Project system Network table

Hi Sap Experts,
After define Net work in project system , which where will be stored ( Data base table)
Please suggest me the appropriate table.
Regards,
Prabhakar

Hi
Pls find the relevant tables. Let me know if this works.
AUFK Orders/networks headers
AFKO Production Orders/networks
AFVC Network activities
AFVU Network activities
AFVV Network activities
Regards
Srini

Similar Messages

  • Project Systems:Transparent Table holding ECP data

    Hello experts,
    Does anybody know what table holds the the ECP (Easy cost planning) for a WBS element.
    Any help would be appreciated
    Thanks
    David

    CKHS & CKIS are the ECP specific tables
    sorry i mentioned ECP tables..I will find and post right table..
    Edited by: Mahalakshmi Padmanaban on Jan 29, 2010 12:34 AM

  • Project system network activity cost distribute

    it is possible that i distribute the plan cost of external network activity to period wise. if yes then how ..........
    thanks

    Hi
    You can't plan the cost of external network activity period wise. The lowest level you can plan period wise is WBS Element level.
    Regards,
    Suraj

  • GGB0  for PS (project system) , how to add another table

    hi all,
    how to set in ggb0 , under Project System-Network activity, we need to add table resbd to check field saknr , how to add the table resbd?

    1) Using bcdedit.exe /enum
    To enable the computer to also boot Windows 7 you again use bcdedit.exe with the following command which will copy the current Windows
    Boot Loader details for Windows Server 2008 to Windows 7.
     bcdedit.exe /copy
    {current} /d "Microsoft Windows 7"
     bcdedit.exe will
    respond with something like the following.
    The
    entry was successfully copied to {................................}.
    Using
    bcdedit.exe /enum to again enumerate through the current entries within the BCD store you'll see the newly added entry.
    Before you can use the newly created Windows boot loader configuration, you'll need to change the partition for Windows 7 using
    the following two bcdedit.exe commands.
    bcdedit.exe /set {.................................} device partition=D:
    bcdedit.exe /set {.................................} osdevice partition=D:
    If you now reboot the system you should now be able to boot into either Windows Server 2008 or Windows 7.

  • SAP R/3 4.7 Enterprise Project System(PS)

    Hi,
            I have to do achieve following four tasks for four integration scenarios :
          1. Create a Project in Project System.
          2. Create a Network in Project System.
          3. Create an Activity in Project System.
          4. Update an Activity on Project System.
    I want to know the following :
         1. Which BAPIs to use?
         2. How to import these BAPIs in my integration repository.?
    Thanks in advance.

    Go to transaction BAPI in R/3
    <i>1. Create a Project in Project System.</i>
    Project System -> Project Definition -> CreateFromData ->  FM: BAPI_PROJECTDEF_CREATE
    <i>2. Create a Network in Project System.</i>
    Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN
    <i>3. Create an Activity in Project System.</i>
    Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN, this has activity create
    <i>4. Update an Activity on Project System.</i>
    Project System -> Network -> Maintain -> FM: BAPI_NETWORK_MAINTAIN, this has activity update
    <i>I want to know the following :</i>
    <i>1. Which BAPIs to use?</i>
    mentioned above.
    <i>2. How to import these BAPIs in my integration repository.?</i>
    Double click on your SWCV, click the radio button <b>import RFC and IDoc interfaces from SAP Systems permitted</b>, then enter your R/3 System ID and client number. Save and activate. Then you will see new item under the SWCV
    Imported Objects
      RFC
      IDoc
    Right click on Imported Objects and in the pop up mention R/3 system host, system number, userid and password.
    regards
    SKM
    Message was edited by: SKM

  • In which tables this Project system 'CJ20N' Data has been stored.

    Dear Guru's
    Please help to fullfil my requirment.
    In Project System we are creating 4 levels WBS structure in CJ20N; we are assigning deferent machine types and deferent Personal nou2019s to deferent WBS elements.
                     Here I want a report against this project what all the Machines & Employee No that we have assigned, and against Employee Network we are booking the time sheet for Employee and we are transferring the same to Controlling, we are Preparing the Sales Order by using the WBS element and than we do u201CDP91u201D to create Debit Memo request with reference to sales order for that employee for his working approved working Hrs.
    From which tables we will get this required information to prepare u201CZ-Reportu201D
    Are there is any link to get the document flow from Project to Debit memo request.
    Regards,
    Kalyan

    U have to refer multiple tables for this.
    Fot CATS time entry u can get the date from table CATSDB.
    Refer below link.....
    SAP Project System - A ready Reference ( Part 2 )

  • In which tables (ABAP) the Project System Information Will be stored

    Dear Guruu2019s
    Happy New Year
    In project systems can we able to see, against the projects and against WBS what all the sales orders, Employees and material etc... That we assigned, in which STD report we can check all these assignments, from which tables (ABAP) it picks up the data to populate in the STD report.
    I need the Tables for preparing the Z- Report. Please help meu2026
    Regards,
    Bhanu Prathap

