Plant Maintenance Schedule Calls not creating Maintenance Order

Hi,
I have created a maintenance plan that is schduled on a weekly basis. This worked fine initially but now calls are not being generated and therefore no orders are also being generated. The process I used is:
1. Create Equipment
2. Create Task List
3. Create Maintenance Item
4. Create Maintenance Plan
5. Schedule Maintenance Plan
Can you help?
Also can you tell me which program you use to create orders for an entire maintenance planning plant, I know IP10 can be used for maintenance plans? For example you schedule your maintenance plans but I assume a periodic job must run to actually create the orders

Hi Gary,
I had an issue with calls not being generated and was browsing similar issues when I came across yours. I note that you also asked how you could create orders for a whole maintenance planning plant.
This can be done by using the sort field on a maintenance plan. You need to define sort fields (config) for the maintenance plans for each of the plants required and then insert them on each plan. You can then use the sort field as a selection when scheduling.
Hope this helps.
John

Similar Messages

  • Maintenance schedule is not getting generated

    Hi....
    Past one year, maintenance schedule is not getting generated.
    Could you please let me know to where i have to look out for this problem in Equipment & Functional Locations?
    What are all the fields will be mandatory and triggering the maintenance schedule / Notification in Equipment / Functional Locations?
    Need your response at the earliest.
    Regards,
    Mohd Ali.

    Hi
    There May be several resons...
    Check Whether Maintenace for perticualr maintenance plan is not scheduled... their could completion requirement tick might selected previous maint. not done for the equipment.
    Check any scheduling for inactive equips/fl
    check any long offset has been set....
    check while scheduling any sortfield key is set or genral...if pertiucalr sort key is belong to Eq/fl which will not help
    regards
    krish

  • MRP Run can not create Planned order to Sales order

    Hi,
    I have a problem with planning run to sales order. We have a configurable material which have make to order strategy. MRP Run does not create planned order to some of our sales order. I think it has relation with schedule lines but i can not understand the problem.
    If schedule line has 1 as confirmed quantity MRP run can not plan but 0 as confirmed quantity MRP Run creates planned order.  How can i solve this problem?
    Regards,
    techmastere

    Hi,
    Order for which qty is confirming, check which schedule line is determined and which requirement type system is determining.
    then in VOV6 for schedule line tick mark availability check & Transfer of requirement
    for requirement class OVZG tick mark availability check & Transfer of requirement
    Note: if schedule line is not relevent for availability check & ToR then system always defaul confirm quantity.
    kapil

  • Could not create Purchase Order Stock Transfer Order

    Hi Expert!
    Need your help.
    User could not make Could not create Purchase Order Stock Transfer Order for new plant 1075 & 1076 at P05 with error message Not posible to determine shipping data for material. Our new vendor are 510022060 for new plant 1075 and 510022061 for new plant 1076.
    The problem was caused by the missing STO setup for these two plant 1075 and 1076, as no customer code being referred.
    Now i got the customer number for these two plants but how to set it up in configuration? Please guide me step by step.

    Hi Crystal,
    The following customising need to be carried out for Inter Company Stock Transfer.
    Path : sproMaterials ManagementPurchasing-Purchase OrderSet up Stock Transport Order
    Define Shipping Data for Plants :
    For the Supplying plant (1) the Sales Org data to be maintained.
    For the Receiving plant (2) the Customer No to be maintained.
    Create Checking Rule - U can use existing one Eg : B
    Define Checking Rule : Use Standard one Eg :01 linked to B.
    Assign Delivery Type and Checking Rule -- For the Supplying Plant (1) and document type NB use the delviery type NLCC and Checking Rule B.
    Assign Document Type, One-Step Procedure, Underdelivery Tolerance :
    For the supplying Plant (1) and Receving Plant (1) ; assign the document type : NB.
    Points to be noted :
    The Material should exists in both the plants ( 1 & 2 ) with the sales view maintained . Note that the Loading grp / Transporting Grp is mantaory in Sales Views.
    The Vendor is to be assigned to the supplying Plant (1 ) in Purchasing View of Vendor Master.
    For that click on Extras - Add Purchasing data in Purchasing view of Vendor Master (XK02 )
    Do maintain the customer in Control data of Vendor Master.
    Do maintain the Vendor in Control data of Customer Master.
    Also note that shipping conditions are maintained in the Customer Master . The same can be found in Sales Area - Shipping Tab.
    Shipping Point determination :
    SPROLogistics ExecutionShippingBasic Shipping FunctionsShipping Point and Goods Receiving Point Determination--Assign Shipping Points ( For a particular Shipping condition/ Loading Grp /Plant - the shipping point is assigned ).
    Regards
    Ramesh Ch

