Hi friends,
How do I pay to the vendor before the due date for certain invoice through payment program.
and
How does system calculates discount on that invoice in automatic payment program.
what details do I need to enter to make system pay before due date and calculate discount as per payment terms.

Hi,
Please try this to remove the check box 'Payment per due date' is selected in your FBZP   > Payment method for company code settings. If you have switched off the flag and carried out testing.
Please assign points if it useful
Regards
Ravinagh Boni

Similar Messages

  • F110 bill of exchange: error FZ731 "...requires payment before due date"

    Hi everybody.
    I'm facing an issue that is driving me crazy <:-)
    I want to configure a payment method of type "bill of exchange" (in Spain, "pagaré"). I have several due invoices (due dates: 30/11/10, 31/12/10...), which have this payment method. Some other items are not yet due (30/1/11).
    When carrying out a payment run thru transaction F110, the system asks for the bill of exchange issue date, which I have populated as 30/11/10. At another tests, I have populated as 10/1/11.
    When running F110, the vendor items are then classified as exceptions, with error FZ731 "Pymt method I in the item requires payment by b./exch. before due date", and also message FZ732 "Item not due in 000 - 000 days".
    I think this problem may be motived because the definition of the payment method "I" (company code data) says: Days until due date: 0. But this field is not updatable.
    I've searched the message numbers in the forums, but found no answer.
    Anybody can help? Kind regards,
    Alvaro

    Never mind, I just had to update the Paying company code, fields Bill of exchange due date... > Earliest-lates due date in...days.
    Regards.

  • Payment made to Vendors before due date adjustment of Interest

    Hi SAP Gurus,
    The Practical scenario of the client is like this
    Suppose Invoice is booked on 01.10.2007 for an amount of Rs.100000. The due date for payment is 31.10.2007. But the actual payment is made on 20.10.2007.
    In this situation the Client wants to deduct some interest for early payment which has to be calculated daywise.Assuming that the interest rate is 5% P.A.
    The Interest amount should be calculated as Rs.1774 (Rs.1000005%11/31).
    Then at the time of payment only Rs.98226 (Rs.100000-Rs.1774) must be paid.
    How to configure this scenario in Standard SAP?
    Regards
    V.Krishnan
    (Points assured)

    The Scenario explained is with respect to Vendors and Not Customers.
    Kindly advise in this respect.
    Moreover interest calculation has to be made day wise for different line items
    (ie) for one line item the payment would have been made 10 days before the due date. for another line item the payment would have been made 5 days before the due date. For the first line item the system should calculate interest for 10 days and for the second line item it should calculate interest for 5 days.
    Kindly advise

  • How to define reminder letter before due date

    Dear Expert,
    How to define dunning procedure in FBMP (for tcode F150) for this condition:
    1st reminder letter should be generated 7 days before due date.
    Currently the setting for dunning level is 4 (days in arrears: blank, 14, 60, 180)
    But I confuse how to be set in 'Days in Arrears' for the first reminder letter?(I set blank since could not set as negative, e.g -7 (7 days before due dates)
    Kindly advice
    Thank you.

    Hi
    maintain Denning Level like Below
    Days in arrears            0    7  53   173
    Calculate interest
    Print Parameters
    Always dun?
    Print all items
    Payment deadline      7     7     7   7
    hope it will resolve your issue
    satish

  • Sales Credit Memos, Payment terms and due date for payment

    Hello all,
    does anyone out there know how to get the terms of payment assigned to sales credit memos taken into account when the due date for payment is calculated in the accounting document?  (I know this is a bit puzzling as why should one need payment terms for a credit memo)
    I have looked at SAP notes 17410 et al..but remain unclear re how 'V' is populated in BSEG-REBZG.

    Number of the Invoice the Transaction Belongs to
    For line items which are related to another line item, this field contains the number of the partner document.
    Use
    In the standard system the field is used for:
    o   Credit memos which refer to a particular invoice item
    o   Subsequent invoices for an invoice item
    o   Partial payments for an invoice item
    o   Partial clearings of down payments.
    In the first two cases mentioned, the terms of payment are copied from the cross-referenced invoice item into the item currently being processed. This ensures that items due on the same date are paid together by automatic payment.
    A special rule applies to credit memos which have a "V" in this field.  The due date is determined in the same way as for an invoice. If the field is empty (containing neither a document number nor a "V") the due date is the baseline date for payment.

  • Exam Voucher 74-409 expired before due date

    yesterday I went to prometric testing center to schedule my exam for 74-409 with free voucher print out, the Test Administrator check the voucher number in his system and replied me that your voucher is expired before due date and advise me to contact
    Microsoft.
    My email ID: muzeepk,  on which I received the voucher , please do the needful as soon as possible.
    Thanks,
    Mustansir.

