Process order variance calculation not taking the GI+Activity confirmation Cost

Hi,
Process oder was settled in the Month of June,2014. Accounting document was generated,but system only considered the GR cost. System was not considered  the GI as well as activity cost on variance calculation. Variance posted GR= Variance.
22nd June,2014 Variance calculated, on 30th WIP entery also reversed with the same amount.
1st July,Order done untecho and no transactions are posted in the Month of July.
Now they would like to settle the Process in the Month of July. system is throwing the error " Status DLV/TECHO reversed after settlement period 006.2014"
Order status was TECO PRT  CNF  PRC  CSER BASC BCRQ CRF No variance calculation status.
Any one faced any similar issue , please suggest me how to proceed.

Hi,
Please check SAP Note 386816 for error KV181.
In general it is recommended to use the Cost estimate of the Process Order (Planned Cost Estimate) for the WIP at target calculation. In additional please pay attention to SAP Note 386816 which explains this procedure and which prerequisites must be met to calculate WIP at targets or the scrap variance. Even if the group counter of the routing is different you can still calculate WIP at targets but only if the message type of message KV181 is set to SPACE by Customizing settings.
Hope this will a bit help to you.
Best regards, Takashi

Similar Messages

  • Process order variance calculation

    Hi All,
    We have Sub- Assemblies which are currently set up in the system as purchased, sub-contracted sub-assemblies. this is how we will procure these the large majority of the time. There will be instances, however, where we will need to build them in house. but when we run cost estimate and mark and release sytem is using sub-contract Quantity structure in cost roll and when we producing we are using different Quantity structure like like BoM and Routing.at the time of variance calulation we are getting errors becuase of conflict in cost estimate Quantity structure and process order Quantity structure.
    How can i solve this issue?any help is appreciated...
    I'm getting the following error..
    Message no. KV181
    Diagnosis
    This message tells you which quantity structure was used by the cost estimate that calculated the target costs, and which quantity structure was used in the actuals.
    The cost estimate that calculated the target costs did not use the quantity structure used in the actuals.
    This means that the cost estimate used a different combination of task list type, task list group, and group counter than in the order itself (such as the production order).
    Example:
    Suppose the target costs were calculated in the standard cost estimate for the material, and that the standard cost estimate for the material is based on the routing identified by task list type N, task list group 50000309, and group counter 1.
    Now suppose the production order specifies a routing identified by task list type N, task list group 50000309, and group counter 2. This would lead to the error.
    System Response
    The system cannot calculate target costs for the valuation of work in process or scrap.
    See also:
    Routing/master recipe in actuals differs from qty structure for target
    Thanks,
    Anusha

    Hi,
    Please check SAP Note 386816 for error KV181.
    In general it is recommended to use the Cost estimate of the Process Order (Planned Cost Estimate) for the WIP at target calculation. In additional please pay attention to SAP Note 386816 which explains this procedure and which prerequisites must be met to calculate WIP at targets or the scrap variance. Even if the group counter of the routing is different you can still calculate WIP at targets but only if the message type of message KV181 is set to SPACE by Customizing settings.
    Hope this will a bit help to you.
    Best regards, Takashi

  • Process order settlement Ko88 not working.

    Hello Sapients,
    i am getting a message:"There are no accrued amounts; settlement is not possible."
    Following are the steps i cariried.
    1.) created a Process order CR01
    2.) did goods issue to the process order using MIGO_GI
    3.) when i run KKAX I am able to the costs in WIP.
    4.) but when i execute the ko88 for the particular process order systme is not settling any but instead giving me a message: "There are no accrued amounts; settlement is not possible."
    5.) Could you please advise if I am missing any thing.
    Thanks and Regards
    Ravi

    Hi Ravi,
    Please, check if you have run the settlement already for period that you wants to do the settle by path  KO88 -> goto -> previous settlement or by  extras -> activate flow trace at Ko88 to analysis the problem.
    Please, also verify the SAP note 179533. This note has some informations regarding the problem.
    Regards,
    Paulo

  • Process order batch number not reflecting in corresponding inspection lot

    Hi QM gurus,
    I am working on inprocess inspection for production. I am creating process order during that time batch no is generated automatically by the system. Now process order is released during this time Inspection lot generated with inspection type 03. Now the problem is in the inspection lot, process order batch number is not reflecting. I have checked all the master data seetings. All seems to be fine. what could be the problem. any settings missed can anybody help me out.
    Thanks
    Vinameath

