Outbound Certificate with following business scenario

Hi
My client (components industry) has the following business scenario:
1)     Quality Inspection at Goods-In for raw material
2)     Quality Inspection at Goods-In for semi-finish products
3)     Quality Inspection during Production (first and last PP operation with MIC)
4)     Quality Inspection at Delivery to the customer for the Finished product*
*Finish product contains raw material and semi-finish product inspected in process 1 and 2.
A Certificate Of Conformaty is required to be attached on the delivery with following information:
u2022     Results of point 1
u2022     Results of point 2
u2022     Results of point 3
u2022     Results of point 4
My question is, what is the SAP solution to cope above business scenario taking into account the batch management and serial number are not implemented? or more precisely how the system track and tight the MIC recorded in each stage (goods-in, production, delivery) described above and put together on COC with the corresponding results?
Possibly this topic has been broadly discussed but I am getting hardly confused. Not sure if the batch management is mandatory for this business scenario. If it is needed further details please let me know.
Thank you

Batch managemnet would be required.
You will want to report the results from the batch for point 3, (finished goods inspection), use the certificate functionality of resutls from the production chain to pick up data from points 1, & 2, and report the data from master inspection characteristics from the type 10 inspection lot, (delivery inspection).
FF

Similar Messages

  • Terms of payment - how to cover my business scenario

    Dear experts,
    I am dealing with the following business scenario.
    A Sales rep proposes to the client a term of payment made up od several partial amount; for example let assume 3 partial amounts.
    The Rep proposes to the client a fixed date, representing the date of the first payment that the client has to do and the installments.
    For instance, the client's first date of payment is 1st february and then 1st march and 1st april.
    1st february is determined on the M/AM billling data set as 30 days after actual billing date
    Issue:
    If the actual billing date is not equal to the planned billing date, the result is that the client has to pay the first partial amount in a  date different fronm the one agreed with the Rep.
    Is there any way in SPRO in order to link the installment to other dates rather than to actual billing date? (i.e. planned billing date, custom date field)
    Thanks in advance

    Hi Kalyan,
    ...how to do automate start for a process in CE7.2...
    Create a new message event trigger and a new service interface(WSDL) in the process composer and link the service interface to the event trigger. Now assign the event trigger to the start event of your process as message event.
    On deployment, the EVENT TRIGGER you created is exposed as web service (can be verified in wsnavigator). Execute the web service to automatically start the process.You could have a web dynpro application to execute the web service on click of a button.
    Regards
    Sangeetha

  • How to migrate changed Business Scenarios from Template Project to Solution

    SAP Solution Manager - How to migrate changes in Business Scenarios from Template Project to Solution?
    Our Global ASAP strategy is based upon a Template Project, Implementation Project, Maintenance Project and Solution with Business Scenarios.
    Changes in the Template Project for existing and new Business Sceanarios, etc. are correctly executed. Up till now we have successfully implemented our Template Project and secondly extended our Business Scenarios from 4 to 14. Our 3rd upcoming change will be changes on Business Scenarios as well. These planned changes for the Business Scenarios need to be consistent, possibly without manual intervention.
    During a Proof of Concept (PoC) in our Sandbox (SXB) we have identified a possible serious problem when trying to publish these changes in Business Scenarios in the Template Project to the Solution. SAP Solution Manager (SSM) does not seem to support a scenario where Business Scenarios in the Solution can be refreshed or updated with changed Business Scenarios in the Template Project.
    We have identified 2 possibillities:
    1.     Manual project upgrade
    1.1.     Synchronize the changes for the Template Project normally;
    1.2.     Delete the changed Business Scenarios from step 1.1 in the Solution;
    1.3.     Add the changed Business Scenarios from step 1.1 into the Solution.
    For this scenario we foresee a big problem because all Content and Issues connected to the old Solution Business Scenarios loose their coupling with the Solution.
    For the Content this may not be a real problem because the Content is also available in the Template Project.
    However the Issues are loosely coupled to the Solution Scenarios and therefore need to be coupled manually to these processes.
    2.     Manual changes using Maintenance Project
    2.1.     Synchronize the changes for the Template Project normally;
    2.2.     Publish all changes from step 2.1 in the Template Project
    2.3.     Add all new Content from step 2.1 to the structure of the Maintenance Project;
    2.4.     Relocate Content and Issues when the Business Scenario has been relocated.
    Because SSM does not support this activity we need to delete this Business Scenario first and secondly re-create it again on the correct spot.
    Our question: How has SAP done this in other customer projects?
    We need to have a working solution by the end of March, 2009.
    Best regards,
    Peter Hendriksen

    Peter,
    Did you get an anwer to this question from SAP?
    Rgds,
    Eamonn.

