Project Server 2013 - After host header defined, WSSCreateSiteFailure
after configuring webapplication and provisioning PWA (URL: http://<server_name>:<port>/pwa), i have extended the webapp to use host header and SSL protocol. now URL become something like this https://mycompany.com/pwa
if users access the site using this new URL, project site creation gives an error in queue as following. in ULS logs there is nothing useful as well. and if i open/publish the same project again, it gives me an error that project site is already in use.
once point which may can makes a difference is that security certificate for above URL is yet to be configured, and due to this users are getting this certificate error in their browser while access site. could
this be a cause?
however if users use the site using the same old URL, project site get successfully created.
any guesses?
General
CreateWssSiteContent: Creating project site failed! Project Uid=6b33f03d-b3af-e311-93fd-00155d01a359, site URL=https://epm/Projects/Project Site Teset, site name=Project Site Teset. :
WSSCreateSiteFailure (16400). Details: id='16400' name='WSSCreateSiteFailure' uid='0809ce4e-b3af-e311-93fd-00155d01a359' projectUID='6b33f03d-b3af-e311-93fd-00155d01a359' workspaceUrl='https://epm/Projects/Project Site Teset' projectWorkspaceName='Project
Site Teset'.
Queue:
GeneralQueueJobFailed (26000) - CreateWssSite.CreateWssSiteMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='0909ce4e-b3af-e311-93fd-00155d01a359' JobUID='df8efb43-b3af-e311-93fd-00155d01a359' ComputerName='191cfefc-7d92-4801-a9d5-37d90cb6465e'
GroupType='CreateWssSite' MessageType='CreateWssSiteMessage' MessageId='1' Stage='' CorrelationUID='1fe97e9c-2dfa-d087-6465-e3809f2d856d'. For more details, check the ULS logs on machine
191cfefc-7d92-4801-a9d5-37d90cb6465e for entries with JobUID
df8efb43-b3af-e311-93fd-00155d01a359.
Khurram Jamshed - MBA, PMP, MCTS, MCITP (
Blog, Twitter, Linkedin )
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”.
Hey Paul, good to see you mate :)
and yea i think now we are hitting more on the target.
patch level is 0, its a RTM version without any update. and applying any kind of patch is also not easily possible, because its one server hosting a very complex and huge SharePoint portal as well.
with your clue, i have got Brian's blog related to this exact issue: http://blogs.technet.com/b/projectsupport/archive/2013/01/10/project-server-2013-project-sites-alternate-access-mapping-and-themes.aspx
here he has mentioned a workaround until we apply patch, and also quoted it as a good way of configuring.
From Brian's Blog:
The first would be to use the fully qualified domain name (FQDN) as the Default zone Url, and then add an Internal
Url to the same Default zone for the server name – http://Project2013/.
Another option would be to set the FQDN as the Default zone Url and then add the shorter version as the Intranet zone or Custom zone. Either of these would mean that the strings wouldn’t get confused and the site would get created.
now in my case, assuming machine name is: ServerA, and while creating webapplication which going to host PWA site i am defining required host header assuming: epm.
provisioning my PWA using this web app and defing PWA path as "Project" because its a migrated site so i have to use the same name, and the URL i am going to get in the end would be: http://epm/project
AAM is, default zone: http://<server>:<port> and intranet zone: http://epm
is the above complying with the first option of Brian?
Khurram Jamshed - MBA, PMP, MCTS, MCITP (
Blog, Twitter, Linkedin )
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”.
Similar Messages
-
Workflow in Project server 2013 online not going particular stage after Approval
Hi All,
i have created workflow using sharepoint designer 2013 for project server 2013 online. and i have also set the approver after the first stage. when i create a project using this workflow, project is created successfully and the approval task also go for
a approval to specific user. and i have set the property that after approval it has to go on specific stage. but the problem is when user approve the task it shows approved but my stage in workflow is remain same. it is not going to any stage.
i don't know why this type of problem is occur.
FYI, i have created same workflow for Project server 2013 on premise(Which is installed in my server) and
it is working fine but when i want to deploy this workflow in
project server 2013 online its giving error.
so please help me to solve this type of issue.