    The most common overviews with respect to sales and distribution can be obtained from CN54N/ CN55N or you can also use CNS54 / CNS55. Tables for the same are VBAK/ VBAP.
    For materials you can refer to CN52N overviews for material components and CO24 for missing parts.
    For resources, CN50N provides the capacity requirements and CMP9 workforce planning.
    Venu

  • Project system: Purchase requisition coming from Networks

    Dear Experts,
    I have a tricky problem. I want to exclude a specific number range for purchase requisition coming from the Project system.
    The current number range I have for the purchase requisition is let say: 10000000 - 19999999.
    I want to use another number range (50000000-59999999) for the purchase requisitions as an impact of material components of an network activity.
    What I've tried but it is not working properly:
    1. TC: OMH7 - I created a new number range as I mentioned above
    2. TC: OMEB - I've copied the document type NB to a new document type ZNB (NB = ZNB)
    3. TC: OPTT - as last step I've assigned the document type ZNB to the order category 20 (network)
    Please advice ASAP
    Thanks a lot in advance

    It should work as it works fine for me.
    1. You create the Internal number range (50000000-59999999) first and number it with an ID.
    2. Create the ZNB document type and assign the number range number (i.e., two-character ID)
    3. Assign this ZNB in OPTT
    If I've repeated what ever you've done/said, check the settings once again. It should work.
    Regards
    Sreenivas

  • Project system tables for getting baseline and forecast values

    Hi all,
    I am new to Project systems and currently i am having the PS report.
    I need to pick the following values based on project definition (proj-pspid):
    --> historical baseline values like:
    1) versions
    2) created by
    3) created on
    --> historical forecast values like:
    1) versions
    2) created by
    3) created on
    Can you please let me know the tables and fileds for fetching the above values.
    Regards,
    raviraj.

    Hi,
    IMAK Appropriation requests - general data
    IMAV Appropriation request variant
    IMPR Investment Program Positions
    IMPU Texts for cap. inv. program positions
    IMTP Investment programs
    IMZO Assignment Table- CO Object - Capital Investment Prog.Pos.
    PMCO Cost structure of maintenance order
    PRHI Work Breakdown Structure, Edges (Hierarchy Pointer)
    PROJ Project definition
    PRPS WBS (Work Breakdown Structure) Element Master Data
    Check with tables

  • Tables for Project System Component

    Hi,
    I hve the list of standard DS from Project System component. Currently these DS are not active in our ECC system. Now I need to find the Source table for all these DS. Can any one please provide the table name if you have. I searched in sdn/help.sap but I couldn't find any.
    Master Data DS:
    0ACTIVITY_ATTR
    0ACTIVITY_CUST_ATTR
    0ACTIVITY_TEXT
    0ACTIVITY_USR_ATTR
    0ACTY_ELEMT_ATTR
    0ACTY_ELEMT_CUST_ATTR
    0ACTY_ELEMT_TEXT
    0ACTY_ELEMT_USR_ATTR
    0CASHDETAIL_TEXT
    0CASHTYPE_TEXT
    0CLAIM_ATTR
    0CLAIM_TEXT
    0DATE_EVENT_TEXT
    0DATE_SRCE_TEXT
    0MILESTONE_ATTR
    0MILESTONE_TEXT
    0MLST_USE_TEXT
    0NAE_INH_ATTR
    0NETWORK_ATTR
    0NETWORK_CUST_ATTR
    0NETWORK_TEXT
    0NTW_INH_ATTR
    0NWA_INH_ATTR
    0ORD_INH_ATTR
    0PROJECT_ATTR
    0PROJECT_CUST_ATTR
    0PROJECT_TEXT
    0PS_APPLNO_TEXT
    0PS_CHANCE_TEXT
    0PS_COMPONT_ATTR
    0PS_COMPONT_TEXT
    0PS_HERKZ_TEXT
    0PS_OBJ_TEXT
    0PS_OPPNT_TEXT
    0PS_PRJTYPE_TEXT
    0PS_RESPNO_TEXT
    0SCOPE_TEXT
    0STATUSCLM1_TEXT
    0STATUSCLM2_TEXT
    0STATUSSYS0_TEXT
    0WBS_ELEMT_ATTR
    0WBS_ELEMT_CUST_ATTR
    0WBS_ELEMT_TEXT
    0WBS_ELEMT_USR_ATTR
    0WBS_ELEMT_WBSH_HIER
    0WBS_INH_ATTR
    Transactional DS
    0PS_CLM_CST
    0PS_CLM_ECP
    0PS_CSH_NTW
    0PS_CSH_NWA
    0PS_CSH_ORD
    0PS_CSH_WBS
    0PS_DAT_MLS
    0PS_DAT_NAE
    0PS_DAT_NTW
    0PS_DAT_NWA
    0PS_DAT_PRJ
    0PS_DAT_WBS
    0PS_KAP_NAE
    0PS_KAP_NWA
    0PS_NAE_ECP
    0PS_NAE_EVA
    0PS_NTW_EVA
    0PS_NWA_ECP
    0PS_NWA_EVA
    0PS_ORD_EVA
    0PS_WBS_ECP
    0PS_WBS_EVA
    Regards,
    Jackie.