  • BW business scenarios example

    Hello Gurus!!!!
    I have practically implemented the examples from Step-by-Step guide by Fu Fu.
    Now I want to implement some BW related examples. Could anyone pls provide me with some business scenarios or real life example for extracting data ..reporting etc
    Points will be rewarded ..................................................
    Thanks,
    aryan

    Hi ,
    Pls chk this links.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/biw/s-u/sap%20bw%20in%20growing%20landscape.pdf
    http://www.businessobjects.com/pdf/partners/sap/sap_di_fact_sheet.pdf
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/7445d290-0201-0010-70b7-a7bbfe2e5f8b
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/biw/s-u/sap%20bw%20in%20growing%20landscape.pdf
    http://help.sap.com/bp_pharmav1470/Pharma_DE/Pharma_DE/HTML/BW_EN_DE.htm
    **Pls assign points ,if links are useful*
    Regards
    CSM Reddy

  • How to use security certificate with Business service

    Hi,
    Information:
    I need to use a security certificate for connection from Business service to legacy system.
    I have created PKI mapper in WebLogic console, deployed keystore on server and Service Key Provider in OSB.
    I can see can connect the certificate in OSB console through the Service Key Provider.
    I have done Authentication setting in the Business service "HTTP Transport Configuration" as "Client Certificate".
    Problem:
    Now whenever I try to invoke BS, the username, password and security key provider is asked at the prompt. Should not the BS collect security certificate automatically? Again,
    when i put username and password as that of WebLogic sbconsole; the error pops up with following message :
    <env:Envelope xmlns:env="http://schemas.xmlsoap.org/soap/envelope/">
         <env:Header />
         <env:Body>
              <env:Fault>
                   <faultcode>env:Server</faultcode>
                   <faultstring>Failed to process signature.null</faultstring>
              </env:Fault>
         </env:Body>
    </env:Envelope>
    If I don't supply username password and certificate at the time of invoking the message pops up as : "The service requires a digital signature, you must specify a service key provider which has a digital signature credential."
    I think some mistake is done in the above steps, could anybody please clarify?

    The problem was resolved with upgrade to version 10.1.3.4.

  • What is the best way to follow the scenario for Out look integration with share point using SAP Gateway?

    1)what is the best way to follow the scenario for Out look integration with share point using SAP Gateway?
    2)workflow concepts for Purchase order?
    3)Email triggering from out look for an approval process of PO? how these scenario can be best implemented with updated functions in Duet Enterprise.

    Hi,
    I do not have much idea on gateway integration with outlook but found out this document GWPAM Workflow Template which can be helpful for you to start with.
    also you may want to post your question in SAP Microsoft Interoperability forum
    Regards,
    Chandra

  • New business scenario for reapir from customer and sending them to vendor.

    Hello team,
                          We have a scenario where we need to configure in the system -
    We  recieve a material from my customer for repair.We need to send this to my vendor who will repair  it and send them back to Us. On this we  recieve revenue from the customer and pay i pay half amount my vendor for the service.
    We are following above scenario in SAP as
    In the first step
    The production team create a serviece order in IW31 for the material that need to send to the vendor, which was recieved from the customer. When service order is created in the back end a Purchase requisition is created.
    In next step we  created a  PO w.r.f to the above PR and  we need to send this  to vendor on subcontracting so that we can track the material from him after the repair.
    The problem is --- When PR is created automatically during serviece order creation (iw31) we are unable to create Po with Item category L (subcontracting) because PR is not created with L.We are even unable to change L in  PR since it is created automatically at the background.We ried to change the field at document type in spro. But no luck.
    Pls let us know is there any other business process where we can handle this situation or any technical help to change the PR.
    Regards,
    L.chaitanya.