  • MRP batch job not creating planned orders

    Hi Experts,
    Can anyone help with suggestions of where/what to look at with this situation. My MRP background (batch) job is not creating planned orders for materials in certain MRP planning areas as expected, but will create planned orders in other MRP planning areas.   Running MD01 or MD03 creates planned orders for materials in all MRP planning areas of the plant as expected.

    Ben,
    Any time you get a difference between interactive MRP and batch MRP, first look to the planning file.
    Start out by finding some of the discrepant parts (no planned orders are being created) Review for the presence of a planning file entry in MD21. If an entry does not exist, create one in MD20.  If an entry does exist in MD21, but there is nothing in the NETCH/ NETPL/reset ord/reexpl bom cols, then this means no relevant changes have taken place, and NETCH MRP will ignore the parts. You can optionally reset these flags in MD21.
    If you discover that you have one material for which there is nothing in MD21 (no record at all), then you probably have others as well. Run MDAB in Background, which will mass create all the missing entries. Also a good idea to run MDRE in case something has been corrupted.
    Here is [OSS note 205681|https://service.sap.com/sap/support/notes/205681] which explains a bit about the planning file.  Also, See  [OSS 371016|https://service.sap.com/sap/support/notes/371016] which describes a similar problem.
    Rgds,
    DB49

  • PSL not creating internal orders in ECC

    Hi
    We have a scenario were we are creating a Product Service Letter of type 'PSLH'.
    We are creating Service Orders based on a template attached to this transaction type.
    We also need to capture the cost for this PSL Type. But the system is not creating internal orders in ECC to capture the costs.
    Please guide as to how the cost capture can work for product service letters of type 'PSLH'.
    Regards

    Hi,
    Please check the below link.(Controlling section)
    http://help.sap.com/saphelp_crm50/helpdata/en/c1/704348030bc64b8b40118e10ad98f1/frameset.htm
    as per this, integration of PSLH with ECC is not present, you may have to custom code it.
    Regards,
    Krishna

  • CO08 can not create Production Order!!!

    Dear Experts
    We are running an MTO(make to order) scenario!
    First we create an contract in the system!Then we create sales order
    with reference to this contract!
    And when the sales order is sent to the planning department! They use
    TCODE:CO08 create production order with reference to the sales order!
    But we get an error message as follows:
    Account assignment cannot be carried out because of different origin no.
    Message no. V1134
    Diagnosis
    The sales document to which you want to refer is based on sales document 41033737 and item 000010.
    Therefore, the settlement and possibly inventory management are carried out using the number of the
    preceding document.
    ut when I entered the the contract in Co08 and then I am able to create
    the production order.
    And when I back to see the detail in the sales order ,I find there is no
    value in the account assignment to the profitability segment!!
    Why the sales order have no profitability segment??*
    Why we can not create production order with reference to sales order??
    It seems there are one problem!
    Thanks for any reply!!

