Tamilarasan.

    Hi Tamilarasan,
    You must select the checkbox of "Billing element" in the frame "Operative indicators". If you don't see this check box, you must display it from SPRO PS customizing => Define field selection for WBS structures.
    Regards

  • Statistical WBS Element in Sales Order

    Hi,
    I tried to post a sales order with a statistical WBS element but the system shows me an error saying I can't open it because the WBS is statistical (Message CJ070).
    Could it be a problem of Controlling Area or Operating Cornern?
    Is there a setting that allow me to open a sales order on statistical WBS element?
    Thanks

    are u posting to some other cost object also. normally they wud have to be posted to a COPA also with the cost element being 11 category.
    the wbs will receive the statistical posting, so there needs to be a real object also.
    see whether the real object is getting derived.
    the system is nt finding the real object and trying to post with the WBS in real, but since its statistical, the error.
    any other calrifications. plz post.
    regards
    anantha

  • Availability control on statistical WBS element

    Hi everybody,
    The issue deals with <i><b>availability control on statistical WBS element</b></i>.
    <u>Part 1</u> : I released 25000 as budget (CJ32) for a <b>statistical WBS element</b>.
    Availability control is active for this WBS element.
    We made a good receipt (MIGO) for 20000 on an AUC (asset under
    construction) - so we get the value as statistical value on the WBS
    element -, then invoice verification (MIRO) and finally the asset
    transfer (ABUMN) from asset under construction to fixed asset.
    On this statistical WBS element we get +20000 (MIRO) and -20000 (ABUMN).
    The problem is that the amount that is used for the availability check
    is 0, instead of 20000 as you can check !!!
    We set a budget on the statistical WBS element in order to have the
    availability check ... and this is not working as the system in the described case shows 25000 as available but for me we should have only 5000 (= 25000 - 20000).
    <u>Part 2</u> : This is working perfectly (I get the expected value for available) when we use a <b>"real" WBS element</b>, put an expense on it, then run the period end closing tranction CJ88 in order to transfer the cost on an AUC, and finally run CJ88 again in order to transfer from AUC to fixed asset.
    Did anybody already encountered this problem with statistical WBS element ? How did you solve this (we would like to keep our statistical WBS element) ?
    Thanks in advance for your help.
    Benjamin

    Hi Benjamin,
    Pl go through the link below :
    http://help.sap.com/saphelp_47x200/helpdata/en/3e/a98337dd34ca76e10000009b38f8cf/frameset.htm
    I have not faced this but as far as I remeber for AUC Statistical assignments have some limitations.
    Any specicfic reason for keeping the WBS Statistical? Are you able to see "0" zero on this WBS in CN41.
    Regards,
    Sudhanshu
    PS: Assign points as a way to say thanks.
    Cheers,
    Sudhanshu

  • Project System Cash Management in combination with statistical WBS element

    Hi,
    within  a customer project, we have to solve the following issue:
    Customer runs projects and statistical projects in combination with internal orders.
    We want to use the PS Cash Management for planned and actual payments.
    With statistical projects we have the following problem:
    Invoice and actual payments will be processed with the transaction CJFN.
    Actual payments are shown only on the internal order (transaction CJIA), but not on the statistical WBS element.
    We want the information about the actual payments with in the project system reporting (S_ALR_87013574).
    Projects, not flagged as statistical will deliver the expected results.
    Many thanks for your ideas, to solve this problem.
    Steffen

    are u posting to some other cost object also. normally they wud have to be posted to a COPA also with the cost element being 11 category.
    the wbs will receive the statistical posting, so there needs to be a real object also.
    see whether the real object is getting derived.
    the system is nt finding the real object and trying to post with the WBS in real, but since its statistical, the error.
    any other calrifications. plz post.
    regards
    anantha

  • No costs visible statistical WBS element

    Hi,
    The followin steps are the setup:
    - Project with a statistical WBS element and a network below
    - Create a PO with Account category "Fixed Asset"
    - Fill in a fixed asset, but also a (statistical) WBS element (put fields 'project' and 'network' optional in customizing)
    - execute a MIGO to book costs
    Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
    HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
    Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
    kindest regards
    bert

    It is normal

  • PM Budget - Statistical WBS element

    Hello,
    My intention is monitoring the PM budget for a plant by linking every PM order to a statistical WBS element.
    After posting on the PM order and performing costplanning via CJ40 i get a overview in transaction: S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %.
    However. Not every PM order shows up in the report. I thought it had something to do with the moment you assign the WBS element to the PM order but this didn't prove to be a valid statement (before or after actual postings on PM order).
    I can probably find out by extensive testing, but i was wondering if anybody knows if there are specific rules regaring the usage of statistical WBS elements in PM orders? More specificaly, when the assignment will NOT work and the actual costs will not show up in S_ALR_87013543.
    Kind regards,
    Peter Hageman

    Settling was done towards a Costcenter. The WBS element used is a statistical WBS element, that only can be used for reporting purpose. how the settlement rule is set up doesn't matter in this case.
    Issue no longer exists.
    Solution was evident. WBS element in the order was stored on the location tab, and in order to use CJI3, you have to link it on the additional data tab...