ThanksI am also experiencing issues with this. After the approval task is completed, the Workflow gets cancelled with the following message
RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
bookmarkManager, Location resultLocation)
All other desired workflow actions work as expected. Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
workflow fails.
What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
not COMPLETED, which is what would be expected.
Has anyone seen this - any potential resolution? -
How do I create a project site after I publish a project in Project Server 2013?
How do I create a project site after I publish a project from project pro 2013 in Project Server 2013? I'm trying to look for an option in the ribbon but haven't found any.
Thanks
James T.FHi James,
See in the article the procedure for site provisionning settings.
Note that the project site is created based on the template associated to the chosen project type (EPT) when the user first publishes his project. Be aware that if you allow the user to choose weither or not he'll create a sharepoint site when publishing
his project, he will be prompted in Project Pro with a dialog box giving the choice to create or not the site.
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS | -
After installing Project Server 2013 (without updating SharePoint Server 2013 SP1))
I am facing the problem while opening project web app. I configured the SharePoint 2013 and project server 2013. Here is the detail what I performed the steps:
OS Server 2012 R2, SQL Server 2012, SharePoint server 2013 version
15.0.4420.1017, Project Server 2013 version
15.0.4454.1000. SharePoint configured and running successfully. After project web app site provisioning successfully completed. I got the below error.
Microsoft.Office.Project.PWA.WebParts.PWAPart' from assembly 'Microsoft.Office.Project.Server.PWA, Version=15.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429c' cannot reduce access.
I run this psconfig -cmd upgrade -inplace b2b -wait -force. But still getting same error.
Previous steps:
Earlier I had also tried to install SharePoint Server 2013 SP1 "3823428". After the installation SP1 some of sharePoint site features suddenly stopped e.g: Cannot browse "Service Applications -->
Manage service applications" option even after re-start the server. This was previous error after upgrading SP1
"Method 'get_IsClientValid' in type 'Microsoft.SharePoint.WorkflowServices.WorkflowServiceApplicationProxy' from assembly 'Microsoft.SharePoint.WorkflowServices,
Version=15.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429c' does not have an implementation"
Anyone can help me!!! Thanks...
Faisal Numanhello,
For SP2013 and PS2013 to work properly on Windows Server 2012 R2 you need to use the SP1 install media for both, download SharePoint 2013 with SP1 and Project Server 2013 with SP1
http://support.microsoft.com/kb/2891274
http://blogs.technet.com/b/office_sustained_engineering/archive/2014/03/03/announcing-availability-of-slipstreamed-office-2013-and-sharepoint-server-2013-with-sp1.aspx
http://blogs.technet.com/b/projectsupport/archive/2014/02/25/project-2013-and-project-server-2013-service-pack-1.aspx
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS -
After Migrating to project server 2013 some of my Mpp are not opening in project professional
After migrating to project server 2013 from 2010. my some of mpp are not opening in project professional.
project professional taking some time and then showing checkin error. There are no logs on project server to this issue.
but you can see these project in project server 2013 without issue. I have also tried the EditLink function. but result is same project professional not able to open. Check in error.Hello,
Can you try this:
Open one of those Projects in PWA to edit in the browser
make a slight change (new dummy task etc.)
Save and Publish from the web
Close and check in from the web
Wait for the jobs to complete
Open project professional
try and open the same project again from there
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS -
Problem after installation Project Server 2013 CU September 9, 2014
Dear All,
I have some problems after installation
Project Server 2013 CU September 9, 2014 (Hotfix 2883072) on 3 level farm
Before installing CU, I have installed
SP1 for Project Server 2013, installation and configuration was successful.
Then I have installed CU and I have not get any errors during installation process. Then I have restarted servers and in SharePoint health analyzer got an error about patch/installation status
on WFE server.