    Fei Liu,
    The current situation that you have described is pretty standard functionality for most MTO requirements classes.  Account assignment is normally to the reference doc, not the 'Release' Sales doc.  This includes quotations as well as contracts.
    If your business requirement is to instead use the Sales Doc number, and not the Contract number, you can change this by setting OVZG "Account Assignment Consumption" to 'blank'.
    http://service.sap.com/sap/support/notes/459734
    http://service.sap.com/sap/support/notes/729381
    Rgds,
    DB49

  • Order schedule lines not created using BAPI_SALESORDER_CREATEFROMDAT2

    Hi experts,
      I am creating sales order using BAPI_SALESORDER_CREATEFROMDAT2. I want to update the Order quantity in VBAP-KWMENG.I got the information from SDN when including the Schedule line in BAPI 'BAPI_SALESORDER_CREATEFROMDAT2  '.
      I tried by using Update flag = 'I'.I am not able to update, what are the values to be passed and how to update the field.
    Is there any other way..Please suggest me..
    Thanks&Regards,
    Karthik.

    Hi, In the BAPI if you look at the tables parameter you will find ORDER_ITEMS_IN and ORDER_ITEMS_INX as well as ORDER_SCHEDULES_IN and ORDER_SCHEDULES_INX. To update KWMENG you will have to pass that value to ORDER_ITEMS_IN-TARGET_QTY and update the same in the table ORDER_ITEMS_INX (ORDER_ITEMS_INX-TARGET_QTY) with 'X'.
    For updating schedule line go for ORDER_SCHEDULES_IN-SCHED_LINE and update X for the same in ORDER_SCHEDULES_INX.
    Try looking into the following code, I am filling in both the Item data as well as the Schedule line data.
      loop at t_mdata into fs_mdata.
        fs_item-itm_number  = fs_mdata-posnr.
        fs_itemx-itm_number = c_flag.
        fs_item-material    = fs_mdata-matnr.
        fs_itemx-material   = c_flag.
        fs_item-target_qty  = fs_mdata-kwmeng.
        fs_itemx-target_qty = c_flag.
        fs_item-item_categ  = fs_mdata-pstyv.
        fs_itemx-item_categ = c_flag.
        fs_itemx-updateflag = c_flag.
          APPEND fs_item TO t_item.
          APPEND fs_itemx TO t_itemx.
        fs_sline-ITM_NUMBER  = fs_mdata-posnr.
        fs_slinex-ITM_NUMBER = c_flag.
        fs_sline-SCHED_LINE  = c_sline.
        fs_slinex-SCHED_LINE = c_flag.
        fs_sline-REQ_QTY     = fs_mdata-kwmeng.
        fs_slinex-REQ_QTY    = c_flag.
          APPEND fs_sline TO t_sline.
          APPEND fs_slinex TO t_slinex.
      endloop.                             " Loop t_mdata
    c_flag contains 'X'.
    fs_item is of structure ORDER_ITEMS_IN.
    fs_sline is of structure ORDER_SCHEDULES_IN.

  • User Exit to check whether chapter id for Material and Plant combination is maintained while creating sales order

    Hello all,
    my requirement is, system should give error message while creating sales order, if chapter ID is not maintained for a material and plant combination.
    please suggest the user exit.

    Hi
    CASE 1 : All Plants are excisable.
    In Material master , Foreign Trade data tab-  mentioned Control code field mandatory. ( i.e nothing but Chapter ID)
    CASE 2 : Few Plants are excisable
    In the Case 2 you need to go for Enhancement
    Program Name : MV45AFZB 
    User Exit:            USEREXIT_CHECK_VBAP ( Item Level Check )
    By using above user exit you write a logic with the help of ABAPer
    Plant and Chapter ID combination table : J_1IMTCHID

  • Schedule Lines not created from MRP

    Hi !!
    I have a finished product ""111-2523-64"" and in its BOM i have a semifinished product ""111-2523-64-010"" produced(Inhouse)& three raw materials .
    For the Raw Materials I have made the scheduling agreement & source list with indicator ("2"" create schedule lines automatically""
    Problem -: Now when I run the MRP using T-Code MD02 the system is planning the finished & semifinished product 
    *but no schedule lines are created for the raw materials.*
    Please Guide , Itz very urgent.
    Regards
    Rahul Bhardwaj
    9909986406

