Oracle Projects WBS and Construction Industry Projects

Hi, I would like to hear from anyone who can share example Work Breakdown Structures for Construction projects (e.g. high-rise commercial buildings, etc).
We currently have a process where we manipulate a Bill of Quantities in a spreadsheet and upload that in a summarized format (as a series of Trade Packages,etc) to Oracle. There is then a process to create the WBS and the Budget.
My query is around whether anyone has an alternative WBS-style for projects in a construction-oriented company. Because our WBS is based on Trades, it can get extremely long and unwiedly. Example below:
0.TP0430 Concrete Supply & Place
0.TP0431 Precast Concrete
0.TP0610 Reo Supply
0.TP0620 Reo Fixing
etc, etc.
thanks,
Mike.

Hi
When your invoice method is WORK (Time & Materials) you must run the process GDR (PRC: Generate Draft Revenue) before you run the process GDI (PRC: Generate Draft Invoice). That is because only the GDR process is calculating the billing amount and creates the RDL (Revenue Expenditure Line) for the Expenditure Items. Later on the GDI process select all un-invoiced RDLs and group them into the invoice lines.
When your invoice method is based on Events then GDI picks all un-invoiced events. It is not required that events will be included already in a draft revenue. Therefore, in that case the order you run the GDI & GDR processes does not matter.
Dina

Similar Messages

  • IDOC - Projects / WBS and Status

    Hi Expert
    In my testing I find that only realesed (I0002) project travel througth the master system into the host system.  Someone knows or has a list about the status of Project / WBS that the IDOCs takes to transfer by the master system???
    Thanks in advance.

    Hi Expert
    In my testing I find that only realesed (I0002) project travel througth the master system into the host system.  Someone knows or has a list about the status of Project / WBS that the IDOCs takes to transfer by the master system???
    Thanks in advance.

  • Library project errors and imports of projects using them

    So this is something that I have put up with in FB for a long time now, but I decided to try doing some research today to see if there is a workaround as it is very annoying. Unfortunately I couldn't find anything.
    I attempted to file a bug/feature request, but it turns out that for some unknown reason FB is the only Adobe application that gives a link to another url (http://bugs.adobe.com/flex/) and, today at least, the link is dead so I have to post here instead.
    The problem is with library projects (which I love by the way). I use them a great deal and for more than just creating standalone APIs. As do many others, I like to have the core of many of my cross-platform projects in a library so that I can create other ‘harness’ projects for different runtimes and use the same bulk code. This way I can just write code in each master project that is particular to that runtime be it air or web or whatever - this is a great bit of functionality that I would really miss were it not there.
    As a result of this workflow however, I am often working in the library project directly in order to update all versions of a project. The problem arises when there is an error in the library project. When this happens, all the projects reading from the library lose all linkages to the swc and as a result the problem tab fills up with hundreds of problems that don’t exist, because as far as those projects are now concerned the swc no longer exists.
    Now I understand why this happens but surely FB could be made to understand what is going on and override (what I assume is) the compiler’s behaviour, and just not display these errors.
    This whole thing is exacerbated by (and may not even be that big a problem where it not for) the fact that I am forced to turn off 'build automatically' due to the 4.7 crash bug that has been reported here numerous times. Because of this I tend to write large chunks of code between each compile so I don't instantly know what has broken.
    Please save the feature that I enjoy so much by either getting FB to deal with the situation better or by fixing the crash bug so I can use ‘build automatically’ again… or god forbid… fix both!! I can dream. J
    If anyone has any good tips regarding this please let me know.
    Many thanks,
    James

    Can I then delete the project from the hard drive (as it's now in the library?) or will that delete the whole thing forever?
    That depends on how you did import the projects.  If your images are referenced they might still be stored in the previous projects, but if your library is managed, then it will be save to delete the projects you already imported.

