Planning time fence- MRP

Hi Guys:
Can I use Planning time fence if i am using MRP type PD?
what are the settings i need to maintain for planning time fence and how it defined generally , is it a function of leadtime?
Thanks
Kodali

Hi Padmasri :
How to freeze the order proposals if i am using MRP Type PD.
Because , I might run MRP Yesteraday it might have created Planned orders or Purchase requistions and Buyer might have issued purchase order to the vendor.
today i got some more sales order and additional requirements , So when i run MRP today System propose Purchase requistions asking to change the previously created requistions on Previous Run?
Could you explain how to manage this scenarious without timing fence and still using MRP type PD?
Thanks
Kodali

Similar Messages

  • Managing planning time fence ( P1 MRP type ) and firm zone in ME32L

    Hello,
    I want to know if there is or are some documents to know how to manage planning time fence in MM02 and firm zone in ME32L ?
    For me, in ME32L the firm zone is the firmed quantities sent to suppliers but not firmed for MRP so how to manage this easily ?
    Thanks.
    Romeo.

    Dear,
    Firm ZOne in SA, says that that much qty will be procured from that vendor with in that date specified, if not taken the production cost and cost related to that will be paid.
    Now the planing time fence, is the time with in which no change is allowed. Hence if there is any new requirement to that RM, then it will be pushed to outside the time fence.
    Hence if there is a schedule line which is already there and requirement is coved with in that, then your requirement is met, if not system will create a new schedule line in the trade off zone/planning zone.
    I hope you got the point.

  • MRP type & planning time fence

    Hello.
    When I enter MRP type at MM01, error message comes up;
    "The MRP type requires you to specify a planning time fence."
    This check is not necessary for us.
    Please teach me how to deactive this check.
    Thank you in advance.
    Emma S

    Thank you for your reply.
    To Vijay
    I can't use PD because we run MRP on this material.
    I want to know how to prevent these MRP type from requiring Time fence.
    To Maria Nunez
    Firming type of the MRP type is set "0(Planning results not firmed)".
    Both ex-R/3 (Enterprise) and new R/3 (ECC 6.0) are set same.
    But only ECC 6.0 requiring Time fence.
    Any other customise affects??
    To R.Brahmankar
    This errror message (M3/097) is not set at transaction code OCHS, OMT4 and OMCQ.
    If it was set, I would change the message type...
    Thank you and regard.
    Emma S
    Edited by: Emma S on Dec 2, 2008 7:33 AM

  • Planning Time Fence Use with MRP

    Hi,
    I was wondering if planning time fence has use with an MRP type without a firming type. Basically, SAP says it is only used with the MRP contains a firming type. However, i thought the planning time fence is also used with SAP. For example, i can tell MRP to only plan materials outside of the planning time fence. Anyway, just looking for further insight or clarification.
    Thanks, Erik

    for automatic firming ,
    you need to maintain a MRP type related to firming , while running MRP , system will firm the order with in the planning time fence, & based on the firming type, any new requirement system will plan according to the MRP type
    Firming type 1- P1 or M1. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed.
    Firming type 2- P2 or M2:  The system does not create any new order proposals within the planning time fence. That is, the shortage situation is not adjusted within the planning time fence.
    Firming type 3- P3 or M3: Order proposals that lie within the planning time fence are not firmed automatically. The order proposals required to cover the requirements are moved to the end of the planning time fence.
    Firming type 4- P4 or M4: Within the planning time fence, the system creates no order proposals automatically. That is, the shortage situation is not adjusted within the planning time fence.
    Manual firming
    you can firm the planned order in MD12