    Please contact your Regional Service Center.
    (As of this very second, that page appears to be broken so perhaps try it again later)
    Jason Warren
    @jaspnwarren
    jasonwarren.ca
    habaneroconsulting.com/Insights

  • HT1657 2 rented movies disappeared before due date when I updated my ipad software

    2 rented movies disappeared before due date when I updated my ipad softawre.  Any way to get them back?

    You will need to try contacting iTunes support and explain and see if they will grant you a re-download : http://www.apple.com/support/itunes/contact/ - click on Contact iTunes Store Support on the right-hand side of the page, then probably Purchases, Billing & Redemption

  • Running Payment Program before Due Date

    Hi Gurus,
    I have a problem.
    I want to run the payment program -Tcode F110- before the due date and I need the document posting date to be the same as the due date.
    How could I sort it out?
    Please help,
    Samuel

    Your requirement can't be fulfilled by standard set-up, because SAP payment run can post with only one posting date in a single run. This posting date will be what you are entering in the parameters, and system will not split payment posting date separately based on Due date. You can group your items based on due date and can pay future due items as well but you can't split your payment posting with different payment posting date based on due date in a same payment run.
    You can possibly do following workaround.
    - Run vendor open item report (T-code FBL1N) and sort it based on Net Due column (if net due date column is not available change the layout to populate it). And decide for items with which due dates you want to settle today. Lets say you want to settle for following due date xx/xx/xxx, xx/xx/xxx1, xx/xx/xxxx2
    - Then you should run three payments run separately.
    Payment run 1 parameters-  Posting Date=xx/xx/xxxx, Next Posting Date=xx/xx/xxxx+1
    Payment run 2 parameters-  Posting Date=xx/xx/xxxx1, Next Posting Date=xx/xx/xxxx2
    Payment run 3 parameters-  Posting Date=xx/xx/xxxx2, Next Posting Date=xx/xx/xxxx3
    Imp: Note that Posting date=Due Date and Next Payment Run Date=Due Date1 in the parameters+
    This will involve more than one payment runs in a day but will satisfy your requirement
    Thanks
    Ranjit

  • Vendors Payment Before Due Date

    Dear All,
    We could like to restric the release of Vendor payment before the due date.
    We feel there is a system in SAP by which it should give a Error/ warining message (pop up) if any payment is made before the due date.
    Do suggest.
    Regards,

    SAP will give you message if your posting date for e.g. is in past or in future, but the next posting date in F110 parameter decides if you can pay some not due items today or not. SAP will not give you a warning message even if the next posting date is 10 days ahead of today's date.
    In the F110 parameter please make sure Next posting date is always the very next day of the payment run date or Posting date and in the Additinal log tab, please check the indicator Due date check
    This user procedure will make sure that payment is never released before the due date.
    But if still you want some system message to pop up, then SAP standard setting I think will not be of great help, you need to use the BTE00001830 (functional module SAMPLE_PROCESS_00001830) which will help group all the not due items in a group, and exclude the entire group from payments. Information about the group will be received by FM in structure C_REGUH and its line items in table T_REGUP
    By Setting the field XIGNO in C_REGUH to the value "X" the entire group of not due items can be excluded from payments. Please take your abaper help
    Thanks
    Ron

  • Payment Stop Before Due Date.

    Dear All.
    I need to know is there any option we have to stop the processing of Vendor Payment against the NON DUE ITEMS.
    Here in my client, normal terms of payment is for 45 Days. Now the users are asking that, if a line item is Not Due as on Date, if by mistake we have selected such item for payment processing, the system should drop a error & stop the processing.
    The requirement is as follows as error message....
                 """ The Selected Item is Not Due"""""
    So, wht i have found out is, by changing the line item layout included the additional fields like:
    Due Date
    Item Due Indicators.
    But, here these are only for the information purpose, which dont have any control over item payment process.
    SO, CAN ANY BODY PROVIDE SOME IDEAS ON THIS, IF SUCH OPTION IS AVAILABLE IN SAP..
             """ LINE ITEM PAYMENT BLOCK IS NOT SUITABLE HERE """""
    Thanks
    Talluri

    Hi
    With my knowledge,  You have choosen the best process ie., brining the due date in the screen layout. even thou, the client required to make the error message, first work out the change of the message type
    or
    there is no such standard process to stop the payment voucher. Either you have to evaluate any routine
    or alternatively last option will be
    you can use the following procedure
    1. Maintain the Vendor Master -> Payment Transactions -> Maintain the Payment Block
    2. Generate the vendor line item daily with due date is "today's" date & select the MIRO document numbers.
    3. Release the documents through MRBR by selecting the above line items.
    This is for your information.
    Regards
    Anilkumar

  • Vendor Payment before Due date

    Is there any setting whereby the system will not allow me to pay the vendor before the due date?
    Or else it will give the warning message for the due date.