    Hi,
    please work out in this way...
    It can be done Using PM02 and PM03 control keys. Select the operation row select the External button in the bottom u will find Sub con check box u can click it .The prerequisities are create a material BOM in the bom as L item select a row and click the item which will be near to the header cap 2nd tab status/long text click it .Mat. Provision Ind select Lor X if it is not available go to IMG setting.Plant maintenance ->Master Data in Plant Maintenance and Customer Service->Bills of Material->Item Data->Define Material Provision Indicators, K&L will be standrad create S Rework Material,XRework Material from Subcontrmake a tick mark in Recursivity of Subcontracting Component and save it . while creating the material to the operation to be assigned from bom then in the component select the row go to the general button in the bottom then Mat. Prov. Ind will be there select rework material the system allows you to proceed further . save the order then check the PR it will be Account assignment will be F and Item categeory will be L selected automatically.
    Then create PO then do MB1b (prerequsitie the material should have stock)using PO reference( movement type 541) the it will be moved to the vendor stock (check with mmbe)
    Aganist PO Material sent to the vendor .While doing Goods Recipt do with MB01with movement type 101, now u can check the stock in mmbe it will be in storage location...
    Kuber

  • Post a good issue against an outbound delivery with movement type 601 K

    Hello,
    according to my business scenario I need to manage the stock of different vendors into the client's location (plant) at storage location level and I need to post the good issue against an outbound delivery to decrease the stock level.
    Since the owner of the goods isn't my client the item is managed only at quantity level (not value) so I'm not interesed in the accounting document.
    To do it I'm using the functionality related to the vendor consignment stock but I'm not able to post the good issue against an outbound delivery using the movemement type 601 and the special stock indicator equal to K.
    In particular I've tried in two different ways:
    - setup the consignment stock indicator (= K) into the sales item category, but when I post the goods issue the system is not able to find out the right vendor
    - to create a stock determination rule instead of the setting previous described, but the system display an error message (Fld selectn for mvmt type 601 / acct L534200770 differs for Cost center (010) ) even if the accouting is not relevant in my scenario
    Can you suggest me how the system has to be setup in order to cover my requirements?
    Thanks in advance,
    Alessandro

    Hi,
    Please clarrify which material type you are using in this scenario? I suggest you to use material type UNBW (no value updation will be there) and create a material master.  Use special stock indicator K. Proceed with 601K to do GI. Hope it works. Thanking you.

  • Outbound AS2 with Seeburger Adapter

    I am attempting to send a flat file using Seeburger's AS2 adapter. 
    1.  I created a new scenario. 
    2.  In the identifier section of the partner, I added a line for Seeburger | AS2ID | theID. 
    3.  I created a communication channel of type AS2.  It's setup for Transport Protocol HTTP.  I gave a server ip address, port, url, timeout, and no MDN.
    4.  The Receiver Agreement contains the signing key, encryption certificate, and authentication certificate.
    In my scenario, I have a sender agreement and communication channel that is monitoring a directory for the file to be sent.  Then the document is supposed to be sent to our partner.  When I attempt a transmission, I get the following error when I look at communication channel monitoring.
    Message processing failed. Cause: javax.resource.ResourceException: Fatal exception: com.sap.aii.af.ra.cci.XIRecoverableException: SEEBURGER AS2: AS2 Adapter failure # Outbound configuration error: Sender configuration incomplete - perhaps AS2ID missing.., SEEBURGER AS2: AS2 Adapter failure # Outbound configuration error: Sender configuration incomplete - perhaps AS2ID missing..
    Sending failed. [2/19/09 6:14 PM]
    Error type: COMPONENT_ERROR,NOT_TRANSMITTED >> Error date: 2/19/09 6:14 PM >> Description: AS2 Adapter failure Outbound configuration error: Sender configuration incomplete - perhaps AS2ID missing.. com.seeburger.as2.AS2Plugin.execute(AS2Plugin.java:321) [2/19/09 6:14 PM]
    AS2 Adapter failure [2/19/09 6:14 PM]
    I am not sure where my problem exists, and hope someone can assist me.  I don't quite understand the error because I have the AS2ID entered in the Party (where I am sending to).
    Larry

    Hi
    Check this link, this may help fixing your problem
    Re: SEEBURGER AS2: 403 Forbidden #
    also
    Re: Seeburger AS2 comm channel problem (B2B) - "perhaps AS2ID missing"
    Regards
    Vishnu

  • Issue with "firstRecord" Business Component method of JAVA Data bean API.