  • Planning time fence and MRP question

    Good morning,
    We have the following requirement:-
    1. We want the Planning time fence to move once a week (by 1 week)
    2. If we have a schedule line at the end of the Planning time fence, we want this to   move inside the planning time fence (as per step 1)
    3. Put a fixing indicator on anything that falls into the Planning time fence (as per step 1).
    Thanks in advance

    mm

  • Scheduling Agreement & Planning Time Fence

    Hello,
    I read a lot of articles on Planning Time Fence and the MRP Types P1 to P4 that goes with it. And I have tested it out in a Testing Environment.
    But I can't get it to do what I need.
    This is a normal planning with no PTF and MRP Type PD.
    Sometimes we have false requirements that show up in the past due to human error. When this happens, MRP rolls during the night and adds a bunch of deliveries in the past to cover the requirement.
    I wanted to use the PTF to prevent this. Meaning that extra deliveries would get added by MRP but after a PTF and not Firm deliveries. So that once the error is corrected, MRP rolls again and deleted all the extra deliveries it added.
    ** Only P2 and P4 adds deliveries after the PTF, but I need it to act normal on a day to day basis aswell and have MRP create deliveries like the print screen above. To add non-Firm deliveries after the PTF is just in rare cases of human error.
    Not sure if my explanation is clear.
    Patricia

    Hi Patricia,
    The planning time fence is there to stop MRP from making changes to requirements that fall within the planning time fence.
    Your planning time fence is a rolling period which shifts by 1 day each day and is calculated as of the current date. Yesterdays date is passed so it would not make sense for a planning time fence to use a date in the past to start it's calculation.
    Everything that falls before the end of the planning time fence will not be changed by MRP and you will see that all these schedule lines in MD04 will have an * assigned meaning they are firmed for MRP.
    If you manually add schedule lines in the past, the planning time fence will not stop you from doing this. The planning time fence will only stop MRP from making changes.
    By the way:
    If you manually add requirements to the scheduling agreement then MRP will never change these requirements as these are fixed requirements.
    If your customer would add requirements in the past or you add independent requirements in the past and your current stock does not cover the requirements the system will generate schedule lines and will put these directly after the planning time fence with an exception message assigned to them.
    As a side note:
    I always wonder why such questions arrive in the forum as this is something that can be very easily tested in the test environment.

  • Planning Time Fence and Rescheduling Purchase Req

    How to Process the MD04 exception  u201C30 Plan Process According to Scheduleu201D for Purchase Req.
    Please provide me a Step by step procedure with example to Reschedule the Purchase Req with given rescheduling date.
    *Really I am confused with PLANNING TIME FENCE.
    What it does with Planned Order and Purchase Req ?
    Based on the some of threads in SDN, I couldnu2019t come to the conclusion of the terminology behind PTF.
    So could you please provide me an explanation with example will make clear idea on PTF.
    Thanks in Advance.

    dear friend,
    as far as i know, all planned orders that lie in the planning time fence are firmed. that means that they can no longer be changed automatically by the system in the planning run in long-term planning.
    outside the planning time fence, the system creates order proposals as usual according to the shortage quantity and the lot-sizing procedure. once these planned orders move into the planning time fence, they are automatically firmed depending on the how you have set the firming type.
    the planning time fence can be defined per material in the material master record or via the MRP group.

  • What is planning time fence

    in material master we enter planning time fence & in house productiton & plnd delivery time
    explain wirh a example

    planning time fence: basically it is the period in which no changes to the plan happens automatically through MRP run
    inhouse production time: the time required to produce a material in calender days
    Pld delivery time: time required to procure a material if it is procured externally.
    the latter 2 values are of significance in scheduling the delivery dates. inhouse production time for the product  and PDT for the components(sourced externally)
    please explore further in the following link
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm]
    get back in case u need more details

  • Firmed planning time fence

    Hi gurus,
    My business scenario is to firm my planning shop flloor during 60 days.
    To do it I used the planning Type P1. So If there is a requirement during these 60 days the planned orders is proposed at the end of this time fence. But this is the requirement date that is defined out the time fence. I have to begin the production (and so change the shop floor planning) during my firmed time fence of 60 days to respect the planning proposed by MRP.
    Is it possible to achieve my scenario ?
    Thanks.