    Dear Rahul,
    When u r running MRP maintain '3' for Delivery Schedules Field under MRP Control Parameters ( T Code MD02). Sheduling Agreement should be valid. If there is sufficient stock on hand compared with the requirement then system will not create any Schedule Lines. In material master of raw Materials on MRP2 view Procurement Type should be Maintained as 'F'. If u have maintained 'E' or 'X' then MRP run will not create schedule lines.
    Regards
    Sunil Kumar

  • Shopping Cart is not creating Purchase Order

    We are using SRM 4.0 in an extended classic version.  We have been running into a couple of situation where that shopping cart that are created and approved are not creating PO in SRM.  The follow-on document in the SC shows it's approved and the SC # but there is no purchase order linked to it.
    I have looked in tcode BBP_PD but it's not yielding anything to this situation. I have also checked to make sure BBP_GET_STATUS is running and that is fine....so can someone point me in a direction to look?

    Hi
    <b>Please refer to follwoing SAP OSS notes as well.</b>
    <u>Note 980017 - Follow-on document not created
    Note 949162 Follow-on documents exist, status I1111 and I1113 active
    Note 899006 - Status I1112 and I1113 even though subsequent doc exists
    Note 1040670 Requirements are greyed out in the sourcing cockpit
    Note 865797 BBP_ALERT_SB_NOTTRANSFERED: Incorrect status set
    Note 854478 Alert monitor: No longer possible to transfer shopping cart
    730239 Check status: Missing Backend reference
    798604 Shopping cart monitor: Icon transfer inactive
    729967 Shoppng cart:Status I1111,no follow-on docs->analysis report
    728536 Shopping cart: Follow-on docs => analysis-/correction report
    486246 Incorrect shopping carts offered for confirmation
    Note 432434 'Item in the transfer process' for reservations</u>
    Hope this will definitely help.
    Regards
    - Atul

  • For ROH system not creating planned order

    Hi PP gurus,
    Can anybody tell me that system is not generating planned order for raw material but generating it for its Fert of which it is a bom component. For fert it is giving exception message 62.I checked material master MRP type-M0 FOR FERT MATERIAL
    MRP type-PD  FOR RAW  MATERIAL
    pLANNING TYPE FENCE IS ALSO MAINTAINED AS 14 days for raw material
    Pl.reply ,it is urgent
    Thanks in advance

    hi,
    with which transaction code r u running the MRP??
    as per my knowledge u must be doing it with the MD02 with finished product at the header level.
    just try this, run the MRP for the Raw material since you are having the dependant requirement with the -ve value, it will create the palnned order.
    i am not remebering what is issue?? there is something theorotical,
    u just try this
    i wil let u knwo furhter once u get the planned order.
    in MPS, i am doubtful that it will go for multilevel, thats why its creating only dependant requirement.
    you try to run the MRP thr MD01 then u ill get the order.
    Let me know ASAP, i will help u out.
    REgards
    Pravin Mukkawar

  • BAPI does not create Sales order

    Hi All,
    I am using BAPI_SALESORDER_CREATEFROMDAT2 to create sales order.
    It is working fine till now.
    But I found that whenever there is a material whose condition price is maintained and doesnot match with the valuation type, the Sales order does not get created, neither it gives any error msg.
    For e.g For Valuation type Consign , condition type ZPCS is valid and similarly for Turnkey , condition type ZPTK is valid.
    if a material has valuation type consign and condition type ZPTK.. The SAP system ofcourse will not allow to create a SO unless we delete the ZPTK entry from the SO and create ZPCS...
    BAPI also doesnot create the SO but doesnot return the error messge too.
    I try to put the ZPCS value to BAPI thru BAPICOND..but still not working?
    How do i handle such case?
    Points will be awarded to useful ans

