Problem in rough cut capacity planning

Hi,
I am facing following problem in rough cut capacity planning....
When the capacity is overloaded in a particular month then capacity requirement is getting passed on to previous month as shown below....int the month of MAY 2014 capacity is getting overloaded then capacity requirement is transferred to Previous month APR 2014... I don't want this...what can be done to avoid this....I want to see overload in month wise....Plz help
Thanks
Kumar

Hi Rupesh,
Thanks for your help...finally issue is resolved...making the changes in OPU4 done the job...in OPU4 we need to remove the indicator of scheduling for rough cut capacity planning ........now getting the results as desired...

Similar Messages

  • Rough Cut Capacity Planning

    Hey all,
    i wanted to configure Rough Cut Capacity Planning in such a way that
    1. i could view capacities of workcenters given that the demand (load) of planned orders could be executed in a particular period.
    I accomplished this partially, meaning i could find out the bottlenecks on the workcenters but this was only on single material level, if i wanted to run this check on multiple the system, supposedly, offers me the option of using the product group, my question is, where do i view these bottlenecks on capacity IF i want to run RCCP on Multiple products.
    2. i wanted to find out exactly how much i can produce in a period, given that the external and internal procurement lead times are incorporated this is usually reffered to as Master Production Scheduling, as far as i know atleast.
    kindly shed some light on these matters.
    Regards,
    Danish
    PS. i've seen similar posts to this but none directly addressing these issues hence i felt the need to ask these questions seprately.

    to further clarify my question i would like to see, as a result of stimulative planning (RCCP):
    1. Impact of Planning (planned order quantities) from ALL materials that were being planned on work centers used in recipes.
    2. Identification of bottlenecks, which is of course the subsequent function from point 1.
    3. Capability to produce with reference to Materials availability (lead-times being incorporated of components).

  • PP-PI:  Rough-cut capacity

    Hi Gurus,
    We are in a process industry and using descrete production. We are not using production group but we use product hierarchy.
    Now we want to run rough cut capacity to check resource capacity. Can anyone send me the complete scenario to check rough-cut capacity in my environment?
    Thanks in advance.
    Shiv

    1. Create a rough cut capacity planning profile in the Tcode mc35 using the infostructure.
    2. Then create your planning data for the flexible planning  mc93
    3. then when you create the Planning data in the View Tab - y ou have the capacity situation .
    4. when you select this it will branch to the Rough cut capacity planning - then select show in that
    5. Now based onthe values that you avhe maintianed in the RCCP you can see the capacity requirement in an additional screen below your planing values.
    Check the configuration for the
    Configure scheduling parameters in the SOP menu of the SPRO
    Let me know if you need more details

  • Rough Cut Capacity Profile

    Hello All,
    I want to ask about Rough Cut Capacity Profile and how to analyse it in MC82 t-code,
    I have made RCCP using MC35 for a Product Group X, where i use 2000 ton for the base qty
    After that, i use MC82 t-code and than I enter the production line for just 1 month, for example i enter production value for June 2010, but for April,May and June still blank
    The Problem is when i choose View --> Capacity Situation --> Rough Cut Planning --> Show, to analyse the capacity requirement,
    I get that the Capacity Rqmnt value is not only in June, but also in May, Why it has to divide the calculation for 2 month? , because i just entry the production line for June, so i expect that the capacity rqmnt value is just appear in June
    and How to calculate the formula for capacity rqmnt in MC82 ?
    Regards,
    Marufat

    Hello All,
    Is there anyone who can help me?
    Please, I really need to solve this problem
    Regards,
    Marufat

  • Rough-cut Capacity Check at any level on the Plng Hierarchy ??