I checked in Windows installed updates and hotfix is installed. I checked in SharePoint Update and Upgrade history and there were no errors during installation. But when I checked in Manage
Patch Status list I found an information:
Language Pack for SharePoint and Project Server 2013 - Russian
Microsoft Project Server Russian Language Pack 15.0.4420.1017 Installed
Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
15.0.4649.1001 Missing/Required
Microsoft Project Server 2013
Microsoft Project Server English Language Pack 15.0.4571.1502 Installed
Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
15.0.4649.1001 Missing/Required
Service Pack 1 for Microsoft Project Server 2013 (KB2880553) 64-Bit Edition
15.0.4571.1502 Installed
Microsoft Project Server Web Front End Server
15.0.4571.1502 Installed
Hotfix for Microsoft Project Server 2013 (KB2883072) 64-Bit Edition
15.0.4649.1001 Missing/Required
Service Pack 1 for Microsoft Project Server 2013 (KB2880553) 64-Bit Edition
15.0.4571.1502 Installed
If I run installation again I get message that nothing will be updated - no update needed.
Please help, how I can install missed packages?The problem was solved !
I solve it using two ways:
1. I have installed the hotfix for Project Server - Hotfix for Project Server 2013 October 14, 2014 KB 2889959 (Projectserverwfe-x-none.msp, Projectservermui-Language-Code.msp)
2. using command
Psconfig -cmd upgrade -inplace b2b -force -cmd applicationcontent -install -cmd installfeatures -cmd installcheck -noinstallcheck
After two actions I was able to run SharePoint Configuration Wizard and upgrade database. Configuration completed successful. -
In Project server 2013, users are getting Project Site Provisioning Pop-up even after Operational Policies set as Do
not create a sites.
We can use “Deny” Global Permission, “Manage SharePoint Foundation”, which controls Project site creation/ delete
as temporary workaround however want to know is this know defect in Project server 2013?
Any suggestion would be highly appreciated.
Thank youHi Raushan,
I can reproduce the same behaviour in my environment. It pops-up the dialog box when Project Site Provisioning settings set to 'Do Not Create' in the Central admin for the Project Web App.
As you mentioned already you can control it via permissions as an work-around.
Alternatively, you can also ask users to select the check box 'Don't show this again for this project'
Cheers, Badal -
No PDP found after restoration of Project Server 2013 !!
Hi All,
I have an issue while performing database restoration of project server 2013. I have followed below mentioned two links for backup and restore procedure
http://technet.microsoft.com/en-us/library/dd207307.aspx
http://technet.microsoft.com/en-us/library/dd207305.aspx
Everything works great ! restored successfully all projects, custom tables, group settings etc. But while opening the projects it prompts error that unable to find PDP etc something like that.
Can anyone please help in such situation as how can we get the PDP pages in database restoration and what is the reason behind that ? Is there anything that I am missing?
REGARDS DANISH DANIEHello,
Sounds like a new PWA site collection was created as part of the restoration? The PDPs are stored in the content database. If you are rolling over between environments (prod to test for example), see the post below:
http://pwmather.wordpress.com/2013/05/02/projectserver-2013-environment-migration-rollover-steps-powershell-ps2013-msproject-sp2013/
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS -
After Project Server 2013 SP1 update (without updating Sharepoint Server 2013)
I get this error entering the PWA root:
Derived method
'RequiresWebPartClientScript' in type
'Microsoft.Office.Project.PWA.WebParts.PWAPart' from assembly
'Microsoft.Office.Project.Server.PWA, Version=15.0.0.0, Culture=neutral,
PublicKeyToken=71e9bce111e9429c' cannot reduce access
SharePoint Server 2013 version: 15.0.4420.1017
Project Server 2013 version: 15.0.4569.1506
There is no SP1 uninstall process? Totally lost!Hi Ximet,
If you go to Central Administration > System Settings > Manage Servers in this Farm. Do you see Upgrade Available for the servers.
If they show Upgrade Available, can you run the SharePoint Config Wizard one more time or you can also try running the command "psconfig -cmd upgrade -inplace b2b -wait -force"
Just curious to know if the issue is because the binaries have not been updated properly.
In case the issue persists and is impacting your business, I would suggest that you raise a support ticket with Microsoft so that we can further assist you on the case.
