PS report for Actual and commitment Balance

Dear experts,
Is there any report in PS where i can see list of projects has actual balance and commitment balance?
Note: I want to see only the balance of actual cost ( which is not settled) and commitment balance (Open PO, PR etc..)
Regard
Vetrivelan

Hi,
For commitment- CJI5
actual - CJI3 with correct layout as per you requirement.
also try S_ALR_87013558 report & go to line item report for detail actuals(& you have to change the layout accordingly) & commitment.
hope this would help you...
regards,
SL

Similar Messages

  • Tables related to PM order for actual and commitment items

    Hello Experts,
    I need help in finding the tables related to PM order for actual and commitment items.
    I need develop a report which can show the actual and commitment items for each order and Operation/component under that each ITEM wise and its related documents.
    For the component we can find the table RESB.
    But i am getting the difficult to find the data related to Operation (services)
    In my client we can able to see PM orders with activity types and SKF
    How can build the logic to find the values for each operation item and its commitments (PO, PR) and actual that is FI documents
    Please guide me the   TABLES and fields or else give me the hints, how can find the tables
    Thanks and Regards,
    Narendra

    Hi,
    The tables are COEP (actuals) and COOI (commitments); that is if you mean the financial figures.
    Regards,
    Eli

  • Inventory Report for actuals  and  projected?

    Hi,
    currently i am doing APO-BI Project. I have a requirement to extract the Opening stock from ECC and Projected(Forecasted) Opening stock from APO.
    both are 2 different key figures 1 is from ECC and another one is from APO. I need to display in Bex report in
    say for example, if we have 53 weeks in a year. if i run the report in week 25, in the bex report it has to display the Opening stock values from ECC up to week 25 and remaining weeks till 53 weeks it has to display Projected Opening stock values in the same line.
    plz provide me the logic to achieve this report.
    regards
    venuscm

    Hi,
    Create Two Cubes one is for APO and another is 0IC_C03 for Inventory. then build a MP on both and create reports.
    Use 2LIS_03_BX, 2LIS_03_BF, 2LIS_03_UM to 0IC_C03 Cube and design the report.
    Use :See the steps how to load the data to 0IC_C03.
    Treatment of historical full loads with Inventory cube
    Setting up material movement/inventory with limit locking time
    If it is BI 7 then for BX in in DTP in Extraction Tab you need to select Extacrion mode = NON-Cumulative option.
    0VALSTCKVAL      " For Value
    0VALSTCKQTY      " For Qty
    0CALMONTH        " For Month
    Use the above combinations in New Selections in columns and go it.
    For Qty Opening:
    New Selection, drag and drop following InfoObjects
    0VALSTCKQTY     " For Qty
    0CALMONTH       " For Month and restrict with less then or equalto option variable (single value, user input)  and set the offeset
                    " value = -1 bcoz if user will give 12.2009 , so it will display 11.2009 closing stock, this is opening for 12.2009.
    For Qty Closing:
    New Selection, drag and drop following InfoObjects
    0VALSTCKQTY    " For Qty
    0CALMONTH      " For Month and restrict with less then or equalto option variable (single value, user input) .
    In the same way build for Value and other Keyfigures on 0IC_C03.
    And
    Drag & drop
    0MATERAIL
    0PLANT  " Give some Input Variable.
    Thanks
    Reddy

  • Period Balance Report for Actual/ Commitment only

    Hi,
    Do we have any report for getting Periodic balance for cost Centre Actual and commitment Balances.
    Regards,
    Venkat

    If there is not a specific YtD report, then it is easy to create one: Using the report painter, copy the existinf report, and amend the columns to reflect not the current month, but from the 1st period to the current month.

  • Is there standard report for planned and actual devlivery date?

    Hi Guru,
    Could you help me to find standard report to compare planned delivery date in PO and actual delivery date (GR Posting date)?
    I wonder, Is there standard report for planned and actual delivery date?
    or I have to create a customizing report.
    Thank you very much.

    hi
    i dont think it is possible to see both in one pan so try to create some Z report
    u try ME80fn here u have to change the views ,in del shedule view u can see the delivery dtae and in PO histry view u can see the posting date
    regards
    kunal

  • Document or report for assessment and reversed assessment?

    Hi guyz,
    Is there any document or report for assessment and reversed assessment?
    I need to find documentation as a proof for any execution and reversal of assessment, such as journal entry or report line items that is showing debit or credit for the expenses..
    Currently, I can only see actual cost document which shows execution of assessment and an assessment cost element debit and credit in the Cost Center Actual/Plan/Variance report.
    However, when I do reversal at KSU5, in the Cost Center A/P/V report is showing that assessment cost element is still exist (no more debit and credit showing as the result of the reversal), only that the value is now zero.
    Need your answer asap...Thanking you..

