PRODUCTION ORDER--Qty changed after one operation----URGENT

Dear Experts
        Hope u all R doing well
In the production order,after one operation completed(whether it is first ,second  or last ) the system is allowing to change the qty.
but we want the system to disallow  the qty change.
could anybody can help, is there any configuration settings inside?
waiting for your valuable response
Thanks in advance

Hi,
Sorry for the delay.
Pl. follow the steps below.
1. Create a status profile Eg: s1 usng t.code bs02.
2. Enter status no. as 1, status as CRTD, a description, tick Initial status & lower status no. as 1 & higher status no. as 2.
3.In the second line enter status no. as 2, status as REL, a description,  & lower status no. as 1 & higher status no. as 3.
4.Choose Object type tab.
5. Choose PP/PM: Order header.(tick)
6.Then come back to main screen & double click REL.
7.Click the create icon in the top.
8.Choose Release & then choose radio button under <b>SET.</b>
9.Then come back to main screen & again double click REL & then choose create & select change & check the radio button under <b>FORBID</b> & then save.
10. In t.code OPJH(order type), choose your order type & then assign the status profile( Eg:S1)
11.Now convert the planned order into production order.Release the order & save.
Further changes cannot be made in the production order.
Pl. give feedback after testing.
Regards,
S.D.Senthilkumar

Similar Messages

  • Production order qty change tracking

    Dear gurus,
    In a production order qunatity change should be tracked.Say for eg prodn order qty is 100.User is changing  to 200.As a client requirement they want he change historya of PIR change history.The same tracking reuired for Component change qty.plz through some light.Without OCM any other solution plz guide me
            Please through some light
                             -Guna

    Hi,
    There is a way by which the quantity field in the production order can be fixed and made non modifiable
    You need to create a status profile in bs02
    Double click the status profile.
    Enter the user status as crtd
    Tick the initial status as enabled
    Place the cursor on the status profile
    Select the object type as PP ORDER HEADER
    Now choose the user status
    Double click the user status
    Goto create mode
    select change and set forbid radio button
    save.
    Assign this status profile to order type in opjh tcode.
    Now once you have created the production order the system automatically forbids any change.
    And
    OCM is option to track it or authorization feild to restrict it.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Jul 22, 2008 10:38 AM

  • Production order quantity changes

    Hi Guru's,
                  Please help me to trace the production order changes.
    for example: order 1 = 100 and later I changed to 200
    how can i trace it.please explain the steps to follow.
    Thanks
    Satya

    Dear Sathyanarayana,
    Production order Changes can be traced only using OCM - Order Change Management.
    So you have to activate Order Change Management,Check these links
    [OCM Link1|Re: Changes to item in prod order]
    [Link for using an OSS Notes instead of OCM|Re: Production order qty change tracking]
    Regards
    Mangalraj.S

  • Deactivating production order changes after 1st operation is confirmed

    Hi,
    I want to deactivate production order changes after 1st operation is confirmed through CO11n.Ie. production order qty should not be allowed to change after 1st operation is confirmed.
    Expecting ur immense help on this.
    Regards,
    JS Karthi

    Dear ,
    PPCO0007
    EXIT_SAPLCOZV_001 Exit when saving production order
    Provide the restrictions in coding, so that when saving the order check for the order status PCNF or CNF and quantity change.
    Check thread
    first operation confimed - after system allowed changed order qty
    Regards,
    Ishwar

  • Production Order qty in Report Painter

    Can we get Production Order qty in Report Painter?
    I have tried and used couple of Libaries but the values are not getting updated in report.
    Can anybody please tell me which Library and Table combination to to get the result.
    Kami

    Hi
    Prod order qty (Target / Plan / Actual) is available in KKO0 reports
    To activate them:
    a. OKN0: Assign a cost comp str here and choose Product Group = Material Group.. Transport this setting
    b. Run KKRV every month after period end settlements are over...
    c. Finally execute KKO0 reports
    b and c you need to do every month... a is one time setting
    br, Ajay M

  • I need Checking in Production Order Qty

    Hi all,
    In our industry we are creating Production Order From Sales Order (MTO Scenario) by using T.Code CO08 or CO01 T.Code with out running MRP.Now if anybody intend to change the PO qty by using CO02 T.Code system allows and as a result the Sales Order Qty and Production Order qty mismatch.Now please give me solution so that anybody cannot change the production order qty and it must be same as sales order qty.
    I am waiting for your valuable suggestion.
    Thanks & Regards
    Nirmal Sharma

