Hi guys, how are you.
One scenario : I am using the header level BOM(printer)
Alternative 1 :
2tray                 :  1no
hard disk(20GB) : 1no
Duplex kit          :  1no
Alternative 2 :
Hard disk(20GB)  : 1no
Stand                 :  1no
Duplex kit           :  1no
Here i want to maintained pricing for header item bcz it is the header level BOM.
How to maintain the different pricing for respective alternatives at header level only.
Regards
lakki

Dear Lakki,
Try in this way it may help you,
-->Add the field STLAL in the field catelog with the help of ABAPer.
-->Try to put the field 'Alternative' (STLAL)in the pricing condition table then put that in to access sequence then assign that access sequence to the condition type then maintain the condition record for that condition type in the transaction VK11 with key combination 'Alternative' .
I hope it will help you
Regards,
Murali.

Similar Messages

  • Prices taken for BOm levels

    Hi,
    When we perform the cost roll up process (ck40n) how the prices will be taken in each level for BOM structure.
    Regards
    Mastan Reddy N

    Hi,
          As this is correctly ansered by some of the experts.To add some value , i would like to focus on the basic concept before heading for your solution.
    You must define the costing variant in Customizing for Product Cost Controlling under Cost Object Controlling > Product Cost by Sales Order > Preliminary Costing > Costing Sales Order Items with Product Costing > Costing Variants for Product Costing > Check Costing Variants for Product Costing.
    hope you are done with above settings.
    second You specify in the costing variant whether you want to transfer order BOM cost estimates. Order BOM cost estimates are only transferred if they were created with the same costing variant. You therefore use the same costing variant for sales order costing as for order BOM costing.
    A costing run for multiple order BOM cost estimates that are not linked to each other is not supported.
    If a subordinate assembly in a multilevel BOM for an  order item is changed and costed, this has no effect on the cost estimate of the higher-level assembly. If you change assemblies, you must take organizational steps to ensure that all relevant cost estimates are organized.
    So please make sure you have configured/maintained the same before running your final cost estimates for BOM.
    Regards
    Chandra

  • No price determination for Material/Plant error CK465

    While calculating the cost for a material through process order ,  no price could be determined for  input material despite the standard price of the same is being released , error message CK465.Apart from that the valuation variant and costing varaiant has also been checked and found correct. Still the error persist.
    How to correct the cost calculation while creating process order ? Plz suggest

    HI,
    Please check the Plan Costing variant (usually 'PPP1') assigned to Order ('Control' Tab) and make sure you maintained the prices as per this Valuation strategy maintained in transaction OPL1.
    Hope this helps.

  • Moving Average Price Determination for new stock in project

    Hi Gurus,
    We have following scenario in our project. One plant is shut down ( say plant A ) and a new plant (plant B)  will come up to replace the older one. So we are transferring the materials present in A to B. We have extended the materials to B and maintained same MAP. Then we are doing goods issue in plant A (mb1a ) and goods receipts in plant B ( mb1c - movement type 501). But the account document shown for mb1c is not picking up correct MAP.
    Please note: Plant A nad plant B are in different company code.
    Could you please explain how is MAP determined in case of GR done thorugh MB1C and please suggest if the process we followed is correct ?
    Regards
    Sayan
    Edited by: Jeyakanthan A on Jan 8, 2012 10:40 AM

    HI Jurgen,
    Thanks for your reply.
    1. We have maintained the price control as V
    2. You have mentioned "However it is as well possible to enter an external value in the movement (if enabled in customizing). then the movement is valuated with this value and the MAP in material master is adjusted."
    Where to checl in IMG for the above ?
    3. We did goods issue in the previous period 12/2011 but doing the GR in current period 01/2012. Do we need to maintain MAP for both the periods ?
    If you can please tell us what is the standard process to carry out such activity ?
    Regards
    Sayan

  • Price Determination for Delivery

    When I create the delivery document with reference to sales order, I want to copy the pricing (all the conditions and values) from the sales order to delivery .But the standard SAP is  re determining the pricing
    <u>Simple Example.</u>
    In the sales order line item the net value is 10 $  (Standard price 9 $ and Freight 1 $). This Price is determined by the pricing procedure.
    If I change the freight manually to 2 $ in the sales order the net value becomes 11 $ now.
    If I create a delivery with reference to this sales order the net price of the line item in deliver will be again 10 $ which is determined by the pricing procedure. But I want to copy the price from sales order line item which is 11 $.
    Did any one come across any enhancement to do this, So that the Pricing determination will be suppressed and the pricing will be copied from the reference sales order?

    Hi
    I have gone through the copy control options .Pricing copy can be done for sales documents and billing documents by giving pricing type <u>D</u> (Copy pricing elements unchanged)
    But there is no option to copy pricing for delivery documents.
    pricing copy option is available for the following
    Sales Document to Sales Document
    Billing Document to Sales Document
    Sales document to billing document 
    Billing document to billing document
    Delivery document to billing document
    But pricing copy option is not available for
    sales document to delivery document.
    That is the reason why it is a development.
    Can any one help me out by telling the suitable enhancement.

