Process Order technical completion

Hi
whensoever i m trying to technically complete the order, i m getting the Error message no. BS007 i.e. ""Change" is not allowed".
The current status of object 'ORD XXXXXX' prohibits business transaction 'Change'
Current status are as follows :
REL  CNF  DLV  PRC  CRFI EXPL EXTS GMPS MANC NTUP PIGN SETC
No status profile is assigned to order.
i have checked in BS22. All the status contains technically completion permission.
Kindly Guide.
Regards
Sachin Ahuja

Dear
Just a re-check
Did you check the User status in COR2 ? Here there will be a Blue I- symbol (Status) as like Production Order -C002 .Select that I symbol and Choose TECO status or REL status , then set TECO from Function -Resstrict Processing and SAVE.
I think it should work based on the User staus which is allowed .
Regards
JH

Similar Messages

  • PP - PI Process order - Technical complete problem

    Hi Gurus,
    I have created process order and generate Cont.recepie. Then I tecnical complete my PI sheet after report data. when i set technical complete in my process order. system says "It cannot be technical completed because status "CRCR" Contrl recepie created". How i can set status technical complete to my proc.order.
    kindly help
    Majid

    Hi,
    Inorder to TECO or close your order first you have to close the Control Recipe. To do so follow the steps:
    1. TCode: CO57
         Proc.Message Cat: PI_CRST (Message on control recipe status)
         Process Order Number
         Control Recipe Number
         Control Recipe Status: 00005 or 00004 or 00007
         After these entries save the Process Message.
    2. TCode C054
        Here send the Process message that was created in the above step.
    If the message is successful, the status in the order changes from CRCR to either CRAB (if control recipe discarded), CRFI.
    Then you can close your order.
    Regards
    Vinod

  • MIGO Process order-Delivery completed indicator by default as "2. Set"

    Hi all,
    Can We have the MIGO Process order-Delivery completed indicator by default as "2. Set" instead of Set automatically by any configuration.
    Pls suggest.
    BR,
    Subbu.

    Hello Subbu,
    Go to SPRO --> MM --> Inv Mgmt & Physical Inv --> Goods Receipt --> Set "Delivery Completed" Indicator
    Deselect the "Delivery Completed" indicator for your Plant. Then go back & do the MIGO and check.
    Hope it will help.
    Regards,
    Anup

  • BDC recording not executing last OK code for order technical completion

    Hello!
    Regarding a QM requirement, I have created a rather simple BDC recording to change the activity type of an order to new ones (based on particular conditions not relevant here) on transaction IW32.
    However, if the order is technically complete, I have to cancel the technical completion, change the activity type, and then complete the order technically again (so it remains just the way it was before modification).
    The only order types relevant in the requirement are YM01 and YM02. For YM01, the BDC recording works like a charm. But when executing the proper recording for type YM02, the last OK code (i.e. pressing the OK button on the Complete subscreen) is ignored and the process remains incomplete: the orders are never completed technically again.
    Here is the recording:
    0     T     IW32     BS AA X   F
    SAPLCOIH                       101     X                                                                               
    0           BDC_OKCODE     /00
                                            0           CAUFVD-AUFNR     80000005
    SAPLCOIH                       3000     X                                                                               
    0           BDC_OKCODE      =WIAR
    SAPLCOIH                       3000     X                                                                               
    0           BDC_OKCODE     /00
                                            0           CAUFVD-ILART     206
    SAPLCOIH                       3000     X                                                                               
    0           BDC_OKCODE      =ARCH
    SAPLIWO1                           200             X                                                                               
    0           BDC_OKCODE      =WTER
                                            0           RIWO1-CLNOT     X
    Any help would greatly appreciated!
    Best regards,
    André Santos

    Leandro, thanks for the answer!
    The BDC recording does not work when executed visibly or step by step. After some extensive debugging, I realized that the final screen (the technical complete confirmation screen) is not an actual subscreen, even though it has its own number. That screen is actually generated by an FM, so apparently that's why it's ignored when the BDC is executed.
    I found a BAPI to replace that missing step: BAPI_ALM_ORDER_MAINTAIN. However, I'm having a hard time figuring out how to reference the orders I need it to complete. The FM asks for an IT_METHODS table and I couldn't tie the method to the orders:
    it_methods-refnumber = ???
    it_methods-objecttype = 'HEADER'. "That's what I found on the example, not sure whether this is right or not.
    it_methods-method = 'TECHNICALCOMPLETE'.
    it_methods-objectkey = ??? "Maybe the order number itself?
    APPEND it_methods.
    Has anyone used this BAPI before?
    Edited by: André Felipe Oliveira dos Santos on Oct 20, 2010 2:18 PM

  • Technically completed production order

    Hi Friends,
    I am facing one problem in production order. In CO01 i am creating production order and when i try to change the production order in CO02 it is giving error '"Change" is not allowed (ORD .........) .  Some times this problem is coming and sometimes this problem is not coming. If i check in debugging i found that the problem is coming becuase of status TECHO, if that status is active then this error is coming. But i do not understand why this problem is coming only for some times. I am creating production order with same details but the problem is coming some times only.  Any help will be highly appreciatedd.
    Thanks a lot in advance.