    Hi,
    1. I dont think this is possible in any standard configuration.
    2. You can utilise the exit   EXIT_SAPLCOBT_001 and write our logic inside that
    3. This exit is validated when ever we save the order,
    4. The abap code should be written such that each time it should check for the sales order / itme no and check the quanity to be matching if it fails it should give error
    note: in this case if you are trying to creat multiple production order for one single salesorder/item number then it will not be possible or another logic is to be incorporated.
    reg
    satheesh

  • In inprocess inspection lets say the production order qty is 20. i would want only 1 no. to be inspected while inprocess inspection is configured. kindly guide. Regards,Mathew

    In inprocess inspection lets say the production order qty is 20. i would want only 1 no. out of the 20 to be inspected while inprocess inspection is configured. kindly guide.
    Thanks in Advance
    Regards,
    Mat

    Hi Mathew,
    Create sampling procedure with fixed sample and give sample size = 1. Assign this sampling procedure for the characteristics of the in-process materials in Routing/Master Recipe etc. For sample size calculation at-least one characteristic should be required characteristic for the Material.
    Thanks&Regards,
    kumar

  • Production Order Qty- Inspection Lot Qty

    Hi Guru's,
    When an  production order is relreased an inspection lot is creaetd with the production Qty. But later when we change Qty for  the released Prodction Order the inspection lot  Qty is not changes it remains the same as previous Order Qty.
    Say for Ex: intial Prod  order qty (MTS Scenario) is 200 (production order released). Inspection lot Qty is 200.
    Later  User changes the Qty to  100. Our problem is the inspection lot qty  does not change ramins the same as 200. Can inspection lot qty be changed automically on change of production order qty .
    What settings need to change? pls advise
    Regards,
    Sankaran
    Edited by: Sankaran M on Oct 10, 2008 9:41 AM

    Hi Sankaran,
    It is possible if the user not doing any result against existing lot.
    Follow the Below step.
    Your Existing order Qty = 200 Nos Inspection lot no 300000200.
    Now you want change the Qty as 200 to 100.
    Before change the qty, first you have to delete the Inspection lot Go to CO02 -> Got to menu Functions -> Inspection lot -> Delete.
    Now change the Qty 100.
    And Again go to Functions -> Inspection Lot -> Create. and save the order.
    Now system will delete the Old indpection lot and create the new inspection lot.
    Qty : 100 Inspection Lot 300000201.
    Revert further clarification.
    Regards,
    S.Babusingh

  • Confirmation of the production order qty equal to sales order qty

    Hi Experts,
    I need to control the confirmation of the production order should be equal to sales order qty.
    I'm having the scenario as follows
    If sale order qty for X material = 3
    while running the MRP, system will plan the order qty as 8 because of we maintained rounding profile in the Material master and enhancement we used for this.
    Rounding Profile Qty=5
    Total Production Order Qty=8.
    But, finally they will do the GRN for sales order qty only, remaining will be used for testing purpose.
    So, the confirmation also has to happen for only sales order qty. There, we need to control the qty based on the sales order.
    Is there any exit or Enhancement is available for this.
    Please help me.
    Naren

    Hi,
    Exit for confirmation check is CONFPP04.
    However, opening orders for quantities higher than demand and leaving pieces undelivered and unconfirmed in production orders does not make sense. I could not get the requirement of incresing production quantity by adding rounding value? Moreover, if rounding is to be used for test purposes, why not do you receive them into stock? Why don't you receive 8 pieces into stock, deliver 3 pieces to sales order and transfer 5 pieces to related department?
    If it is because of MRP and you really do not want to produce extra 5 piece immediately, you may use material reservation or any other form of demand for 5 pieces, use EX for lot size calculation and have MRP create two planned orders for sales order and testing requirement, then you can convert planned order for sales order requirement into production order and continue processing.
    Regards.

  • Excess Qty confirmation than Production order qty

    Hi
    SAP Experts
    Is it possible to confirm excess qty of yield in co11n against Production order qty.
    pl. guide me the steps required.
    with Best Regards
    Yogesh

    Yes,
    If you do not waht to conform excess qty than the production order qty, then the following are the options
    - as our friend told in Work scheduling view the under/over delivery tolerance should be zero and unlimited delivery tick should not be active
    - In production order the under/over delivery tolerance should be zero and unlimited delivery tick should not be active.
    - In OPK4 fior the combintaion of plant and order type the following confirmation parameters are to be maintained
    Under delivery - X error if qty below under delivery tolarance
    Over delivery - X error if qty above over delivery tolarance.
    With this settings you can avoid what you wanted.