    Hi Vinameath,
    Go to the Master Recipe (C202) of this Process order/Material. Go to Recipe Header tab and click on the Quality Management Header button.
    Now,go to the Partial Lot Assign field and maintain the value " 0 Partial Lots not supported " and save.
    Then create a new process order and in all probabilities, the batch should appear on the in-process inspection lot.
    Hope this helps you!
    Regards,
    Vinodh

  • GR of Process order - Document does not contain selectable items

    Hi Guru's,
       While doing GR for process order, user is not able to do the GR because of the below message:
    Document XXXXXX does not contain selectable items
    The other user is able to do the GR. The status of process order is
    REL PCNF PRC EXPL EXTS GMPS MANC PDLV. There is overdelivery tolerance so, the delivered quantity is more than ordered qty.
    There is no auto GR setting, no COGI errors, no final delivery indicator, no authorisation issue.
    What could be the reason for this ?
    Thanks in advance.
    Regards
    Kalyan

    Hi Dee Joy,
      I am using MIGO for posting the GR. So, kinldy let me know what setting in MIGO needs to be done.
    Regards
    Kalyan

  • HT4623 My computer is not taking the new update from itunes. It states that i do not have the requirements to finish the Install and that it was Installed incorrectly. I have never had any issue with any previous update regarding iTunes. What is the issue

    My computer is not taking the new update from itunes. It states that i do not have the requirements to finish the Install and that it was Installed incorrectly. I have never had any issue with any previous update regarding iTunes. What is the issue?

    Hi there Double2D,
    You may find the troubleshooting steps in the article below helpful.
    iTunes 11.1.4 for Windows: Unable to install or open
    http://support.apple.com/kb/TS5376
    -Griff W. 

  • The Informatica maps are not taking the parameters from dac

    Hi All,
    The Informatica maps are not taking the parameters from dac. We have tried setting the parameters at DAC level, task level. The parameter file is getting generated by DAC and has correct values as we expect. But when we run a full load from DAC, the initial date in Informatica is being taken as 1/1/1753. Do we need to specify the parameter file name at workflow level?
    Is there any setting that we are missing. Please guide us and let us know the steps we should take to make sure that the parameters that we set at DAC level get passed to the Informatica maps. Also mention this is happening only with dates and other parameters like data source num , soruce and target database information is getting passed to Informatica maps.
    The version of Informatica as 7.4.1 and dac version AN 328, Build date Aug 8 2007.
    Please Help me in this issue.
    Thanks in advance for all members.

    Hi Ananth.v
    Try to make sure that your parameter file's path in Infa is in-sync with the path of DAC files being generated.
    The date you are getting seems strange - which are your Source/Target DB platforms?
    In general take a look at [this thread|   http://forums.oracle.com/forums/message.jspa?messageID=3405906#3405906] , it may make some thing clearer for you.
    Hope it helps,
    Please post if you found a solution,

  • While creating Process Order system has to validate the Batch field

    Hi All,
    While creating the Process Order system has to validate the Batch field which comes under Goods Receipt tab. Please let me know is there any standard user-exit is there for this requirement.
    Regards
    Naveen

    Dear Swapnil,
    Thanks for the reply,
    At the time of creation of process order I am entering the External Batch no as per the logic i.e. first two letters as 08 (for year), next two letter as section 51 (for solid mfg section, which i am planning to maintained in the Z table) and last three letters as 001 (for serial no in this section). so batch no is 0851001.
    Now i want to validate these all letters as per the above logic i.e first two letter should be cross check with current year, and next two letter with Z table for section and last three letters for sr no with previous batch, which is already created for this section.
    Now can you please help me to find out the function exit or screen exit to validate the above requirement at the time of creation of process order i.e. COR1, under the Goods receipt tab. 
    Thanks in advanced
    Naveen

  • Order types, why do we need to create our order types and not use the stand

    HI
    Order types, why do we need to create our order types and not use the standard ones during implementation.