    Fellow Experts,
    I have the following Planning hierarchy on my self-defined, consistent planning, Info structure:
    MFG Plant >> Prod Family >> Materials.
    Product Family is a grouping of materials by Machine Cells(Work centers). I've the data available @ the material level & the same is also auto-aggregated at the Prod Family levels. At this point I want to trigger Rough-cut capacity check at the Product Family level.
    I've maintained the key-figure on the Info Structure, required data set-up on MC35, config for Scheduling parameters (to do rough-cut planning) & selection ID maintenance for Rough-cut Plng Profile to be picked up. Yet, the system keeps bumping me off with "No Resource Load exists" error.
    Is there something wrong I'm doing or my expectations are incorrect?? Could someone help me out here??
    Cheers
    Anand

    HI,
    Make sure the capacity planning relevant field is maintained for the Infostructure config setttings in MC7F.
    Regards
    Ratan

  • Mass processing for rough-cut capacity

    Hello PP experts,
    Help me with the options of checking rough cut capacity in flexible planning in Mass.
    Are there any separate transactions availbable or can i create a macro?
    Thanks,
    G.Madhvaraj.

    Thanks Brahmankar, I understand that. Next doubt is,
    This rough cut capacity situation is not been stored in my info structure.Where does it get stroed?
    G.Madhvaraj.

  • Problem in Rough Cut Plan while displaying Date & the nbre of columns

    Hi Expert,
    During the creation of Rough Cut plan for material Trx MC87, the system display only one Column and the displayed date  is 2012.
    I Tried to extend the period by using the the button "page Right" and "page left" but there is no  chance.
    your support is highly suitable
    Tsang

    Hi dear,
    I tried that but not working for me could you please investigate again in my request

  • Problem in Rough Cut Plan while displaying horizon nbr of columns

    Hi Expert,
    During the creation of Rough Cut plan for material Trx MC87, the system display only one Column.
    I Tried to extend the period by using the the button "page Right" and "page left" but there is no  chance.
    your support is highly suitable
    Olfa

    Hi Dear,
    should Go to trx MC79 and change the date and the period or make it all blank field

  • Rough cut Capacity load in Standard SOP

    Hi there,
                 I have created some sales & production plan syncronous to sales......but when I try to see the capacity load thru View- > Capacity Situation - > Rough Cut planning- > Show
    It is showing me that No Resource load exists ...... please guide me how can I see the load for the same
    Regards
    Kaushik

    Hi,
    Please maintain the settings as mentioned below.Then you can see the load.
    Before you can carry out resource leveling in SOP, you must:
    1.) Create a PP task list (a routing, a rate routing, or a rough-cut planning profile) for the material, product group, or characteristic values combination whose resources you want to plan.
    2).Configure resources planning in Customizing for Sales & Operations Planning.
    3).If you use routings or rate routings to do resource leveling, define the key figure to which the resources are tied. Do this in Customizing for Sales & Operations Planning under Set parameters for info structures and key figures.
    4).Define the planning plant of any information structure whose plant is not uniquely identifiable (that is, either your information structure does not contain the characteristic "plant" or your rough-cut planning profile covers more than one plant). Do this in Customizing for Sales & Operations Planning under Set parameters for info structures and key figures.
    5).Set the default SOP plant for Sales & Operations Planning. Do this in Customizing for Sales & Operations Planning under Set planning plant for SOP.
    Thanks,
    DV

  • Rough Cut Planning Profile-by Capacity category

    Hai,
    I am creating Rough Cut Planning Profiles in ECC6.0 for use in Standad SOP (S076). In MC35, I don't see a place where I can enter by Work center category- like I want both Machine and Labour categories as I have different times for each category.
    { when I view the rough-cut capacity situation in MC82, system displays both categroies, but it is based on only the hours I maintained for one of the categories- how do I maintain for both categories?}
    Thank you in advance:)
    Sonali
    Edited by: Sonali on Apr 28, 2009 3:05 PM

    Hello Sonali,
    Rough cut capacity planning is used only  for bottle neck resources.Analyze your process and you will come to know for the product group or material which category or machine is bottleneck.
    Create a rought cut planning profile for a production line or Workcenter or PRT or Cost(Relative cost not product cost).
    PS:Roughtcut capcity planning should not be used for all the workcenters.
    Thanks,
    Raj