    Hi,
    This TECO status is set through CO02 transaction itself.
    Goto CO02 if order is already teco, it will show u the msg.press ok button.
    after that goto Functions->Restrict Processing->Revoke technical completion.
    This way u can undo teco.
    May be your user is setting this status as part of his regular exercise.
    Regards,
    Sunny

  • Change material code in process order or delete process order

    Hi experts,
    While creating a process order in COR1 transaction code, wrong material code was entered.
    Can we change the material code in process order.  If not, what is the complete procedure to cancel or delete the process order.
    Request you to revert.
    Thanks in Advance.
    Regards,
    Farha.

    Dear ,
    One the Process Order has been created with any material either it is wrong code or correct code , it can not be deleted .If it wrong code , then do not  perfom goods Issue -MIGO-261 or through Backflash  and also operation confirmation etc .
    If Goods Issue , Confirmation happend then you need to reverse those txn once again .
    In that case the best oiption will be goto COR2-Enter the Process Order -Select Process Order from Header -Restrict Processing -Choose Technically Complete .
    Now , once you did TECO , then there will not be any farther txanationl posting like Goods Issue , confirmation will not be possible .Likewise , you can also Lock or make set CLOSE  from COR2 in case there is no WIP , Variance .
    Hope this is clear
    Regards
    JH

  • Process Order Details like batch number, mfg date flow to a new process ord

    Hi Experts,
    I have a doubt in Process Order.
    I have two stage production.
    1. Blending
    2. Packing
    I create a process order for blending and assign a batch number and manufacturing date for Blending operation.
    Release the process order.
    Final Confirmation of the process order.
    I complete all the process, Goods Reciept is done.
    Technically completed the Process Order.
    Now my 1st stage Process order is completed and ready for the 2nd stage production i.e., Packing.
    Now I create a new process order,
    here I am having the problem that I need to enter all the details like batch number, manufacturing date etc..
    I want to avoid this in the 2nd process order.
    How to do this i.e., carry forwarding the details of the 1st process order into the 2nd process order.
    Is there any setting required at the back end?
    I was told about Push operation to rectify the above problem. But I am not clear about that.
    Can any one clearly explain about that step- by - step.
    Thanks in advance,
    Regards,
    B. Praveen
    Praveen

    closing thread

  • Goods Movement for Process Order

    Hi PP Experts.
    Is it possible to take goods movement in TECO process order directly.
    is there any other possibility for take goods movements in TECO process order?

    Hi,
    After TECO you can't do Goods Movements. For carrying out , GOOds Movements you need to revoke TECO in process order as following :
    GO to COR2-> Process Order Menu->Functions->Restrict Processing-->Revoke Technical Completion and Save.
    After revoking TECO , You can carry out Goods Movements.
    Hope this helps.
    Revert if any doubt.
    Award points if useful.
    Regards,
    Tejas

  • ReworK: Rework process order

    Hi Experts,
    Can I have an answer to my following question?
    Problem: we want to create a rework process order and we want cost settlement to got to process order (already completed). When I select order as as an account assignement object it raise an error of order status" your bach is archived".
    Can anyone reply?
    Thanks
    Shiv

    Hi shiv
    Can u explain what is the status of ur order?
    Thanks & Regards,
    Irshad

  • Re: Process Order Confirmation

    Dear All,
    I have a query. Is it possible to confirm a process order without completing the RR & UD for the inprocess inspection lot.
    If yes, Please advice.
    Regards,
    Vivek

    Hi'
    Yes example given by you is a std sap.
    But as 03 & 04 inspection lots are behaves differently .....establish the connection between two is bit difficult.
    Just check one possibility of 03 inspection type.
    Go to OPK4 & OPJ8
    Choose your order type and Plant
    Under check heading
    u201Cerror message if no inspection results existu201D.
    Use inspection point in the 03 inspection type task list(routings)
    then do operationwise confirmation.
    Make a setting for partial confiramtion.(in operation overview mainatin:qty,valuation& confiramtion for inspection point)
    When you do partial confiramtion then system will only allows  that much QTy's confiramtion in Co11.
    that means if you do confirmation of only 40 qty of 03 then 04 will only be created with 40 not more.
    I hope this will work.
    Regards
    Sujit