  • Updating the Price Determination Field in the Material Master (MBEW-MLAST)

    I'm doing a material conversion into an existing SAP system and the program to load the materials didn't load a value in the price determination field (MBEW-MLAST).  Normally this field is required but because the conversion BAPI doesn't do as much validation as MM01 it was possible to create the record without a value.  The field is not open to input when I use MM02, and even though it appears to work, when I do MM17 mass change the field is also not updated.  Finally I tried transaction CKMM - Change Material Price Determination for Material Ledger but it required an entry in the Old Price Determination field and it won't let me enter blank. 
    We've since corrected the program but my problem is that I've converted about 5000 materials without a value in the field meaning the FI guys can't release cost estimates which is causing a bunch of problems for the testing that we want to do in this system.   We've taken about 3 weeks to do this conversion so going back and doing it again is a terrible option.  Does anybody know a way to get a value into this field other than what I've mentioned above (MM02, MM17, CKMM)?
    Suggestions please.

    have a look into OSS Note 1491364 - BAdI CKML_SET_VPRSV: Price determination cannot be changed

  • Erro"Transaction cannot be posted due to errors in price determination"MIGO

    Hi All,
    I am facing error message "Transaction cannot be posted due to errors in price determination" for "X-field conversion" while posting GR document against Scheduling agreement.
    I have checked the Validity periods of conditions maintained in Scheduling agreement and it was within validity.
    In Material master - Price Control - V (Moving average price/periodic unit price)
    Standard price              0.00 
    Per. unit price             1.58 
    Price unit             1         
    Please help me to resolve this issue.
    Cheers!
    Sujay Chinchole

    your material master displaying Zero price .maintain the price in material master.and also check why material has Zero price.
    what is the price  in  material moving average field
    Edited by: Sridhar Jayavarapu on Mar 13, 2009 7:17 AM

  • MM - Price determination per business types

    Hello,
    I need to determine multiple price determination for the same material purchased to same vendor.
    Indeed, depending on the business type (purchase for production, for trial or for aftersales), one single material can have different price towards the same supplier.
    The business type must be set up at purchase order item level, and depending on the business type, a different price must be determined.
    Do you know how to proceed? Can the field “sub-item category” be used in the pricing procedure?
    Any other idea?
    Thank you for your help,
    Nathalie

    If you want to a single material can contain multiple price..
    And all valuation will be as per different price, then the better option will be split valuation.
    Here you have to use valuation type for each material which you want to set the different price..
    Suppose you want to use price 10 for material which will be purchased, then you can use one valuation type for the material..
    And you want to use price 20 for material which will be used for trial, then you can use another valuation type for the material.
    Both valuation type can contain different valuation class and different price but material will be only one...
    Regards
    Dev

  • Price determination as per delivery date

    Hi All,
    I have created a PO in which the PO is picking up the dalivery date as the current date. when i change the delivery date as some other date there is a message saying Delivery date changed (new price determination process may be necessary).. I worked with my ABAP guy and solved this problem and now the PO is not picking the current date.
    Now, the user wants me to configure how to determine the Price for different delvery dates.
    That is if i change the delivery date to some other how to check if the PO is picking the price determined by that delivery date.
    I checked the info record and the validity date is 12/31/9999. and this is the message iam getting
    Delivery date changed (new price determination process may be necessary)
    Message no. 06484
    Diagnosis
    If the price determination date is the delivery date and other conditions are valid on the new delivery date than those that are valid on the old one, the price is no longer valid.
    Procedure
    If this is the case, and you wish to see the price that is valid as at the delivery date, carry out a new price determination process.
    And u said to define on the basis of which Date of Price Determination system should select the price. where can i define the price determination for delivery date. This is the first time iam working on such issue of price determination.
    Thanks,
    Sameer

    Dear Sameer
    There is no relevance of pricing date with delivery date.  For information,  while creating sale order in VA01 after giving your sales area and execute, there is a field "Pricing Date" in Sales tab and the date will flow into this field by default the date on which you are creating sale order. 
    So irrespective of your delivery, your invoice pricing will be effective based on this field.  Unless you change the date here, your pricing condition will not change, if you have a different pricing in VK11.  Of course, you can also change the pricing date at item level for which click on "Goto -- Item -- Sales A".
    thanks
    G. Lakshmipathi

  • Error: "Transaction not posted due to errors in price determination"

    Hello,
       Please tell me why this error occurs "Transaction not posted due to errors in price determination"
    for purchasing document.
    I have checked the PO and it contains all the valid pricing details.
    Then why the error?
    Thanks & Regards,
    Priyanka

    Hai
    Check ur Pur.Grp and the Vendor U are using some time u may be using the differrnt vendor grp and pur grp or pur org thru which the pricing procedure hets triggered
    thnk u
    with rgds
    moosa anis

  • You can't perform price determination /You must first allow price determina

    Hi Friends,
    While performing the t code CKMH (Single level price determination) I am putting plant, period and fiscal year but when i am going to execute I m getting the following error.
    1.you cannot perform price determination in period 01/2009.
    when I tried with previous period and years then i m getting                                                     
    2You must first allow price determination for period 001 / 2009**
    Any pointers will be rewarded.
    Regards

    HI,
    You have to allow the respective period in CKMG, it will allow in CKMH.
    Regd,
    Khan Mansoor.