    Hi,
    If you are saying that you cannot create a sales order with the Valuation type and Condition type mismatch even through VA01 manually, then there is nothing much you can do in BAPI also.
    2nd Case is you say that that BAPI RETURN table is not getting populated and it is empty in this issue which is not letting you know that Sales order is not Created.
    The one work around for this issue is you can check the exporting parameter SALESDOCUMENT if it has the Sales Order number or not. if the RETURN table is empty and the SALESDOCUMENT field has SO Number, then SO is created and if RETURN table is Initial and SALESDOCUMENT is also Initial, then it is the issue that you are facing.
    Also try posting a Query in OSS.
    regards,
    Mahesh

  • Not create Sales order

    hi
    when im create sales order va01.than i have complete sales order i m click on incomplete log some missing item.two item missing this msg display.
    1) profitabolity segement number  this filed is is requer
    2) wbs element this filed also active how to inactive this filed this filed is there account assignment  main field display. please help mee....

    Hi,
    This is due to incompletion procedure for the sales document type. You can remove these from the incompletion procedure for the sales document type in SPRO. Steps as below:
    SPRO->Sales & Distribution->Basic Functions->Log og Incomplete Items->Define Incompleteness procedure.
    Here, for change the prcedure for Sales -Item
    Please close the message, if found useful.
    Muraleedharan.R

  • Material type for BOM that should not create production order

    Hello all,
    We have following situation in our company:
    We ship few products say for e.g A,B,C which are part of higer level BOM for product M1  to the customer, before the actual product M1 is shipped.Currently these ship-a-head products(A,B,C) is also part of  BOM for M1.
    We need to combine these ship-a-head products A,B,C as one product  M2 (thinking of a BOM) and ship that M2 to customer before M1 is shipped.
    In that case what could be the material type for product M2 so that MRP won't create any Production orders for M2.
    Also wondering Is there any other way, other than creating a BOM that could combine products A,B and C and ship to customer a-head of time.
    Thanks,
    Sre

    Hi,
    Please create BOM for Material M2 by using usage other than production..
    1     +     .     .     -     -     -     .     Production
    2     .     +     .     -     -     -     .     Engineering/Design
    3     .     .     .     .     -     -     .     Universal
    4     -     -     .     -     -     +     .     Plant Maintenance
    5     .     .     +     +     -     -     .     Sales and Distribution
    6     .     .     +     .     -     -     .     Costing
    7     .     -     .     .     -     -     -     Empties
    8     -     .     -     -     -     -     -     Stability Study
    M     .     .     .     .     -     .     .     External Munitions Display
    hope it may help you.
    Kuber

Maybe you are looking for

  • Java Plug-in not working with WinXP SP2 Registry Key Missing Error Pop-Up

    I have WinXp PRO with SP2 and the Oct 12 Security Update Patch for SP2 loaded and I went to my Control Panel and saw that the JavaRuntime Environment 1.4.2_04 icon was missing and when I went to click the Java Plugin icon to Open it, I got the follow

  • Why can't we backup (with Time Machine) our Airport hosted 1TB HD from our iMac (hosting a 2TB HD)?

    With an iMac (one year old), we are using Time Machine to backup the iMac and one small external HD to a 2TB HD (USB). The iMac is on a small wired network along with an Airport Extreme hosting a 1TB HD for shared iPhoto Libraries, 2 printers and a r

  • I am getting an error 1310 error writing to file

    I had to clone my computer due to motherboard going out in other.  Aodbe wanted me to update registration found out I had to uninstall and reinstall CS2.  Did it and I get the Error1310 Error: Writing to File code.  Please help

  • Screen sharing worked and not working

    i have set up both my computers for screen sharing and have accessed my macbook pro 17" (snow leopard- up to date)  for months on my macbook pro 15" (lion- up to date)- it worked.... THEN, when i went in reverse- mb17" accessing my mb15"- it worked..

  • Can I run Photoshop CS4 and CS5 on the same system?

    I read somewhere a zillion years ago (right?) that you coould run CS4 and CS5 on the same system but at the time I wasn't even considering it. Run on the same system - not ness to run at the same time Or should I install it on a seperate drive (boota