    Hi Raj,
    Well there is no hard and fast rule that you have to copy nad create a new order type. Its just to meet our own requirements that we copy the standard and make the changes if required to meet our business needs.
    And by this way we keep unchanged the standard order type for further use.
    If you are sure that the standard order type satisfies your need you can directly use that only.
    I hope this clarifies the issue.
    Do reward if find useful
    Regards,
    Abhi

  • Help! My phone is not taking the whole screen! (edge around the screen)

    I ve only been using my phone for less than a week. Today my phone was frozen so I hold down the home and the power button to do a reset. However, the apple logo appears and it took forever to get in the home menu so I hold down the buttons to reset the phone once again. The phone did get in the home screen after the second reboot but after that the size of the screen got smaller (Not taking the full screen) I turned off my phone and while I was under the sun i noticed that there is an edge around the screen! It is so noticable even I turned off the phone. So I used a full restore on my phone and now the edge is still there! Can anyone please tell me if they have the same problem before and know how to fix it(Like resizing the screen)? Thanks!!

    Is it a thick border? or just a couple rows? Mine has that, and a lot of electronics have the same thing... they cut the size they need and only use the pixels they want/need to use.
    For example I had a Zune and a new Nano that had the same thing... My Blackberry, and work cell phone... same thing.
    If its a thick border, then yes call apple and get it replaced/repaired.
    Message was edited by: Kalison

  • Why does iTunes freeze when movie download is processing and it will not restart the download but yet it billed my acct for payment already?

    Why does iTunes freeze when movie download is processing and it will not restart the download but yet it billed my acct for payment already? It has been a week now and still not done processing. I get an error message when I try to restart the download.

    What Windows version?

  • HT4060 my ipad has been charging for days and not taking the charge what else can be wrong.?

    i have an apple i pad 16 gb...i have it charging for days and its not taking the charge what else can i try...

    Could be the charger, cable or the iPad.
    Try this first - Reset the iPad by holding down on the Sleep and Home buttons at the same time for about 10-15 seconds until the Apple Logo appears - ignore the red slider - let go of the buttons. (This is equivalent to rebooting your computer.)
    And this - Unplug the charger from the iPad and then replug. May resume charging.
    Or - Recalibrate the battery. See link below.
    The quickest way (and really the only way) to charge your iPad is with the included 10W or 12W (5W on Mini) USB Power Adapter. iPad will also charge, although more slowly, when attached to a computer with a high-power USB port (many recent Mac computers) or with an iPhone Power Adapter (5W). When attached to a computer via a standard USB port (2.5W, most PCs or older Mac computers) iPad will charge very slowly (but iPad indicates not charging). Make sure your computer is on while charging iPad via USB. If iPad is connected to a computer that’s turned off or is in sleep or standby mode, the iPad battery will continue to drain.
    Apple recommends that once a month you let the iPad fully discharge & then recharge to 100%.
    How to Calibrate Your Mac, iPhone, or iPad Battery
    http://www.macblend.com/how-to-calibrate-your-mac-iphone-or-ipad-battery/
    At this link http://www.tomshardware.com/reviews/galaxy-tab-android-tablet,3014-11.html , tests show that the iPad 2 battery (25 watt-hours) will charge to 90% in 3 hours 1 minute. It will charge to 100% in 4 hours 2 minutes. The new iPad has a larger capacity battery (42 watt-hours), so using the 10W charger will obviously take longer. If you are using your iPad while charging, it will take even longer. It's best to turn your new iPad OFF and charge over night. Also look at The iPad's charging challenge explained http://www.macworld.com/article/1150356/ipadcharging.html
    Also, if you have a 3rd generation iPad, look at
    Apple: iPad Battery Nothing to Get Charged Up About
    http://allthingsd.com/20120327/apple-ipad-battery-nothing-to-get-charged-up-abou t/
    Apple Explains New iPad's Continued Charging Beyond 100% Battery Level
    http://www.macrumors.com/2012/03/27/apple-explains-new-ipads-continued-charging- beyond-100-battery-level/
    New iPad Takes Much Longer to Charge Than iPad 2
    http://www.iphonehacks.com/2012/03/new-ipad-takes-much-longer-to-charge-than-ipa d-2.html
    Apple Batteries - iPad http://www.apple.com/batteries/ipad.html
    Extend iPad Battery Life (Look at pjl123 comment)
    https://discussions.apple.com/thread/3921324?tstart=30
    New iPad Slow to Recharge, Barely Charges During Use
    http://www.pcworld.com/article/252326/new_ipad_slow_to_recharge_barely_charges_d uring_use.html
    Best Practices for iPad Battery Charging
    http://www.ilounge.com/index.php/articles/comments/best-practices-for-ipad-batte ry-charging/
    Tips About Charging for New iPad 3
    http://goodscool-electronics.blogspot.com/2012/04/tips-about-charging-for-new-ip ad-3.html
    How to Save and Prolong the battery life of your new ipad
    https://discussions.apple.com/thread/4480944?tstart=0
    Prolong battery lifespan for iPad / iPad 2 / iPad 3: charging tips
    http://thehowto.wikidot.com/prolong-battery-lifespan-for-ipad
    iPhone, iPod, Using the iPad Charger
    http://support.apple.com/kb/HT4327
    Install and use Battery Doctor HD
    http://itunes.apple.com/tw/app/battery-doctor-hd/id459702901?mt=8
    To Extend a Device’s Battery Life, Get to Know It Better
    http://tinyurl.com/b67c7xz
    iPad Battery Replacement
    http://www.apple.com/batteries/replacements.html
    In rare instances when using the Camera Connection Kit, you may notice that iPad does not charge after using the Camera Connection Kit. Disconnecting and reconnecting the iPad from the charger will resolve this issue.
     Cheers, Tom