  • Problem Linking Windows PP Project Assets and Mac PP Project Assets

    I know we are not the only people experiencing this, but perhaps someone has found a solution.
    We have both Windows and Macs running Adobe Premiere Pro CC.  When you save a project on one platform, the other platform won't link the files.  Thanks in part to Windows antiquated DOS volume naming system that makes every volume have a drive letter. 
    Is there a work around to having to search out the files that Premiere can't find due to this problem?
    Any help would be appreciated.
    We save all the files on a shared Facilis 48TB Terablock.
    Mark Underkofler

    This is not an answer but an addition to this problem. I am not trying to hijack but i feel my issues are very similar to what BMercer was having.
    I just recently bought the new mac pro with 500gb ssd internal , 6 core, 64gb ram and dual d700s.
    I upgrade and purchased CC after i was pretty well convinced that CC was the way to go for this computer as opposed to CS6.
    Fo how much i spent on this new computer and new CC subscription i feel this should be functioning better.
    I have noticed when i have very basic files on the timeline(1920x1080, no effects) they are still dropping frames or i cannot scrub through them smoothly. As mentioned by BMercer for a machine capable of handling 6k these DSLR files should be pretty simple.
    I am trying to do a time lapse for a client and I am having extremely slow load times. This is more difficult but i still believe it should be loading way faster then this.
    About 2000 frames of raw DSLR photos simply compiled in AE then opened the sequences in PP and placed them into the timeline. This is taking about 45-60min to render the timeline. I have to do this because scrubbing or trying to play goes nowhere.
    This i could accept as well except for when i look at the stats of the computer in the activity monitor and Istats the CPU maintains a 60-70% idle, the GPU stays very low and the max ram combined usage is about 15gb(memory pressure doesn't even show on the graph). So I would assume from this there is nothing i can see that is "holding" the computer back.
    I have the exact same MBP as BMercer and i am having far less issues with doing the exact same files rendered from a relatively slow thunderbolt external drive.
    Is this a setting issue? Or is this something we can expect to see an update to?
    Sorry again for tagging below you but i felt our issue and answers may be similar.

  • Deleting project clips and photos after project is completed

    I recently discovered that I have numerous clips and photos in iMovie from previous projects. Is there a simple way to remove these clip etc. from iMovie? Currently I am highlighting each clip and hitting the delete button. It is taking me ages to delete all these clips. If any one has a simpler method, please help.

    you can delete the unused (unused in any Project) portions of any Event by "Move event to trash" and then you get a box that asks you to"Delete" or "Delete unused". Pick the later, if you are sure you never want them again. If you Delete the whole event your project that uses those clips (Movie) will never run again, the Project just tells the computer where to find the source clips music etc.
    You can do this with every event and you may need to dump them from another area in iMovie, rejected clips maybe. And then you need to dump your trash, but once done you will free up huge amounts of HD space.
    roger

  • How to download and upload long text for project, WBS , Network,

    Hi all,
    I have two isssues.
    1) I am extracting Projects, WBS , Network , Network activity and network activity element from a SAP 4.7 system using bapi's
    BAPI_PROJECTDEF_GETDETAIL
    BAPI_PROJECT_GETINFO
    BAPI_NETWORK_GETINFO
    BAPI_BUS2054_GETDATA
    I am able to get all the details except long text. I want to know how do i extract the long text other than getting it manually by using select_text and Read_text Function module, is there any bapi to achieve this.
    The reason why i am not using Function modules Read_text and Write_text is, object name( TDNAME ) value stored in STXH table for project, wbs and network are the project, wbs and network itself so i dont have any issues with this but the TDname value for activity and activity element are completely different ( Routing number and counter is stored respectively ) which i am not getting as the part of the bapi(BAPI_NETWORK_GETINFO) output.
    2)  I have to upload the extracted Project and it sub object data to ECC 6.0 system , i am able to achieve this by using BAPI's BAPI_PROJECTDET_CREATE, BAPI_PROJECT_MAINTAIN and BAPI_NETWORK_MAINTAIN. I am not able to load the longtext for the same, is there any way to load the long text .
    All help will be greatly appreciated and rewarded.
    Thanks & Regards,
    Rajanidhi Rajasekeran.

    I don't think there is any BAPI to do it.
    We are doing it by read_text & edit_text . required fields for text name can be fetched by following select
      if not e_activity[] is initial.
        select aaufnr aaufpl baplzl bobjnr b~vornr
          into corresponding fields of table t_longtext
          from afko
            as a
        left join afvc
            as b
            on aaufpl = baufpl
           for all entries in  e_activity
           where a~aufnr = e_activity-network
           and a~aufnr is not null.
      endif.
          txtname = wa_longtext-objnr.
          replace c_nv in txtname with sy-mandt.