    Hello Laurent,
    If I've well understood what you want :
    you would keep normal run of P1 for any planned orders which cover a requirement inside the planning time fence, and in the same time, you would get new proposals from the MRP in the planning time fence if the requirement date is outside the planning time fence.
    In this case, it seems me to be a bit difficult.
    The planning time fence is done to take in account the procurement proposal and not the requirement level. Basically, it's firmed the production plan in a defined horizon whatever the requirements could be.
    In anyway, we could imagine a specific program which runs after the MRP with these internal steps:
    . selection of the planned orders which have been rejected outside the planning fence,
    . filtering the selection against the requirement date (keep the date outside the planning time fence),
    . changing the start date of each good planned order and firming it ( & setting an opération code ).
    In my opinion, technically speaking, the bolt-on is very simple but the impacts on the MRP process has to be evaluate for the final users (understanding and maintenance). Moreover, there is the difficulty to determine the requirement origin in some context.
    I hope to be helpfull,
    With regards,
    François-Robert NICLOT

  • MD04 - Planning time fence for materials that are planned externally

    Hi,
    I have to develop a report in R/3 which will pick up values from MD04 (for a particular material/plant combination) and show the output in ALV grid of materials which are not planned in R/3 but APO.
    It should also show the planning time fence.
    For example, if i goto MD04 in R/3 and enter a material-plant combination which has MRP type X0 (external planning), it doesnt show me the planning time fence.
    This value/row has to be picked up from APO.
    Any idea how to go about it and what are the Function Modules I should use or is there any alternative for this ?
    Regards,
    Anand.

    Hello Anand,
    Try looking at user exit in MD04 that can change the values in MD04. Then, check for material-plant type of the order. If it is X0, call RFC to APO function module to read the information you want.
    I have develop before a report in R/3 that read the correct time of an order in APO to be displayed in R/3.

  • HELP: Planning Time Fence Control

    Hi,
    We have a business requirement where we have Firm Purchase Orders and WIP jobs outside the planning time fence (PTF). We then have new demand for the item coming from SO. When we run MRP, the system is extending the planning time fence up to the Need by date of the latest PO so this means there will be no stock to cover the new demand and we are in backorder!
    Example:
    Item: ABC
    Item Leadtime: 5 days
    PTF: 5 days
    Sysdate : 09-Feb-2009
    Firm Purchase Order: 20-Mar-2009 (outside the PTF for the item)
    WIP job demand: 20-Mar-2009
    New SO 5000001252 with schedule ship date 17-Feb-2009
    To cover the demand for SO 5000001252 MRP is suggesting a new planned order for 20-Mar-2009.
    Plan option:
    Profile MRP:Firm Planned Order Time Fence = No
    Overwrite = None
    Append Planned Orders = Yes
    Planning Time Fence Control = Yes
    Has anybody come across this scenario? How can we force MRP to suggest a Planned Order for the 17-Feb-2009?
    Can the above requirement be achieved with ASCP?
    thanks

    Hi
    I guess planning is creating time fence on its own called the natrual time fence. It would take the firm supply and create a timefence based on its date until creating new pl order within that period.
    Please set profile MRP:Create Time fence to No and recheck
    Best regards
    Partha

  • MF50 : Planning table and planning time fence

    HI,
    I use the transaction MF50 as planning table ( in order to do my MPS planning), I use "set firming date" to fix a firming date.
    Now, I want o know if it should possible to reveal a message when we create a planned order within the firming date??
    Thanks for your answer.

    Hi,
    For clarity , I am describing  below the functionlity of Set Firming date is explained as below:
    By setting Manual Firming date , we extend the planning time fence.
    If a planning time fence has been created for a material then the following applies:
    If the manual firming date lies before the end of the planning time fence, the planning time fence is still valid.
    If the manual firming date lies after the end of the planning time fence, the planning time fence is extended until this date.
    All order proposals with availability dates that lie before the end of the planning time fence of the manually extended planning fence are firmed for the planning run, if the materials have an MRP type which contains firming type or firming type 1 or 2
    The system does not automatically firm order proposals for materials that have an MRP type with firming type 3 or 4, even if their availability dates lie before the end of the planning time fence or manually extended planning time fence.
    Please check if this helps you.
    Regards
    Datta

  • Firmimg the orders and planning time fence

    Hi, Pls explain about firming and non-firming and planning time fence while running mrp or mps?what is meant by firming the orders?  i do not know how it work and how can we interpret the reults? pls explain with one example.