  • I lost all of my calender info and did not have the cloud activated. Any ideas on why that happened?  Any idea if I can get that back?

    I lost all of my calender info and did not have the cloud activated. Any ideas on why that happened?  Any idea if I can get that back?

    Not sure why this happened, but are you syncing calendar events direct with a supported calendar app on your computer?
    If not, calendar events are included with your iPhone's backup which is updated by iTunes as the first step during the iTunes sync process. If you haven't synced your iPhone with iTunes since this data went missing, you can try restoring your iPhone with iTunes from your iPhone's backup. Do not sync with iTunes before doing so, and do not update your iPhone's backup before doing so when prompted.

  • Hello I have a problem with the iPhone 5 does not know the account activation lock

    Hello I have a problem with the iPhone 5 does not know the account activation lock 

    You will not be able to access the device without the account activate lock password. IF you have the receipt and other proof of purchase you may have sucess with contacting apple and asking them for assistance. Depending gretaly on how much proof of purchase you have.
    Good luck Friend.

  • Production order variance calculation RKKKS000

    Hi Gurus,
    we have a strange issue, where system is taking more than 28 hours to calculate variances by using program RKKKS000. because of this business en-countering issues for month end processes, I came to know one of the program which has the ability to select order type and number range KKS1 RKKKS1N0.
    can this job be used in 4.7 version if so how to find the order types and muber range for selection. if business wants to use Existing program RKKKS000 is there any way to reduce Job performance (less than 10 hours).
    Thanks,
    Sree

    Hi,
    set status DLFL for the orders that should not be processed anymore, thats the best way to reduce the variance calculation runtime.
    Check SAPNET note 393896 for other performance tips (parallel processing,...)
    BR Christian

Maybe you are looking for

  • Customer exit ==== Urgent

    Hi All, I ,  have a requirement where i have a purchasing organization to be displayed on the selection screen of the quesry and when the user executes an F4 on the selction screen he should only see the Purchasing Organization which have Classificat

  • If expressions

    How do I create an expression if I want to return a value if another value is > or < a set value? For example: if ( Subtotal < 25.00 ) then ShippingCharge = 6.00 elseif ( Subtotal > 25.01 or < 50.00) then ShippingCharge = 8.00 elseif ( Subtotal > 50.

  • Replace standby server in CCX 8.02su3 HA cluster

    Hej. I am replacing the standby server (secondary node) in a CCX 8.02su3 cluster because of hardware failure. I can only find the procedure for replacing the primary node on cisco .com. Here is what I attend to do : 1. Remove secondary node (server n

  • Updated iPad2 with OS5 but forget backup password, how do I retrieve password or go back to before update since I saved password on iPad

    Updated ipad2 with OS5 but forget my backup password, can I reset from previous setting and try again since my password is somewhere on my iPad?

  • Ability to click button again before thread finishes

    import java.awt.*; import javax.swing.*; import java.awt.event.*; public class A      public static void main(String[] args)           JFrame frame = new JFrame();           Container content = frame.getContentPane();           content.setBackground(