  • 1 project definition with several wbs elements or several project definitin

    Hello
    I need projects as account assignment elements in CO (when entering vendor invoices for costs). Should I have 1 project definition with all projects /wbs elements underneath, or should I have 1 project definition uniquely defined for each project/wbs element? Some projects are not settled to assets und construction, some projects are settled to assets und construction.
    kind regards
    Arjan

    Arjan
    I don't think you can have Projects as account assignment objects. You can have WBS element as account assignment object.
    One alternative I can suggest, if you want to see project costs at higher level instead of breaking down the project into many WBS elements. Create a project with one WBS element only and use that WBS element as account assignment object.
    It is only possible to have a project with one or more WBS elements. I don't think you can define projects within projects.
    letus put it this way assume WBS elements are projects within a project. But make sure all the WBS elements are related to one project
    Hope you are clear now.
    Thanks
    Prasad

  • Report with project name and stock

    Please suggest a report to get project (WBS) and stock

    Hi,
    Please refer transaction CN52 /52N, for material components of projects.
    You can also refer transaction MBBS for the list of materials of the projects.
    Hope this will solve your problem.
    Regards,
    Rakesh Pradhan

  • Capital project WBS settle to AUC individually

    Dear all experts,
    please help me on the following issues.
    i am working on a capital project. Investment profile is defined and assgined to the project profile.
    the top WBS is T-09-001
    the second level WBS are T-09-001-01,  T-09-001-02,  T-09-001-03,  T-09-001-04, T-09-001-05 for example.
    the third level WBS is T-09-001-05-01.
    i do the test settlement when the project status is release. (i didn't maintain the settlement rule.)
    the result is that every single WBS is settled to a FXA (the numbers are generated automatically)
    for example
    T-09-001-01 to  FXA 1000/40047/0   30000CNY
    T-09-001-02 to  FXA 1000/40048/0   40000CNY
    T-09-001-03 to  FXA  1000/40049/0  40000CNY......
    i am not sure if it is correct or not, because it's my first time to deal with capital projects.
    if i want to settle all the sub-WBS to top WBS and the top one settled to AUC, how can i do it.
    i manually maintain the settlement rule for all the sub-WBS to top WBS and settle the project again.
    but the result is the same. i don't know where the problem is.
    please tell me how to do it or how to settle the capital projects in most cases?
    thanks a lot.
    judy

    Below was something which we had done in such case:
    1. Created a substitution rule against the WBS element, if the level of WBS >=2 substitute the Investment profile with 'Blank'. With this when ever you create a project and save it or call the substitution from menu, system would retain the investment profile on level 1 WBS and when project is released only 1 AUC is created for the project which is on level 1 WBS.
    2. Settle all other lower WBS to it's parent WBS and you can implement OSS note 211324 - CJB1: Strategy for settlement to superior WBS. Refer the below link about how this works:
    http://wiki.sdn.sap.com/wiki/display/PLM/ModificationnoteforStrategyforsettlementtosuperiorWBS
    Doing both the above, you would create only 1 AUC (on level 1 WBS) and finally settle all lower WBS to level 1 WBS and from there system would then automatically settle the costs to AUC fixed asset.
    Regards
    Sreenivas

  • Project lite and project online

    I just heard about project lite license and seems pretty cool, we are small company with a PMO, so, I suppose I still need a valid Project Online license for the PMO and then the rest could be just project lite licenses?
    Follow me on Twitter
    levalencia Blog

    Esteban V M --
    The Project Lite license is specifically for team members, and allows them to manage tasks, to collaborate, and to submit timesheets.  Your project managers and members of the PMO staff will need Project Online licenses.  I would also strongly
    recommend that you purchase licenses for Microsoft Project Professional 2013 for your project managers and for your Project Server administrators as well.  Hope this helps.
    Dale A. Howard [MVP]

  • Projects not showing up between project pro and project web app

    I have projects that I created using project standard.  Now that I have a subscription to project pro for office 365 and project online, I wanted to import these projects. If I use project pro and save a project to office365, it doesn't show up on
    the project web app side.  Yet I know it is there because if I try and save with the same name it says it can't because it already exists.  Similarly, if I create a project on the project web app side and then try and open it using project pro, it
    errors out and won't open it. 