    Dear Meila,
    Use tcode KSB1 Cost Center Actual Line Itens, execute then report and change the Layout, insert the field Business Transaction in the report.
    Regards

  • Rolling forecase for Actual and Plan

    Hi
    Iam working on Rolling Forecast for Actual and Plan report.. My Planning here is Quaterly based so for example say we plan it on April so the months after april (May - Dec) would be Planning. So when my month keeps on moving the forecase also moves..
    So can you please guys help me to get out of this with an solution..
    Thanks

    Hi,
    If you are using BI-IP for your scenario of forecasting then you can refer to the below links for forecatsing strategies.
    http://help.sap.com/saphelp_nw70/helpdata/en/43/0c033316cd2bc4e10000000a114cbd/frameset.htm
    for forecasting strategies
    http://help.sap.com/saphelp_nw70/helpdata/en/43/0c033316cd2bc4e10000000a114cbd/frameset.htm
    If you are using SEM-BPS you can consult these links:
    http://help.sap.com/saphelp_sem60ep1/helpdata/en/0a/242537cedf2056e10000009b38f936/frameset.htm
    http://help.sap.com/saphelp_sem60ep1/helpdata/en/0a/242537cedf2056e10000009b38f936/frameset.htm
    Forecast (old)
    http://help.sap.com/saphelp_sem60ep1/helpdata/en/0a/242537cedf2056e10000009b38f936/frameset.htm
    Forecast(Exit)
    http://help.sap.com/saphelp_sem60ep1/helpdata/en/0a/242537cedf2056e10000009b38f936/frameset.htm
    Regards,
    Priyanka Singh

  • Report for Branch wise Trail Balance & Profitability

    Hi,
    I need a report for Branch wise trail balance and Profitability. Is there any standard report in FI for that or do i need to define with Report painter functionality?
    Please advise
    BR,
    Yadayya

    Trial balance and profit and loss account can be drawn atleast at Profit center level or business place through F.01.
    As you have mentioned branch , how have you treated branch ? are they profit centers or business area ?
    Else you can very well use report painter for FAGLFLEXT and draw the details as desired .

  • ACCOUNTING FOR ACTUAL AND ESTIMATED OVERHEADs

    Hi
    I have some basic questions about the accounting flow for actual and applied OVERHEADs in SAP,
    When I receive the goods from production I credit Cost Of Goods Manufactured (Mat CostOHProcess Cost+ Prod Cost)
    1. How does the accounting entry flow in the above case.
    2. How do we provide for these expenses in advance or do we need to pass a JV (Provision/Payable a/cs)
    3. When the actual costs are booked, how do we book the same in Finance,  as we have already inventorised the estimated expenses.
    Thanks & Regards

    Eduardo,
    you don't HAVE to create a new cube, as Ravi says you could use the Actual cube, make it Real time and keep on switching the cube behavior between loading and planning.
    However what I would do is create a real time cube as a copy of the actual one. Build a multiprovider with exactly the same structure and an aggregation level on top of the multiprovider. The old plan data can remain in the Actual cube and using the layouts and planning functions you can use it without a problems.
    Then all the new planning data should be written to the new cube.
    This way, once the old plan data becomes obsolete your data will be partitioned in two cubes, with the advantage of reporting using a multiprovider.
    Regards,
    C

  • Standard reports for cash and fundflow reports?

    Hi,
    i need a requirement to maintain reports for cash and funds flow statements?Actually relevant to these reports i use to maintain customize only but coming to fundflow and cash flow there is much complications to do that.
    so is there any standard reports to maintain fundflow and cash flow reports which is relevant to FI-CO
    Thanks in Advance
    vass

    Hi
    You have Cash flow statement based on 0FIGL_VC1
    http://help.sap.com/saphelp_nw70/helpdata/EN/7d/6cfa40ee14f26fe10000000a1550b0/frameset.htm
    You also have Cash flow statement based on 0BCS_C10, but not sure it does suits to your requirement.
    http://help.sap.com/saphelp_nw70/helpdata/EN/39/09503e50a9054be10000000a114084/frameset.htm
    Hope it helps