  • No costs visible for statistical WBS element

    Hi,
    The followin steps are the setup:
    - Project with a statistical WBS element and a network below
    - Create a PO with Account category "Fixed Asset"
    - Fill in a fixed asset, but also a (statistical) WBS element (put field 'project' optional in customizing)
    - execute a MIGO to book costs
    Now when I run the cost report for this project using transaction CJI3 then I do NOT get the costs visible on this statistical WBS element.
    HOWEVER when I do the same steps, but instead of putting a statistical WBS element I put the network (next to the fixed asset) then I do get the costs visible.
    Is this normal or do I have to change something in order to get the costs visible for my statistical WBS element?
    kindest regards
    bert

    Is this necessary?
    Because in the end I want to book these costs as actual costs on my fixed asset...

  • Line item report on Statistical WBS element.

    Hi All,
    I need to extract Line report on statistical WBS element. I tried CJI3 and end up with the message No costs, revenues or finances were selected.
    can some one help me on this.
    Thanks and Regards,
    Vinod

    Hi,
    Please check below:
    Table PRPS: Select OBJNR and pass to RPSCO and check if any value exists there. Note down the Value type, Year.
    While in CJI3, please check if any dynamic Selection is active, remove all.
    if mutliple selection shows any exclusions, remove all.
    Posting Data: Remove the values. (Or put from 01.01.1900 to 31.12.9999)
    Select the standard SAP Layout (Starting with 1SAP)
    Value type=11 should be selected by default (Ensure it is checked)
    Hope it helps!
    Thank you and Regards,
    Varshal Kachole

  • My customer is looking for a comp. open (unbilled) sales order line report

    Hello:
    My customer wants a listing of open (unbilled) sales order lines.  List of everything they have ordered and do not have a bill for yet.  That seems to be spread between 'Open' Sales Orders - see VA05 (no outbound delivery created yet) AND outbound deliveries that have not yet been billed - see VL06O with Billing Status not completely processed.
    How can both of these be merged into one? 
    Is there something else that can show this TOTAL picture?
    Thanks.

    Hi,
    To show all picture you can go for z report
    Take data from table VBAK,VBAP,LIKP,LIPS,VBRK,VBRP,VBFA
    Kapil

  • Report for Billing Document/sales order against project/WBS/Network

    Hi Experts,
    I want to see the Billing Document/Sales Order for Network/WBS in the projects.
    Also want to see the cost transaction against the WBS and Network.
    Suggest report which can show the details of the Sales Order/Billing Document against the WBS/Network.
    Thanks and Regards
    Ram Kalel

    Hi Ram,
    Please check standard TCODE like
    CN45N for Order list
    CN54N for sales n Distribution documents
    CN55N for sales document items
    Thanks
    Sunil

  • Settlement to cost center posted for statistical WBS element

    We have the following scenario
    Statistical WBS elements with assigned Cost center posted for actual postings
    Network assigned to statistical WBSE and settlement rule on the same WBSE
    On settlement run CJ88  the network costs are transferred from network to Cost Center posted in the WBSE.
    Issue:
    While analysing the active availability control the assigned value is doubled. This happens only of the networks are settled. System considers the Actual values from network + Statistical value from WBSE to caculate the assigned values.
    Simulation details as under.
    SP-SET-02-3  (wbs element)
        COSS 2011 11 0007101000     0001240704 KOAO D INR                 100.00  INR
        NWA 500000002408 0010
            COSS 2011 04 0007101000     0001240704 KOAO O INR                 100.00- INR   S  -- does not contribute to assigned value
            COSP 2011 04 0007101000     0001240704 COIN D INR                 100.00  INR
            COSP 2011 01 0007101000     0001240704 KPPP D INR                 100.00  INR   M   -- does not contribute to assigned value
    Hence the assigned value gets doubled and eating up the budget.
    Anyone encountered similar issues pls share the possible solutions.

    Hi Mohit
    It is against SCN's rules to post the same discussion thread twice. You have already posted a similar question in the below thread. Please refrain from doing this and close one of the threads.
    Initial balance upload of revenue GL accounts with wbs
    Regards
    Sowmya

  • Change WBS's statistical WBS element

    Hello;
    We use the SAP PS module. I create the WBS and WBS's statistical WBS element (XSTAT) set the true.
    I need the change WBS's statistical WBS element and set the false. But WBS's statistical WBS element read only on the screen.
    How is change WBS's statistical WBS element?
    Thanks.

    Hello
    Set a substitution rule for a particilar proj profile/type, to set the WBS as statistical on saving.