Cheers! Happy troubleshooting !!! Dinesh S. Rai - MSFT Enterprise Project Management
Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading the thread. -
How to handle PSW approval task in project server 2013 through declarative workflow VS 2013
Hello,
Plz explain in detail handling PSW approval task in project server 2013 through declarative workflow VS 2013
bcoz when using am posted on with this error when i try to approve the item
"This list item has not been created by the workflow.you cannot apply this content type"
any help would be appreciated!!!!
Thanks regards, Vignesh.I am also experiencing issues with this. After the approval task is completed, the Workflow gets cancelled with the following message
RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
bookmarkManager, Location resultLocation)
All other desired workflow actions work as expected. Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
workflow fails.
What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
not COMPLETED, which is what would be expected.
Has anyone seen this - any potential resolution? -
PowerView In Project Server 2013 is not working
Hi All,
I am working on environment with Project Server 2013. In report part i am not able to see or view only power view reports.
I am testing this with default report provided by Microsoft, where other reports (power pivot) are working fine.
My power view report is not showing any error, it is simply gets opened as blank sheet.
Quick replies and help will be appreciated.
Note: I have installed silver light latest version too.
Thanks
AbbasI am also experiencing issues with this. After the approval task is completed, the Workflow gets cancelled with the following message
RequestorId: 60d96368-4cb4-b059-8086-604972a92e60. Details: System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary. at Microsoft.Activities.Hosting.Runtime.Subroutine.SubroutineChild.Execute(CodeActivityContext context)
at System.Activities.CodeActivity.InternalExecute(ActivityInstance instance, ActivityExecutor executor, BookmarkManager bookmarkManager) at System.Activities.Runtime.ActivityExecutor.ExecuteActivityWorkItem.ExecuteBody(ActivityExecutor executor, BookmarkManager
bookmarkManager, Location resultLocation)
All other desired workflow actions work as expected. Emails are sent, project is moved from stage to stage, however as soon as the workflow approval task is completed, either Approved or Rejected, the Internal Status is changed to Canceled and the
workflow fails.
What is interesting is when the Approval task is completed, the approver will receive an email notification that the task was CANCELLED or DELETED....
not COMPLETED, which is what would be expected.
Has anyone seen this - any potential resolution? -
Error while creating a Timesheet - Project Server 2013
Hi everyone,
One of user of PWA encounters an issue when he tries to create a timesheet. This error only occurs with a timesheet of
a specific period, he can create all the other timesheet.
So, when he creates the timesheet, this error occurs : "The timesheet creation failed, because of problems with Project Web App or with data validations"
After reloaded the list of the timesheets, a link to go to the specific timesheet
is available but if we click on it, we have this error :
"View Failue - The view failed to load"
I think , this error occurs
because the timesheet is not realy existing even if we have a link to it.
In the log (full log at the end), I've got this error :
Exception occured in method 'TimeSheet.CreateTimesheet' System.ArgumentException: These columns don't currently have unique values.
I've found this link with the same kind of problem :
http://social.technet.microsoft.com/Forums/projectserver/en-US/b0a92afc-11fc-40ef-9a44-357d953b31f6/unable-to-open-or-create-timesheets-these-columns-dont-currently-have-unique-values?forum=projectserver2010general but I've checked and published all the
user project but still have the error.
Have you got any idea where are these columns ? How can I found them without checked every project of PWA ?