  • Technical completion of Maintenance Order Dates or Reference Dates Settting

    Hi,
    My client has two requirements
    1- In standard, system allows us to take technical completion on previous date, how should I restrict / stop this completion in past? Could I set technical completion possible after atleast 1 month?
    2- Can I stop technical completion before goods movement or set error message while technical completion before goods movements?
    Regards,
    Edited by: PROCESSES EXPERT on Aug 31, 2010 11:01 AM

    For both of the above requirement you can use the user exit IWO10004 Maintenance order: Customer check for order completion
    You have develop a logic on what basis you have to reject the TECO of the order, please consult your ABAPer and discuss with him for more clarification on this.
    Praveen

  • Technical completion of orders

    Hello Team,
    I have a requirement wherein, I want the following two restrictions in the maintenance orders:
    The system should not allow TECO of the maintenance orders, if the WCM related objects are not in CLSD (Closed) and EUG (Untagged) status.
    The system should allow the user to TECO the maintenance orders within 48 hours of the WOCO status; thereafter the user should not be allowed to TECO. After 48 hours the user's manager should be able to TECO the order.
    Please help me to understand how to achieve this requirement.
    Background: Some of the users are setting the order status to TECO even if the equipment is tagged and the system is allowing them to do so. Also some orders remain open without being set to TECO for a long time, this has to be avoided. Running a batch job to set the order to TECO status is not a feasible option for the client.
    Thanks,
    Beryl

    Greetings Beryl,
    Generally, Technical Completion is not a core part of the WCM process; but you could follow Rakesh's suggestion anyway and use the User Exit mentiones.
    Other thing to consider in your process is that WOCO is a prerequisite for TECO; When are you setting WOCO? Consider if there are any checks you could be making at that point; See if you need to implement enhancement spot ES_WCM_BADI, BADI_WCM_ORDER and method IF_EX_BADI_WCM_ORDER~STATUS_WOCO_CHECK
    Do you consider the "Work Completed" when the crew leaves the workplce, or when the WCA is Closed, or when the untagging is done (WCD is Closed)?
    As for your other requirement, you will probably need to develop some check (on table JCDS and the status WOCO (I0426 in the table) and a z-table with the User IDs of the users allowed to TECO past the 48 hour period. You will need the same User Exit IWO10004 Rakesh Mane mentioned.

  • Technically an Process order

    hi Friends,
    i want to technically complete an order but i cannot proceed because of the status CRCR.what can i do to cancel this?thank you so much...

    Allan,
    You need to manually trigger a Process message to the order, to have the status CRFI - Control recipe finished.
    Transaction CO57, to trigger manually a process message with message Category PI_CRST for the process order and Control reciepe combination.
    Use Transaction CO54 to send the Message to the process order.
    Regards,
    Prasobh

  • Read orders which are not technical complete in custom report

    Hi,
    what do you recommend to read all orders which are not from status "technical complete" in a custom report. Is there a function module to acchieve this with good performance or what do you recommend?
    Thanks a lot.
    Kind regards
    Manfred.

    Hi Manfred,
    Since you asked about a function module for use in a custom report, it is likely that you are not looking to use a standard transaction to display the orders.
    The phase of a maintenance order can be found from the field AFIH-IPHAS, where the phases are:
    0     Outstanding
    1     Postponed (currently not used)
    2     Released
    3     Technically completed
    4     Manual deletion indicator set
    5     Historical order
    6     Completed for business (from 4.6)
    So to find non-technical complete - you would select where iphas not equal to 3. If you need to make this selection RFC capable, then you can wrap it in a RFC capable function module
    Regards
    Andrew

  • [SAP WM] Cancel Transfer Order after Technical complete of prodution order

    Hi gurus,
    i have this problem.
    In my SAP WM implementation, i have customizing the PP-WM interface to create automatically the TO from central warehouse to Production supply aera after releasing of production order. The steps are:
    - Release production order
    - Creation of TR  - automatically
    - Ceration of TO to be confirmed (red light) from central warehouse (001) to production supply area (100) - automatically
    Now i would that after technical complete of production order, automatically the TO to be confirmed is cancelled. There is a way to do it?
    thanks and regards.

    Allesio
    I am confused as to why you would want to CANCEL the TO. Surely if the order is complete (technically or otherwise) then the stock has been moved from its source to the order and therefore you would want to CONFIRM it and not CANCEL it.
    As I said if the TO is to take 100 of material A from bin 1111111111 to prod order 9999999999 and you cancel the TO the stock will stay in 1111111111 when in fact it has gone to 9999999999 .
    If your order is to say create 100 pieces of Z and to do this you need 100 pieces of A then you want to CONSUME 100 pieces of A  and GR 100 pieces of Z.
    If you cancel the TO the consumption will fail as the stock is not in 9999999999 but has gone back to 1111111111.
    The other problem is that you will be showing 100 pieces of A in bin 1111111111 which is NOT THERE as the order has used it.
    I hope that this helps
    Frenchy.