    Firming: When an order is firmed , indicates that the Order  no longer needs to be planned in MRP.
                  Order gets firmed, when we change plannde order manually and save .
    Planning time fence: the time period during which if any Order comes it gets firmed subject the Compatible MRP type.
                                    Depedning on whether they need to be firmed or not and when a new requirement is creatd in the planning horizon, How the receipt needs to be planned within the Planning time fence or out side is controlled in the MRP type.
    Regards
    Ratan

  • Planning time fence using a specific calendar

    Hello
    Planning time calculation is using workdays and the factory calendar.
    I have a customer request to have the planning time fence use a specific calendar, not containing holidays and non-active periods. Is there a possibility in ERP to define a specific calendar for planning time fence.
    Rgds
    Pascal

    Dear PPIO,
    This is with ref to your response to the above question. I too have a similar problem.
    We have a factory Calendar (US) that is used on our day to day business. This factory calendar does not include the weekends and public holidays.
    I created a SAP Planning Calendar(DSI) via MD25 but when i ran the MRP it still gives me the result based out of the Factory Calendar.
    I would like to see my MRP to propose including weekend and public holidays.
    If you could send me your id , i could send the screen shots.
    Regards,
    RAjnish

  • Planning Time Fence Value

    Hi Team,
    I would like to maintain planning time fence value in material master. I do not have any clue that how to determine the value for the planning time fence. Some where i read that the planning time fence value will be the interval time between two MRP runs (ie, if i run MRP four days once, 4 days will be the planning time fence). Is this logic work out? Any guidance to determine the planning time fence for the material?
    Thanks

    Hi Mariano,
    Q1: By implementing Time Fence, you are losing flexibility, so this goes against the service level, so is not going to avoid cutting sales. However, sometimes you still need to use a time fence in order to provide some stability to your supply chain (maximize the use of your production capacity, coordinate the component replenishment with your vendors, etc..).
    Your statement is: "By implementing planning time fence, you are losing flexibility".
    "Losing Flexibility" means, if there is sudden sales requirement (Eg: Emergency sale order), accordingly the manufacturing plan will NOT be smoothened. Do you mean this as "Losing Flexibility"?
    For your information, i am using strategy group 40 for my FERT item. The strategy group 40 will be mainly used to smoothen the manufacturing plan according to the sudden sales requirement. Implementing strategy group 40 & planning time fence together for a material will be AGAINST of each other know?
    Coverage Profile:
    Your statement is:
    Q3: As coverage you can use different methods: coverage profile, safety time, safety stock, etc. The coverage profile is a key that needs to be predefined in advance. I will try to simplify the explanation. Suppose that your coverage profile says that you want to have 10 days of target coverage. If you have a constant forecast of 1000 CS per month and you have 20 working days in a month, this 10 days of target coverage will mean that you want to have 500 CS in excess of your forecast. So the MRP will plan to start the month with 1500 CS (1000 CS of forecast + 500 CS of coverage).
    According to you, the MRP will plan for 1500 CS instead of 1000 CS for the month. But for that particular month additional 100 requirement has come as emergency sale order. How to handle this? My requirement is "How to handle (cater) the emergency sale orders effectively in ECC?" Will "Back order processing in SD" can help to cater these kind of emergency cases?
    Thanks

Maybe you are looking for

  • Crystal relort access in R/3

    Below error occured while accessing tables in crystal reports. Quite sure its not an SAP related access issue. Can anyone help to resolve this. Thanks! Data object can not be opened/accessed Details: Table level security check failed

  • SAP BPC 10.0 Web Client Blank Screen after login

    Hi ALL, We are using SAP BPC 10.0 Web Client with Adobe Flash Player 13.0.0.214 with IE 9.0 on Windows 7.0. We face strange error where on only on certain PC, the BPC web client working.. On other getting Blank/Blank Screen after login (with "movie n

  • Prompting logon screen in remote system..

    Hi All, I have developed a RFC function module in B system and when i call this RFC function module from A system (for displaying a ALV report with the data fetched from B system), to my surprise it is prompting the logon screen of B system for enter

  • Software updates cause network system prefs pane lockup

    Some problems today after Software Updates on eMac G4 running Tiger 10.4.11. The recent updates have been the all the latest IWork and iLife app updates, including QT 7.6, iTunes 8.2.1 and Security Update 2009-004. Whenever I try to get into the Netw

  • How to read qualifications an event?

    Is there any function to read these results? I need to read these results. Help..!