Thanks,
Patmol
Full logs, for information :
[bucketHash:E3B9DED0] Exception occured in method 'TimeSheet.CreateTimesheet' System.ArgumentException: These columns don't currently have unique values. at System.Data.ConstraintCollection.AddUniqueConstraint(UniqueConstraint constraint) at System.Data.ConstraintCollection.Add(Constraint constraint, Boolean addUniqueWhenAddingForeign) at System.Data.DataTable.set_PrimaryKey(DataColumn[] value) at Microsoft.Office.Project.Server.DataAccessLayer.Generated.TimesheetDalBase.ReadCustomFieldsForAssignments(ISet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportCustomFields(HashSet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportActualsAndCustomFields(IEnumerable`1 assignmentUids, ISet`1 userImported) at Microsoft.Office.Project.Server.BusinessLayer.TimesheetLoaderForGrid.Load() at Microsoft.Office.Project.Server.BusinessLayer.TimeSheet.CreateTimesheet(TimesheetDataSet dsDelta, PreloadType preloadType) at Microsoft.Office.Project.Server.Wcf.Implementation.TimeSheetImpl.<>c__DisplayClass45.<CreateTimesheet>b__44() at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace: at Microsoft.Office.Project.Server.Native.dll: (sig=6ea170d1-988e-4153-9f1d-0305c0ea0309|2|microsoft.office.project.server.native.pdb, offset=3C1E) at Microsoft.Office.Project.Server.Native.dll: (offset=1255D)
Watson bucket parameters: Microsoft Project Server 2013, ULSException14, 070f6ea0 "project server", 0f0011db "15.0.4571.0", ea364808 "system.data", 0400766f "4.0.30319.0", 52310bef "thu sep 12 02:33:51 2013", 00000e02 "00000e02", 00000020 "00000020", 44395864 "argumentexception", 00101621 "aeby7"
Error is: GeneralUnhandledException. Details: General Unhandled Exception in _TimeSheet.CreateTimesheet_ Attributes: System.ArgumentException: These columns don't currently have unique values. at System.Data.ConstraintCollection.AddUniqueConstraint(UniqueConstraint constraint) at System.Data.ConstraintCollection.Add(Constraint constraint, Boolean addUniqueWhenAddingForeign) at System.Data.DataTable.set_PrimaryKey(DataColumn[] value) at Microsoft.Office.Project.Server.DataAccessLayer.Generated.TimesheetDalBase.ReadCustomFieldsForAssignments(ISet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportCustomFields(HashSet`1 assignmentUids) at Microsoft.Office.Project.Server.BusinessLayer.Timesheet.ImportActualsAndCustomFields(IEnumerable`1 assignmentUids, ISet`1 userImported) at Microsoft.Office.Project.Server.BusinessLayer.TimesheetLoaderForGrid.Load() at Microsoft.Office.Project.Server.BusinessLayer.TimeSheet.CreateTimesheet(TimesheetDataSet dsDelta, PreloadType preloadType) at Microsoft.Office.Project.Server.Wcf.Implementation.TimeSheetImpl.<>c__DisplayClass45.<CreateTimesheet>b__44() at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) . Standard Information: PSI Entry Point: Project User: i:0#.w|wavenet\cev Correlation Id: 9709e41b-9a18-e411-941e-00155d029b05 PWA Site URL: http://intranet.wavenet.lan/PWA SA Name: Project Server Application PSError: GeneralUnhandledException (42), LogLeve...Hi Patmol,
Have you tried to go to the previous or next timesheet and then navigate with the "previous period" or "next period" to the timesheet in question.
Also have you tried to open it using a delegation session?
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS | -
Issue while installing Ms Project Server 2013 on MS Server 2012 R2 with Sharepoint Server 2013
Hello MS Support Team,
I installed SQL server 2012 & Sharepoint server 2013 and after that the MS project Server 2013 is not installing on the same server -- pls hv a look the enclosed screenshot. sent at [email protected] and guide me to resolve it on priority.
A windows poped up - Installation Error - This Project requires MS Sharepont Enterprise edition... (Which is not available on the MSDN Server)..only standard edition available.
Please reply asap @ [email protected] - Call @ 0120471384
Kind Regards,
Vinay Bhardwaj
Network System Administrator - GREC (IN)
Rockwell Automation | A-66, Sector 64 | Noida | India
LISTEN. THINK. SOLVE
IP : 71384 | E : [email protected] | W : www.rockwellautomation.comHi Siriosus,
Indeed you do need Sharepoint Server 2013
Enterprise for Project Server 2013.