    Hello,
    You should set all the dates in F110 correctly.
    (eg: Documents entered up to, Next pmnt date)
    If you want to pay only a few items just for now,
    better to select a long period and edit the proposal (EDIT-> PROPOSAL-> EDIT)
    and select the only items you wanna pay for now.
    Hope this helps!
    Endre

  • Recurrent payment charged before due date. Refund ...

    Hi,
    I have skype premium (1 year).
    Last month I added another subscription for 1 month (recurring payment). I did this on August 08.
    I could cancel it before the due date but today I got charged again (September 5th). I don't get why this is not advised.
    So, I'd like to request a refund but I can't make it because the link is broken. The same happens with Live chat. There is no way to access there. All links are broken.
    If you access here https://support.skype.com/en/faq/FA297/how-do-i-request-a-refund ,
    there is this link to the request form:
    https://support.microsoft.com/skype/hostpage.aspx?language=en&locale=en-us&oaspworkflow=start_1.0.0....
    If you access, you'll be redirected to: http://support.microsoft.com/common/errors/ServerGeneric.htm?httpCode=403&errorCode=
    This link is not working neither: Skype Live Support Link:
    https://support.skype.com/support_selection
    I can see I'm not the only one and other have already posted this in the community forum. There is no support email to send this either.
    I need to request that refund. Please help

    edgard_shipley wrote:
    1. I can´t find where is that information. If it´s not available, how we are supposed to know this?
    When I got the email stating that the subscription was successfull, there is no advise on this.
    2. How can I request a refund now?
    Hello
    1. I'll escalate the point you make to see if the advice confirmation needs further clarification. Thanks for raising it.
    2. This should help:
    https://support.skype.com/en/faq/FA1170/how-can-i-contact-skype-customer-service?intcmp=SN-Mods
    TIME ZONE - US EASTERN. LOCATION - PHILADELPHIA, PA, USA.
    I recommend that you always run the latest Skype version: Windows & Mac
    If my advice helped to fix your issue please mark it as a solution to help others.
    Please note that I generally don't respond to unsolicited Private Messages. Thank you.

  • BE (Bill of Exchange) purchased back from bank before due date

    I have posted BE through either FBW1+ FBW2 or through F-36. Due date is 1 mth in the future. Then i have discounted it through F-33 using bank clearing liab account (credited here and Post automatically only) Settings in OBYK have also been done for Collection, discounting and forfeiture.
    If the BE is purchased back from the bank before the due date, I am not permitted to reverse the BE liab in F-20 as it says that due date is not reached. This is a common scenario with our client and I need to be able to make this work in SAP.
    Please offer me any solution
    thanks

    Never mind, I just had to update the Paying company code, fields Bill of exchange due date... > Earliest-lates due date in...days.
    Regards.

  • Soon expiring of subscript before due date

    I have bought a subscription world unlimited for 12 months.
    I have bought it from November 28 2011, and skype said on my account panel that I can use it until November 25 2012. But I got a message from skype which told me that I have to pay again to buy the new subscription because my old one will be expire at October 1.
    What happen to my 2 months not used yet, and why would I have to pay 2 months before expiry date.

    The Scenario explained is with respect to Vendors and Not Customers.
    Kindly advise in this respect.
    Moreover interest calculation has to be made day wise for different line items
    (ie) for one line item the payment would have been made 10 days before the due date. for another line item the payment would have been made 5 days before the due date. For the first line item the system should calculate interest for 10 days and for the second line item it should calculate interest for 5 days.
    Kindly advise

  • Due date and payment terms data

    Hi All,
    Goodday to you all!
    My client is posting one transfer posting.
    He is transferring the normal customer line items to special GL items through FB01.
    Giving the first lime item posting key as 09 and customer number and special gl indicator
    But after going inside only the Dueon field shows as mandatory and there is no field called Payment terms.
    This dueon field is for taking the baseline date for calculating the due date.
    The payment terms field is optional in both the field status (Posting key as well as GL account field status variant)
    But the payment terms field is not showing while entering the transfer document !
    Can anybody advise me on this /
    Thanks in advance
    Shankar

    Hi Shankar,
    > Goto Tcode OBC4
    > select your field status variant
    > DoubleClick on Field status groups
    > Goto General (with text, allocation) - G001 (incase of standard SAP)
    >Goto payment transactions
    > Click on Req Entry or opt. entry in front of payment terms.