  • LTP and Rough cut planning with Demand Mangment

    Hello ,
    I am quite new for the planning topics.
    Need help for the understanding difference between  long term planning and Rough cut planning.
    I would like to know in which industry or for which process scenario we choose long term planning and Rough cut planning? Also both this planning scenario how affect or related to the Demand Management.
    It will great Help if you put some example with brief process description or scenario details.
    Regards,
    Maulik

    Hi Maulik
    There is also Sales and Operations Planning (SOP) which is a higher level of planning, that also allows you to create different scenarios.
    Rough-cut capacity planning is used together with SOP. Here, you will generally plan at finished product level, using the sales forecast.
    Long-term planning is a more operational tool, very smilar to MRP, but simulative.
    SOP data can be transfered to DM and LTP can use DM data as an input.
    I suggest you to read the documentation of both functionalities for a better understanding of each one:
    Rough-cut Capacity Planning:
    Executing Resource Leveling - Sales & Operations Planning (LO-LIS-PLN) - SAP Library
    http://wiki.scn.sap.com/wiki/display/ERPMan/Rough-Cut+Capacity+Planning+on+SOP
    Long term planning:
    Long-Term Planning (PP-MP-LTP) - SAP Library
    BR
    Caetano

  • OAG Capacity Planning

    Hi,
    Please help me to clarify on how to properly plan the capacity for an OAG deployment. I’m taking as base OAG documentation:
    http://docs.oracle.com/cd/E55956_01/doc.11123/administrator_guide/content/admin_planning.html#p_admin_planning_ha
    formula described there helps to get the number of Gateways
    numberOfGateways = (ceiling (requiredThroughput x factorOfSafety / testedPerformance) x HA) x (1 + numDR) + staging + eng))
    I’m assuming each gateway is deployed in machines with following prerequisites, as described in documentation
    Intel Core or AMD Opteron at 2Ghz with Dual Core or faster—i386 or x86_64 (32-bit or 64-bit)
    Minimum 2 GB free disk space, 50 GB recommended
    Minimum 4 GB physical memory
    In the case requiredThroughput has significant increments, I think we should deploy additional Gateways, please help us to clarify
    Questions are:
    In order to properly scale OAG deployment, its just required to deploy new Gateways (in additional machines with above characteristics)?
    Increasing physical memory or adding more CPU threads has any positive impact in performance?
    Please advise.
    Regards
    Juan

    Hope you are asking regarding the Manufacturing Capacity Planning.
    Oracle Capacity functionality is part of the Manufacturing module license.
    Oracle Capacity lets you calculate your Capacity load ratio by resource or production line.
    It ensures that you have sufficient capacity to meet your production requirements.
    Oracle capacity provides you with two levels of capacity planning :
    Rough Cut Capacity Planning (RCCP) to validate your master wschedules
    Deetailed Capacity Requirements Planning to validate your MRP plans.
    Check the Capacity User Guide available at Appsnet
    (http://appsnet.oracle.com -> Manufacturing -> User and Implementation Guides)
    for more details.
    Warm Regards
    Vinod Subramanian

  • Rough Cut Planning Profile in SOP

    Hi,
    Need an input on the Values keyed in to the Rough cut capacity profile? Is there any documentation on the same?
    I have maintained the Time span as 1 work day and the basse quantity as 1. In the resource table, i have keyed in the work center and the unit as H. Now when i maintain a value of 1 under the first day the capacity req is 1 in SOP but when i maintain a value of 1 in day 1 and day 2- the capacity requirement doubles
    Edited by: Karthikeyan Balasubramaniam on May 9, 2008 4:28 AM
    Edited by: Karthikeyan Balasubramaniam on May 9, 2008 4:29 AM

    Hi Karthikeyan,
    The follwoing information given by sap will be useful.
    help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPSOP/PPCRP_SOP.pdf
    help.sap.com/saphelp_45b/helpdata/en/a5/63211443a211d189410000e829fbbd/frameset.htm
    Reward if useful.
    Thanks and Regards,
    /N

  • Setting needed for Capacity Planning.