    Hi,
    If I understand well, you had standalone projects that you'd like to import on Project Online?
    Then you just have to open MS Project (connnected to your project server) then SAVE AND PUBLISH it. Be sure to fill any required information such as project custom fields.
    What is the error you get while opening Project Pro? Has the project been correctly published from PWA (not just saved, and no error message in the queue)? Then is Project Pro connected to your project server?
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Save project file and event file?

    When archiving a project, should I save the project file and the event file? All of my raw footage is saved on it's origional media.
    Cheers.
    Tom

    You want to save the Project folder contents and the contents of any Events used within the Project. You can also do this from the Project library itself by control clicking on the Project itself and selecting Duplicate Project. Make sure to attach an external drive for the archive.

  • Project Start Date – modification after project was saved.

    I created new project with  a start date 01/April/2015 and saved it. Next, I change the start date to 14/April/2015 in the setup.
    However still in statistics windows I see the start date as 01/April/2015. Additionally, every new task has start date 01/April/2015.
    Could you please advise me how can I change that?
    https://social.technet.microsoft.com/Forums/getfile/644409
    MS Project Standard 2013

    Thank you for your prompt reply.
    1.Firstly I set up project start date as 01/04/2015 in Project, Project Information and in File, Project Information and save document.
    2. Afterwards, I modified start date into 14/04/2015 in the same places.
    However, the date in Project, Project Information - Statistics was still 01/04/2015 (please check screenshot).
    3. But finally, after several openings and closing of the document the date in Statistics is correct (hard to say what is the reason).

  • RE:  Oracle Projects Setup and budget

    hello
    iam a new user in oracle projets module and working with construction industry. can u please help me in briefing out the process flow of projects.
    Another query is when iam tring to create Activity Based budget with respect to a project number, iam unable to incorporte the Quantity and Rate in the Budget.
    with regards
    vijay
    email:[email protected]

    If you work for an Oracle Partner (which I assume you do because you've copied and pasted an OPN page above), you can take the boot camp mentioned here - http://education.oracle.com/pls/web_prod-plq-dad/db_pages.getpage?page_id=5001&get_params=p_exam_id:1Z0-511
    Regards,
    Brandye Barrington
    Certification Forum Moderator

  • How to block reusage of archived Project definition and WBS element numbers

    Dear All,
    We have archived our projects using the TC SARA and the Project definition and WBS elements numbers no more exist in tables PROJ and PRPS etc.. When I now try to create a new project, the system proposes the next open number or allows to enter a number which is the same as one of the archived projects. But in our organization we cannot reuse the Project definition and WBS element numbers (even if it is archived) as a rule.
    Can anybody guide me what are the possibilities to block or avoid the reusage of the numbers of archived project definition and WBS elements in a fool-proof way? 
    Thanks and regards

    One Workaround:
    Use T code OPSJ and lock the project coding mask. Doing this you can not use this mask any more.
    But you want to continue using the mask but with different numbers. Not sure how this can be acheived. lets wait for others view
    Regards
    Sreenivas

Maybe you are looking for

  • Scanning to Computer, HP Officejet Pro 8500 Wireless All in one Printer A909g

    I am unable to scan to computer with Win 8.1 using my HP Officejet Pro 8500 Wireless all in one Printer A909g.  I can scan to email.  The system says my drivers and software are up to date.  When trying to scan to computer all I get is a blank scan f

  • Strange Flicker

    This is tricky to explain, but here goes: My friend shot a movie on Super8 and had it transferred to video (sd, interlaced. 29.97). Whereever he spliced the actual film together, the film jumped so the video captured this and at every cut the film fr

  • Computer monitor color inverted

    A month ago my HP mini's monitor started displaying colors inverted (Blue is orange; black is white; white is black). It was bearable for a while because I was using an external monitor, but then my external monitor port broke out of no where as well

  • Bold in text mail

    Hi experts, i have a standard text with a word in bold; i read this standard text with the FM READ_TEXT and set it in table contents_txt of FM  SO_NEW_DOCUMENT_ATT_SEND_API1. The result is that, in the body mail, the characters <H> </> are written; i

  • HT203477 After i burn my project onto a blue ray disk and play it some scenes have bright silver lines flickering around the edges of some items on screen

    After I burn my project from from FCPX onto a blue ray disk, in some scenes ther appears a flickering silver line or edge to some items such as aroiund faces or buildings etc