  • Need to display different colors for Actuals and forecasting values in WAD

    Hi Gurus,
    My requirement in the report is, I need to display different colors for particular values like Actuals(say value type 10) and for forecasting values(say value type 20) , and data will uploaded from flat file.
    Scenario : If I upload the data for March Month, I receive actual values upto March(Jan to March month) and from April to Dec(Forecast values with value type 20),  Every month I will be getting file and similarly for subsequent months, i will get current month actual values and forwarding months forecasting values,
    Now , my requirement is, When ever i execute the Report, Say if i execute for April Month, Upto April( Jan to April for actual values should be displayed in one color) and from May to Dec ( forecast values should be displayed in different color).
    I had tried with following options like exceptions and could not display , as it runs based on key figure values where as my requiremnet is based on the CALMONTH , i need to show different colors for both actual and forecast values.
    Kindly, help me out from this,
    Thanks

    Hi,
    it is not necesseary that you need to do that in WAD , you can do the same in BEx platform, Since WAD is build above the bex reports. so automatially any changes done in Report will be replicated in WAD
    Go for Exceptions in Bex. Give some range for Actuals and Forcasting at the creation of the exception.
    if you do those changes in BEX automatically it will replicate in the WAD.
    for more information please read this link
    http://help.sap.com/saphelp_nw04/helpdata/en/68/253239bd1fa74ee10000000a114084/content.htm
    hope this will solve your problem.
    Santosh

  • Simulair report for FBL5N and FBL1N for new general ledger on segment level

    We are working with segments in new G/L ledger. We want to run a open item report where we can combine customers and vendors by segment. The vendors and customers are linked in the master data. In the "old"  reports FBL5N and FBL1N you can do this but not by segment.I found the following report on segment level:
    - S_PCO_36000218 - Receivables: Segment
    - S_PCO_36000219 - Payables: Segment
    What I'm missing is to run 1 report for Customers and vendors. What I'm missing to is that there are only some fields available on line item level. (I like to have invoice number, documentype,.......)
    Is there a standard report for this in new genaral leger?
    Is it possible to ad additional field to th list viewer.

    What is this user license type?  All financial transactions need professional license.
    Thanks,
    Gordon

  • Custom Report for slow and fast moving items

    Dear Xperts,
    My client wants to develop a new report for slow and fast moving items, I checked the std report MC46 however as per std SAP design this report does not consider the special stock like project stock (Q)...could you please help me to know how can develop this new report with following input and output fields?
    Input fields:
    Plant
    Material
    Material Group
    MRP Area
    Special Stock Indicator
    Special Stock (Type)
    Output Fields:
    Material
    Material type
    Material group
    MRP Controller
    MRP Area
    ABC indicator
    Material price
    Category field – Slow, Fast, Non-moving
    Current Stock
    Last Issue Date
    Thanks in Advance
    Regards
    Rahul

    Dear Rahul,
    If you required  project stock and consignment stock with valuated stock report in same place you need to generate new info structure as given below link. Or you can go with customized report with abaper.
    Info structure validation
    Regards
    Sanjeet Kumar