    Hi PP Gurus,
    I want to know what setting we have to do for capacity planning.
    what I know is:
    1. W/C should be set for finite scheduling.
    2. In scheduling parameters for process order tick "Generate capacity Requirement".
    This both setting are made in my scenario, but it is'nt loading the work center fot that week.
    Any other setting nedded?
    Thanks, in advance.

    Dear ,
    You need to have following set up at basic level frist before you perfomr the capacity requirement planning  :
    1.In OPKP-Define Production Scheduling parameter -Availability check -Confirm Capacity and also Finite Scheduling chekc box ticked .
    2.In OPU3/OPU5-Define Scheduling Parametesr -you should mark the following
    1.Automatic Scheduling check box should be marked
    2.Scheduling Log check box should be marked -generate in case there is a scheduling error due to capacity over load .
    3.Scedulinga and Generate Capcity should be ticked .
    3.In OPJK Imaintain check capacity with SAPSFCG013 overall profile and set indicator -1 -Release Order -by user decision if capacity is insufficient
    4.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    5.Routing - enter the values for the standard values. Use control key with scheduling and CRP activated .
    6. OPD0 and have the following set up  : Overall profile : SFAPSFC015 --Inside the over all profile I have the following set up
    1.Selection Profile -SAPSFCS013 SFC: Order view, standard overview
    2.Control Profile : SAP___C004 : Gen Capacity Availability Check for 1.5 months
    3.Time Profile : SAP___Z006 : Gen Capacity Availability Check for 1.5 months
    4.Evalution Profile : SAPSFCA013 : Gen Capacity Availability Chek =3.0D
    5.Strategy Profile : SAPSFCVER1-Gen Capacity availability Check
    6.Period Profile : SAP___P001 -Weekly period
    7.List Profile : SAPSFCI001-Production Planing
    Check all of them in place .Then you can go ahead with Capacity Req.Planning -Evalution and Leveling -CM21/CM22/CM05/CM07  etc.
    Refere the below theread for farther reference :
    Capacity problem in production order
    capacity planning
    Hope this will be useful .
    Regards
    JH

  • Rough -cut plan with capacity requirment calculation

    Hi all,
    We checking SOP with rough-cut plan
    We created Rough-cut profile in mc35 for our bottle neck work center with base quantity -1 and time span - 1
    then we selected new work center (there is no existing cap req). and assigned base unit measure:min.
    and we assigned 1min for each day and saved the profile.
    Now we went to mc88 and checked the material's active version production plan. (period split- DAY)
    in View -> capacity situation -> rough cut planning -> show.
    System calculates some capacity requirement for our production plan.
    Say for tomorrow's date i given 1000 qty - production plan.
    but system showing capacity req
    Work center:  TESTWC3                  Plant: 0001         Capacity:  001
    Info structur  Material          Plant   Order qty     Unit     From              To          Capacity reqmts      Unit
    S076            TESTFERT14    0001  1000.000       EA    29.01.2010  11.02.2010   9000.000              MIN
    with 9000min and cap load more than 652% ( Actuallly  it has to show 1000min as per rough cut plan profile)
    Our available capacity of work center per day - 1380 min
    We cant understand the capacity requirement calculation in MC88..
    Help us out...
    Thanks in advance

    Hi,
    Rough cut planning is genrally done for the group of material say product group, group of workcentre rather than individual material or workcentre.
    As standard, in resource table whatever the value you enter that corresponds to no. of days. Each column represents one day.
    Pl. refer this link for clear understanding of the same.
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/63212e43a211d189410000e829fbbd/frameset.htm
    Madhava