    Hi,
    Following is my use-case scenario:
    I have to add or associate child MVG business component (CUT_Address)
    with the parent business component (Account) using JAVA Data bean API.
    My requirement is: first to check whether child business component(i.e. CUT_address) exists. If it exists then associate it with parent business component (Account)
    otherwise create new CUT_address and associate it with account.
    Code (using JAVA Data bean APIs) Goes as follows:
    SiebelBusObject sBusObj = connBean.getBusObject("Account");
    parentBusComp = sBusObj.getBusComp("Account");
    SiebelBusComp parentBusComp;
    SiebelBusComp childBusComp;
    // retrieve required account.. Please assume Account1 exists
    parentBusComp.activateField("Name");
    parentBusComp.clearToQuery();
    parentBusComp.setSearchSpec("Name", "Account1");
    sBusComp.executeQuery2(true, true);
    sBusComp.firstRecord();
    Counter = 0;
    while (counter < Number_Of_Child_Records_To_Insert)
    childBusComp = parentBusComp.getMVGBusComp("City");
    associatedChildBusComp = childBusComp.getAssocBusComp();
    childBusComp.activateField("City");
    childBusComp.clearToQuery();
    childBusComp.setSearchSpec("City", Vector_of_city[counter]);
    sBusComp.executeQuery2(true, true);
    if( sBusComp.firstRecord() )
    // Child already exist and do processing accordingly
    else
    // Child does not exist and do processing accordingly
    childBusComp.release();
    childBusComp = null;
    associatedChildBusComp.release();
    associatedChildBusComp=null;
    Now the issue with this code is: For the first iteration, SbusComp.firstRecord returns 0 if records does not exist. However from the second iteration, SbusComp.firstRecord returns 1 even if there is no record matching the search specification.
    Any input towards the issue is highly appreciable.
    Thanks,
    Rohit.

    Setting the view mode to "AllView" helped.
    Thanks for the lead!
    In the end, I also had to invoke the business component method SetAdminMode with "true" as the argument so that I could also modify the records from my script.

  • Is there a way to make a self-signed client certificate with keytool...

    Is there a way to make a self-signed client certificate with keytool
    that will install successfully into the personal store in IE?

    hi,
    It is possible to make a self-signed client certificate with keytool and i am successfully using in my dummy application.
    The first thing you need to do is create a keystore and generate the key pair. You could use a command such as the following:
    keytool -genkey -dname "cn=Mark Jones, ou=JavaSoft, o=Sun, c=US"
    -alias business -keypass kpi135 -keystore C:\working\mykeystore
    -storepass ab987c -validity 180
    (Please note: This must be typed as a single line. Multiple lines are used in the examples just for legibility purposes.)
    This command creates the keystore named "mykeystore" in the "working" directory on the C drive (assuming it doesn't already exist), and assigns it the password "ab987c". It generates a public/private key pair for the entity whose "distinguished name" has a common name of "Mark Jones", organizational unit of "JavaSoft", organization of "Sun" and two-letter country code of "US". It uses the default "DSA" key generation algorithm to create the keys, both 1024 bits long.
    It creates a self-signed certificate (using the default "SHA1withDSA" signature algorithm) that includes the public key and the distinguished name information. This certificate will be valid for 180 days, and is associated with the private key in a keystore entry referred to by the alias "business". The private key is assigned the password "kpi135".
    Also please go through the http://java.sun.com/j2se/1.3/docs/tooldocs/win32/keytool.html
    This would help u better.
    bye,
    Arun

  • How manage outbound IDoc with QRFC in SAP CRM 5.O

    Hi experts,
    I want to manage outbound IDoc with QRFC. For doing it I selected the flag Query Processing in transaction WE20. When I run the program QRFC Monitor (RSTRFCM1) the system shows this error message:
    Status is SYSFAIL.
    "[SAP.111.9129] WMSAP Adapter: Missing notification
    - Message type: IDOC INBOUND"
    Can someone help me?
    Thanks a lot in advance,
    Lorenzo

    Hi,
    if you want to find out how to do outbound IDOCs
    with qRFC you can check my new book:
    /people/michal.krawczyk2/blog/2006/10/11/xi-new-book-mastering-idoc-business-scenarios-with-sap-xi
    in one of the scenarios it describes exactly what
    you're looking for (among other things)
    Regards,
    michal
    <a href="/people/michal.krawczyk2/blog/2005/06/28/xipi-faq-frequently-asked-questions"><b>XI / PI FAQ - Frequently Asked Questions</b></a>

  • Reservation with Extended classic scenario

    Hi ;o)
    I'm working at a costumer were we have extended classic scenario. We want to be able to make reservations in the backend if the item is on stock, and we have seen in a solution matrix from SAP that this should be possible.
    The configuration for reservations should be done according to the guides - but no reservations is created when ordering a stock material.
    I was searching on the developer network, and came across a topic, where it was stated that reservations could only be made with classic scenario (or using a BAdI where you switch the extended on and off depending on product category). Do any of you know if this is really a fact?
    Thanks in advance
    Maria Hvenegaard, Denmark