    Try to search it at Help.sap.com web page (use search for BI content)
    For example for your first extracotr:
    http://help.sap.com/saphelp_nw70/helpdata/en/4f/4bc739e033417ae10000000a114084/frameset.htm
    Regards,
    DL

  • Table for budget distribution undet project system.

    hi,
    do any one know the table for budget distribution under a project system?
    i need to get the data of budget assigned to a WBS level with the position ID, for a project. the transaction code to distribute the budget is by using transaction code - IM52.
    i posted this question in here before, but the answer i get is incorrect, as i need the table for budget under porject system. thanks

    Check these tables:
    PRPS  WBS (Work Breakdown Structure) Element Master Data
    IMPR  Investment Program Positions
    IMPS  Assignable Operative Objs for Capital Investment Positions
    IMAK  Appropriation requests - general data

  • Where does Plan Version field store in SAP project system table?

    Hi,
    I would like to know where where does Plan Version field store in SAP project system table.
    The plan version that I m refering is the Plan Version 1 in the menupath u201COn the Project Info System: Progress Analysis: Initial Screen, Choose Settings > Value display > Plan versionsu201D.
    T-Code: CNE5
    Thanks.

    hi,
    try table TKA09
    regards

  • Need Tables and Func Modules related to Project Systems

    Hi
          I am working on a custom program that Creates Project ( CJ01) using standard Project Def.
         All WBS elements of  Standard Project Template  should be copied to the newly created Project
        I am not able to get any Standard Func Module which creates new WBS elements from Standard WBS elements.
      It will be of great help for me, if any one has info on this.
    thanks in advance.

    Hi
    See the Tables
    PRPS  -WBS element
    PROJ - Project Definition
    other tables are
    PRTE,PRTX,PSTX,PSTT  -Scheduling data for items
    PRHIS
    see the fun modules
    CJPN_GET_WBS_ELEMENT
    CJPS_GET_WBS_ELEMENT
    PSBW_GET_TEXT_WBS_ELEMENT
    PSBW_GET_WBS_ELEMENT
    K_PROJECT_WBS_PLANVALUES
    AIPR_GET_HIERARCHY_TO_WBSELEM
    CJDW_GET_NEW_WBS_ELEMENTS
    Reward points if useful
    Regards
    Anji
    Message was edited by:
            Anji Reddy Vangala

  • Change Table Fields in "Costing" in with Project System (PPM 5.0)

    Dear Gurus;
    I need to know, how can I change fields in "Costing" with Project System (Project Management in tab name "Accounting").
    The integration works well, but I need to view the values of: Actual, Plan and Commitment.
    In the Standard way, just only can see the Plan (with the colum "Costs").
    Please, help.
    Best regards.
    Mariano.
    Edited by: Mariano Sabiche on Apr 27, 2011 3:17 PM

    Hi Mariano
    The particular screen you are referring to will only show the planning on Easy Cost Planning due to the labour costs and revenues planned on the cProject.  You can use the services&deatil on the assignment - click on the WBS assigned to get the detailed list of services for the assigned WBS element.  You can then click on Detail Data to get detailed data on the assigned WBS element.  If you want a report with all the data, best use the BW cubes for that to combine cP and PS data.
    Hope this helps
    Regards
    Duan

  • WBS Elements not getting created in ECC Project System from CRM 7.0

    Dear all,
    We are trying to integrate SAP CRM 7.0 with SAP ECC-PS module. The objective is to bring in the marketing plan and elements data from the CRM system, and to create the corresponding WBS in project system. We have done most of the configuration as recommended by SAP in both the systems, and we see that the BDOCS are getting generated and sent to the ECC system. The following steps have been successfully completed:
    1.       Set up the RFC connections between the two systems
    2.       Selected the connection type as Middleware in CRM system.
    3.       Installed the cProject Add on in CRM box.
    4.       Created a project scenario (with project and network profiles) in the PS system and assigned the same in the CRM system.
    5.       The Project Scenario in PS config has the same name as the Project Type in CRM config.
    6.       Created and released the campaign ids being created in the CRM system.
    As already mentioned, we can see that the BDOCS are coming to the ECC system and are getting stored in BDOC_TRACK table. However the issue is that the corresponding WBS elements are not getting generated in the ECC system. Is there anything that that we are missing in the ECC box which would trigger the WBS element creation?
    Request you all to share your inputs which would be immensely beneficial for us in achieving this integration.
    Thanks and Kind Regards,
    Aditya Shrivastava

    Hello Aditya,
    We too are facing this issue.. if you have resolved the issue could you please let us know the solution ?
    Some inputs related to our system,
    We have upgrade from CRM 4.0 to CRM 7.0 SP07 and R/3 backend system is on 4.7 SP27, earlier we have completed the upgrade on sandbox without any issues which was upgrade to CRM 7.0 SP04 but with SP07 we are facing the problem of WBS Element not getting created in R/3.
    Your help is highly appreciated.
    Thanks & Regards,
    Sumukh Kapoor.

Maybe you are looking for