  • ( error no CK 465)  No price could be determined for the material

    Hi,
    While costing for a material i am getting the error messages as folloows
    1) No price could be determined for the material   error no CK 465
    2)Cost component split costed with value of zero  CK240
    Materail procurement type is F - External procurement  so i hope no need BOM and routing , they were not created.
    Material has price control indicator - S
    Material type - ZVAR (Finished product variant)
              What could be the reason for this error and what is the solution
    THannks & regds
    Ramachandra

    Hi Experts,
    I also got the same error how to solve it.
    Many materials costed with errors how to resolve those.
    Error Messages are: 465,240,322,597,168
    Please let me know the solution.
    I have Run the cycle on 29-02-2012, Today i.e 0n 01-03-2012 MM consultant wants to close the period of February.
    Is it required to resolve the errors before closing the february period?
    Can we resolve the errors after closure of the period.
    Please guide me. Most urgent
    Jyoshna

  • Error showing - No price could be determined for subcontracting in CK11N

    Hi,
    We are facing a problem in CK11N that while we are creating Material Cost Estimate with Quantity Structure, getting an error message..
    No price could be determined for subcontracting
    Message no. CK468
    Diagnosis
    The system could not calculate a price for the subcontracting because none of the valuation strategies in valuation variant 001 was successful.
    System Response
    If the system issues a warning message or an information message, the costing item is used in the cost estimate with a zero value.
    If the system issues an error message, it sets the status "KF" (costed with errors).
    If the system issues a termination message, the cost estimate cannot be processed.
    Procedure
    If you have authorization for Customizing, check the valuation strategy for subcontracting in valuation variant 001.
    I read many thread already, but no solution is suit my requirement..
    please help..

    We run the transaction OPN2 and select 001- Planned valuation - mat. Valuation Variant. Db Click on it and select Subcontracting tab.
    There Strategy Sequence is defined as under:
    Priority......Strategy Sequence
    1...............Effective price from Purchase Order
    2...............Net Purchase Order price
    3...............Effective price from Quotation
    and in Quotation in Purchasing option, there is selected - Auto quota arrangement.
    please guide.

  • Price can not be determined for pr in cj20n

    hi
    i am making pr in cj20n before saving message is coming
    "<b>Price cannot be determined for material 4000008727
    Message no. CO283
    Diagnosis
    An error occured when determining the price of a requisition.
    Possible causes:
    •     The system could not determine a controlling area for the plant
    •     Error in the costing variant allocated to the order type
    •     The system cannot determine a valuation variant via the costing variant
    •     Error in determining the price"
    <b>what is the meaning of this, after ignoring this message when i save the pr and do migo, price in material master is not updating.
    plz expalain this scnario.</b>

    Hi Ranjini,
    Please look into the following
    1) Customer master data is fully maintained
    2) Customer number ranges are fully defined in customisation
    3) Customer address details are maintained
    4) Is there any special characters used while defining customer data or customer
    number like $, #,[ etc.,?
    5) Customer int models are active in SCM side prior to IDOC processing (including
    customer, demand, stocks etc)
    Please confirm your findings
    Regards
    R. Senthil Mareeswaran.

  • The Condition for service price determination incomplete

    Dear experts,
    I run the System with EC&O Best Practice. Howerver, I can not enter Services on tab Service of Sales Order: Short text of Service, Quantity, UOM, Gross Price. the error "Condition for service price determination incomplete" occours when I press Enter key.
    Conditions for service price determination incomplete
    Message no. SE477
    Diagnosis
    Either the calculation schema for services does not exist or the condition types have not been defined correctly.
    Procedure
    Please check your Customizing settings for service conditions.
    If you have not yet defined any conditions for services, you can adopt the standard SAP settings from client 0.
    Please help me check this issue on the attached file.
    Thank you very much.
    Thanks,
    Binh Tran
    <Personal details shared by OP is removed by Moderator. >
    Message was edited by: Jyoti Prakash

    Hi All,
    Thank you very much for your inputs.
    I checked all the notes, 25357, 27024  and 1383066. Everything is ok in the system. and these notes explained more on the MM part not on the SD- BOS. However, still i am not able to complete the Inquiry, same error exists.
    This error is in SD not in MM, while i am creating the inquiry BOS.
    If any one come across it and solved it, please let me know.
    Regards,
    Suresh