See article below where it is mentionned:
Project Server 2013 requires the Enterprise edition of SharePoint Server 2013. Prior versions of SharePoint Server and SharePoint Foundation 2013 are not supported.
http://technet.microsoft.com/en-us/library/ee662114(v=office.15).aspx
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS | -
Project Server 2013 - This webpart was unable to load
Hi all,
I am getting the following error in project server 2013 project sites:
This webpart was unable to load. For more information, please contact your server administrator.
<Guid>
I only get this error message on 'Project Summary Web Part'.
Any idea what it could be?
Thank you,
SJHi there!
I got similar problem in a PDP that was working perfectly even after migration to 2013. On this case, my PDP was showing the webpart that let you to choose what fields and custom fields want to show on a specific PDP.
I created a copy of the crashed PDP and got the same error. So I bet for remove all the custom fields and add one by one to see what happens. The surprise came up when it started to work when my PDP had just pair of custom fields. With this procedure,
I found that the problem was on some specific custom fields created that had null values to all the projects created before. Once I forced value on those fields it worked properly!!
Sometimes EPM2013 has a very strange behavioural and in some cases just clicking on EDIT and SAVE without any change have solved some of my problems too.
I hope it helps this to you and feel free to contact me if I can somehow help you :)
Diego -
Can't open Project Server 2013 word documents with office 2010 installed
hello forum members,
we having issues opening a word document in a Project Server 2013 . we have Office 2010 on our computers installed.
when I click on a document link, i get a message "The webpage cannot be displayed". the only way to open a document is to right click on link and select "Open".
Does Project Server 2013 require Office 2013 installed? If not, is there a way to open documents in Project Server 2013 without right clicking on links?
tatiana
tatianaHi Tatiana,
This is the know issue. I have experienced this issue with one of our client. The cause of issue as below -
Scenario
You have 2007 Microsoft Office installed on a computer.
On the same computer, you also have a Microsoft Office 2013 application installed, such as Microsoft Lync 2013 or Microsoft Word 2013.
SOLUTION
To work around this issue, remove the Microsoft SharePoint Foundation Support program component from the Office 2013
installation on the affected computer or computers. To do this, follow the “Install or remove individual Office program components” section of the following Microsoft Office website:
Install or remove individual Office
programs and components
(http://office.microsoft.com/redir/HA010354261.aspx)
After you complete these steps, repair 2007 Office. For more information about how to repair the installation, click
the following article number to go to the article in the Microsoft Knowledge Base:
924611
(http://support.microsoft.com/kb/924611/ )
How to install the individual 2007 Office features or to repair the installed 2007 Office programs
Note When
you follow these steps, set the Microsoft SharePoint Foundation Support
component within Office Tools to Not Available.
This solution doesn't apply to scenarios in which SharePoint Designer 2013 is installed on the affected computer.
You can find further details here at Microsoft support site -
http://support.microsoft.com/kb/2888015
Hope this helps you.
Cheers, Badal
Maybe you are looking for
-
Follow-up question on BOM production and consumption of same item
Awhile back, I asked the question about whether it made sense to have a BOM structured to simultaneously produce and consume an item. BOM that needs to produce and consume same component Thanks for the help and it does what I thought it should. We
-
Error message when trying to open Messages.
Just upgraded to Mountain Lion (10.8) yesterday. Messages won't open. Reports "An Internal Messages error occurred. There was a problem with Messages. You need to quit and open Messages again." Console shows: 7/29/12 8:53:41.594 PM Messages[834]: [Wa
-
Ive recently downloaded it after my ipod said too and now my ipod wont connect too app store or imessage and etc. it also says my back ups are corrupted
-
Mail doesn't download on snow leopard
Mail won't download on my Snow Leopard Macbook Air. Activity icon keeps spinning then it asks for my MobileMe password and keeps spinning. What's the issue? I have iCloud on my Lion Mac Mini and iPohne 4S and they work fine. Is this the same old
-
Terrible Flickering/Delay While Playing Video in Hyper-V
Hello Community, I have a Hyper-V server running on Windows 8.1. I have had it for a couple years now. There's been this problem that has been bugging me (I can't believe I waited this long to say anything!) and I wanted to see if someone can help me