  • Production Order BOM change

    Dear Expers,
    How can i restrict the Production order BOM Change. Please tell me with the steps.
    Other than screen variant.
    Regards
    Raghu

    Hi,
    To do this you can use below mentioned processed.
    1. create a user status and give approval to the order at creation and the user will not be able to change any thing in the process order.
    2. You can use user exits to restrict changes changes at "materials" screen.
    Hope this will help.
    regards,
    kaushik

  • Purchase Order qty changed from 10 to zero, system takes as one

    Hi experts,
    SRM 7.0 EHP2 without EP. PO is created with 10 line items and qty of each line item is greater than zero. The qty of one line item is changed to zero and clicked/saved. The system takes the qty as one inspite of original qty more than one changed to zero.
    Thanks
    Vijay

    Hi,
    Standard behaviour shouldn't allow to choose zero as quantity, when you enter a zero quantity for a line item, when you choose check / order, system throws a error message by asking please enter quantity.
    Coming to rounding of to '1', it depends on UOM decimal place's setup in SRM for that particular unit of measure.
    You can verify this in CUIN > choose UOM > choose details> check the field decimal place's. By standard it will be zero, so when you choose any decimal place less then 1, it will automatically becomes '1'.
    You can change this by entering some decimal place's to be considered before rounding off, so that system allows to create fractional value between 0 to 1.
    Regards,
    Govardhan 

  • Production order Qty update-urgent.

    Hi all,
    I want a query that must not allow me to  update the Qty in the Production order.Once production order created from the MRP,it should not allow me to update any Qty at the production orer level what should be query its urgent.
    mona.
    thanx in advance.

    Hi Mona,
    Query is only for report.  It will not be the tool you are looking for this task.
    The SBO_Transaction_Notification SP can be used instead. There are quite a few threads discuss this topic.  Try search in the forum to find what you need.
    Thanks,
    Gordon

  • User exit for sale order qty change

    Hi all,
    In our industry we are creating Sale Order for MTO Scenario by using T.Code VA01 . Most of the time after taking the MRP run and raising PO for BOM components, Users are changing the qty in the sale order . eg. and due to that it is becoming difficult to make necessary change in production programe. .Now please give me solution/ userexit  so that anybody cannot change the sale  order qty and it must be check the authorised userid to do necessary change in sale order.
    I am waiting for your valuable suggestion.
    Thanks & Regards

    Hi LIMAYE,
      You can use user exit include 'MV45AFZZ'.
    Make necessary changes in FORM USEREXIT_MOVE_FIELD_TO_VBAP.
    XVBAP will contain the old values before making the changes. You can comapare the quantity wtih VBAP field.

  • Production Order  maintain/change

    Hi,
    I need to change operations of a production order via RFC. Therefore I found the function "CLOI_CHANGES_UPL_31" but I have no idea how to use this function. Can anybody give me an example how to change (or even better how to add) operations of a production order.
    An example:
    I've a PO (Nr. 60028803) including three operations 0010, 0020 and 0030. Now I need an operation 0040. How can I add this one via RFC?
    Thanks for any help,
    Joerg

    Hi,
    I would like to update Batch Number into Production Order and by using this CLOI_CHANGES_UPL_31 FM it return no error but when i checked on the BAPI_PRODORD_GET_DETAIL and found that the Batch Number did not change.
    Can anyone be my mentor to guide me how to update batch number into a production order?
    Thanks and Regards,
    WannYang

Maybe you are looking for

  • Boot Camp no longer available after Mavericks upgrade?

    Hi, I've recently upgraded to Mavericks (MacBook 13" 2010). Since upgrading I have not been able to access BootCamp during start up. The partion still exists, but there seems to be some problem(s) with it. I've attached a screen shot of the issue as

  • Movement type assigned to GL Account

    Hi  , I tried using the TCODE  , OMJJ,OBYC, thyanks a lot it did serve my purpose a bit  , but then  ,  i want to see where exactly and how it hits the gl account  where  the credit  and debt takes place , for example if i use movemnt type 521 , what

  • Standard Macro and Functional Module in HR -Programming.

    Hi friends, Could i know the difference between a standard macro and a function module in hr programming. how do we have to use that and what are the different std macro's and functional modules used in HR-Programming... Thanks in Advance.. Regards S

  • Make daemons start after boot?

    Can I make daemons start after the boot has ended? Netcfg uses about 10 seconds connecting to my wireless network, and the mounting of my windows share (trough fstab, using cifs) takes even longer. Therefore, I'd like to know if there's a way to star

  • Please answer for these technical questions

    Post Author: [email protected] CA Forum: Deployment how many members a project contains and what are their roles and responsibilities? How many no of universes and reports a project contains? Two typical sceneriou2019s while creating universes and Re