  • Performace Issue using Crystal Report For enterprise and BEx Queries

    Hi all;
        We are generating the following error stack when trying to build a report on top of a BEX query using Crystal Report for Enterprise :
        |7C4F8ECE44034DB897AD88D6F98B028B3|2011 12 12 17:24:21.277|+0100|>>|E| |crj|20380|  56|ModalContext    | |2|0|0|0|BIPSDK.InfoStore:query|CHVXRIL0047:20380:56.174:1|-|-|BIPSDK.InfoStore:query|CHVXRIL0047:20380:56.174:1|Cut2PbOe3UdzgckPBHn8spEab|||||||||com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects||Assertion failed: Java plugin for CommonConnection is not loaded.
    java.lang.AssertionError
         at com.businessobjects.foundation.logging.log4j.Log4jLogger.assertTrue(Log4jLogger.java:52)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects.newInfoObject(InfoObjects.java:576)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects.continueUnpackHelper(InfoObjects.java:548)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects.continueUnpack(InfoObjects.java:489)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects.startUnpack(InfoObjects.java:464)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore$XRL3WireStrategy.startUnpackTo(InternalInfoStore.java:1484)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore$XRL3WireStrategy.startUnpackTo(InternalInfoStore.java:1464)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore.unpackAll(InternalInfoStore.java:910)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore.queryHelper(InternalInfoStore.java:944)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore.queryHelper(InternalInfoStore.java:929)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore.query_aroundBody24(InternalInfoStore.java:798)
         at com.crystaldecisions.sdk.occa.infostore.internal.InternalInfoStore.query(InternalInfoStore.java:1)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoStore.query_aroundBody20(InfoStore.java:175)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoStore.query_aroundBody21$advice(InfoStore.java:42)
         at com.crystaldecisions.sdk.occa.infostore.internal.InfoStore.query(InfoStore.java:1)
         at com.businessobjects.mds.securedconnection.cms.services.olap.OlapCmsSecuredConnectionService.getConnectionObject(OlapCmsSecuredConnectionService.java:125)
         at com.businessobjects.mds.securedconnection.cms.services.olap.OlapCmsSecuredConnectionService.getOlapSecuredConnection(OlapCmsSecuredConnectionService.java:191)
         at com.businessobjects.mds.securedconnection.loader.internal.SecuredConnectionLoaderImpl.getOlapConnectionFromSecuredConnection(SecuredConnectionLoaderImpl.java:83)
         at com.businessobjects.mds.securedconnection.loader.internal.SecuredConnectionLoaderImpl.getConnectionFromSecuredConnection(SecuredConnectionLoaderImpl.java:60)
         at com.businessobjects.dsl.services.workspace.impl.DirectOlapAccessDataProviderBuilder.loadSecuredConnection(DirectOlapAccessDataProviderBuilder.java:193)
         at com.businessobjects.dsl.services.workspace.impl.DirectOlapAccessDataProviderBuilder.loadSecuredConnection(DirectOlapAccessDataProviderBuilder.java:176)
         at com.businessobjects.dsl.services.workspace.impl.DirectOlapAccessDataProviderBuilder.provideUniverseFromCms(DirectOlapAccessDataProviderBuilder.java:63)
         at com.businessobjects.dsl.services.datasource.impl.AbstractUniverseProvider.provideUniverse(AbstractUniverseProvider.java:41)
         at com.businessobjects.dsl.services.workspace.impl.AbstractDataProviderBuilder.updateQuerySpecDataProvider(AbstractDataProviderBuilder.java:119)
         at com.businessobjects.dsl.services.workspace.impl.AbstractDataProviderBuilder.updateDataProvider(AbstractDataProviderBuilder.java:106)
         at com.businessobjects.dsl.services.workspace.impl.AbstractDataProviderBuilder.addDataProvider(AbstractDataProviderBuilder.java:49)
         at com.businessobjects.dsl.services.workspace.impl.WorkspaceServiceImpl.addDataProvider(WorkspaceServiceImpl.java:56)
         at com.businessobjects.dsl.services.workspace.impl.WorkspaceServiceImpl.addDataProvider(WorkspaceServiceImpl.java:45)
         at com.crystaldecisions.reports.dsl.shared.DSLTransientUniverseServiceProvider.createSessionServicesHelper(DSLTransientUniverseServiceProvider.java:72)
         at com.crystaldecisions.reports.dsl.shared.DSLServiceProvider.createSessionServices(DSLServiceProvider.java:428)
         at com.businessobjects.crystalreports.designer.qpintegration.DSLUtilities.getServiceProvider(DSLUtilities.java:279)
         at com.businessobjects.crystalreports.designer.qpintegration.InitializeDSLRunnable.run(InitializeDSLRunnable.java:82)
         at org.eclipse.jface.operation.ModalContext$ModalContextThread.run(ModalContext.java:121)
    Here seems to be that a plugin is not loaded : com.crystaldecisions.sdk.occa.infostore.internal.InfoObjects||Assertion failed: Java plugin for CommonConnection is not loaded.
    could this affect the performance of Crystal Reports for Enterprise and how could I fix this ?
    Best Regards
    Anis

    Venkat,
    Thanks for your response. Please note, however, the transaction RAD1 does not exist. Let me provide more details about the current settings of the InfoObject.
    The Characteristic is 'Item' (0CS_ITEM) and upon going to RSA1 >  Modeling > InfoObjects > Item (0CS_ITEM) > Right Click > Display > Business Explorer (tab) > Text Type is set to 'Long Text' and BEx description is set to 'Long description' already.
    When I run/execute the query with this Item characteristic, the results in BEx Analyzer is showing appropriate long text, however, Crystal Report for Enterprise shows short text only
    K
    Edited by: Kumar Pathak on Feb 3, 2012 6:18 PM

  • VAT reporting for Spain and Italy

    Hi,
    we have a problem getting VAT report for spain and Italy. Trying to get the report RFUMSV20 for current month but it is giving an error saying " There is no data record for RFUMSV20 Ccode 2008 in Table TRVOR" Can I anyone help me with this?
    Thank you
    Priti
    Edited by: Priti Singh on Mar 13, 2008 7:06 PM

    Hello,
    If your tax config is correct and the GL accounts are updated, then check for some OSS notes. Probably, you need to apply one of those.
    Reg
    assign points if useful

Maybe you are looking for