    Hi
    Read this first.
    <u>You can use BBP_CREATE_RES_BACK BADI using Se18 Transaction.
    This BADI You can find in SPRO -> Supplier Rel. Mngmt. -> SRM Server -> Business Add-Ins -> Follow-on document generation -> Reservation in Backend System</u>
    <u>If you want to create reservation, you have first to switch from ECS to classic scenario through BBP_EXTLOCALPO_BADI then you have to implement BBP_TARGET_OBJTYPE badi to determine the criteria to create a reservation in your backend.</u>
    <u>We need to maintian the customising setings in SPRO Transaction.
    Define objects in Back end systems. Maintain the document type EC or ECPO for Purchase Orders and not for creating reservations. Maintain number ranges (RS) and align the same to R/3 or backend systems. In setting up the org plan in the PPOMA_BBP Transaction, the attribute for resevation - Attribute BWA should be maintained too, if reservations are to be created in the backend system.
    Movement Type Accounting Object
    201 Cost Center
    221 WBS-Element
    231 Sales Order
    241 Asset
    Example :
    logicalsystemname\201</u>
    <u><b>Maintain the following Settings in the IMG using SPRO Transaction.</b>
    1.For internal Procurement > 1.Always Reservation for Material types Subjected to inv Mgmt
    2.For External Procurement >1.Always purchase Requisition.
    Note -> The plant that you use to create the shopping cart might not be extended to handle inventory management. Select a right plant which is extended to inventory management and you will see a reservation being created.</u>
    Be aware that:
    - with the classic scenario you can create PR, PO and/or Reservations in R/3, but there is no local purchasing document (except the SC), so all functions around the local PO will not be possible.
    - with the extended classic scenario, you can only create PO in the backend, but a local PO exists in SRM.
    Concerning GR, it is possible to make it in SRM for both scenario
    Hope this will help.
    Please reward suitable points, incase it suits your requirements.
    Regards
    - Atul

  • BusinessProcess_AutoID_Enabling business scenario in XI 3.0

    Hi Friends,
    We are on XI 3.0 with following SP details:
    -SAP_BASIS(6.4) SP14
    -SAP_BA(6.4) SP13
    -PI_BASIS(2004_1_640) SP06
    We are not getting 'BusinessProcess_AutoID_Enabling business scenario ' during scenario configuration in integration builder during tools->transfer integration scenario for integration respository.
    Please suggest if some extra patch is to be applied on XI or AII system. How in general is business content got in XI system?
    regards,
    Ashit

    Applying XI content for auto -id 2.1 to SLD in XI from
    service market place solved the problem

  • Best Practice Business Scenario.

    Hello,
    Can any one please share your thoughts and best industry business scenarios with relevant information/links for implementing SAP GRC AC suite 5.3 with the following components?
    1. SAP ECC with HR, BI and CRM
    2. SAP IDM
    3. Active Directory
    Thanks in advance.
    Thanks
    -Harry

    Hi Harry,
    Implementation of GRC Access Control depends on the system landscape you have in your organization.
    & it can be integrated with SAP ECC with HR, BI and CRM.
    For more information go through with the following link:
    http://www.sdn.sap.com/irj/scn/events?rid=/library/uuid/c0e1549c-6a36-2b10-4f95-bf36ebb10a9a&overridelayout=true
    Hope it will help.
    Regards,
    Mohit

Maybe you are looking for

  • Group calendar on wiki doesn't work but individual calendars do.

    We have 10.6.3 server running as a OD master and I was looking to use the group calendaring feature of the wiki server. I go to the server using a web browser, sign in, and create a new wiki called "test". I then go into settings for the wiki and ena

  • PATH in my .bashrc

    Hello ,I installed Homebrew today and with command line "brew doctor" i got this : brew doctor /usr/bin is in your PATH before Homebrew's bin. This means that system- provided programs will be used before Homebrew-provided ones. This is an issue if y

  • Refresh of Inbox

    Can we refresh our inbox automatically in albpm 5.7

  • Access to file in HTMLDB_APPLICATION_FILES

    Hello, I have uploaded file to HTMLDB_APPLICATION_FILES and now I want to copy data from that file to a table in database. How can I do that? Thanks

  • Query Cache to Derive Summary Data - Advice?

    Good Evening, I am faced with a problem and I was hoping to get a nudge in the right direction.      I have a cache that is storing the status of orders and their respective times they took to process in that status going though our system. I need to