Putting a production order on hold, removing capacity requirement

Hi,
I have a need to temporarily remove capacity requirements from production order because there is situation on the shop floor that caused the particular order unable to move ahead.
Capacity requirement shall be re-instated when the order specific production issue is cleared.
Is there a way to update a production order to release capacity requirement yet allowing changes to production order routing? I tried "LOCK" production orders but that will not allow me to change anything in the order.
Can I set up a user status + user exit to remove the capacity requirement? If so, how to?
Thanks all in advance!!!
Regards.

Hi
Capacity requirement can be deleted when the following functions are carried out.
1.The production order is set to Technically Complete.
2. The deletion flag is set for the production order
3.The production order is locked
4.The indicator capacity  requirement in the procdution order is reset  and order is rescheduled
5.The capacity requirement is reset with fucntions -----Availability check---reset cap stock
Regards,
Sadan

Similar Messages

  • Capacity planning and schedulng production order based on availabe capacity

    Hi Gurus,
    I am trying to use capacity planning, when the production order is created it takes the order start date as the requirement date. Then when i do he capaity check it says capaity not available. After finite scheduling again it proposes to shift operations by certain days.
    I need the capity to be check in MRP and the palled orders to have start dates based on aviable capity, currenty all the palled orders are starting on the requirement date irresptive of avaiabe capaity. I tried using finite scheduling option in MD02 still it does not take in to account exsting production orders for giving dates of the planned orders.
    Regards
    Abhi

    Dear Abhishek,
    1) This is Std SAP of MRP, only material Av check will be carried out in MRP & create procurement
    Proposals
    2) Capacities will not Checked  ( consider ) in MRP in Std R/3
    3) Your Need can be only met through APO
    Regards
    Madhu

  • Configuration setting to always put Manual Sales Orders on hold

    Can any one tell me the Configuration setting to put Manual Sales Orders always on Hold.

    hello, friend.
    when you say 'on hold', are you referring to a delivery block and/or a billing block?
    if so, you can do this by doing VOV8, select your sales document type and make an entry in the fields 'delivery block' and/or 'billing block'.
    now, when you create a sales order using this document type, the order will be automatically blocked and will require release by an authorized party (VKM1, VKM3 and VKM4 for a delivery block, V23 for the billing block).
    regards.

  • Multiple production orders  are generated for same requirement

    hello guru's
    For a MTO (make to Order) scenario, where the Material requirement quantities are generated from Sales Orders.
    Ex: Sales Order created for 500 Qty.
    I had run the MRP using MD03 with the following parameters
    Processing key              NETCH      Net Change in Total Horizon
    Create purchase req.     1                  Purchase requisitions in opening period
    Delivery schedules       3                  Schedule lines
    Create MRP list            1                  MRP list
    Planning mode              1                  Adapt planning data (normal mode)
    Scheduling                    1                  Determination of Basic Dates for Planned
    System had generated Planned Orders for Qty 500 and these are converted to Production order for Qty 500 for which the Purchase Order for 500 are created.
    Goods receipt of 480 has been made against the Purchase Order for the Ordered 500 Qty.
    When I re-run the MD03 the system is generating the new Production Order Qty 0f 20 which is not supposed to be as this 20 Qty was already part of the existing Purchase Order and yet to be delivered .
    Could you please explain me why this is happening?
    regards

    Dear,
    MRP will consider the firmed PR for the completion date contained in the PR. If the requirements date is different, then MRP will create a new proposal (PR).
    If you wish for MRP to RESCHEDULE the dates of existing firmed purchase reqs, instead of just creating new proposals, you have to set the Rescheduling horizon. OPPQ> Rescheduling (plant) or OPPR >Recheduling Horizon (MRP Groups). Start with a small horizon,  Also check the tick mark for firm reciept there.
    Are you getting any expection message in front of PR?
    MRP will 'assume' rescheduling by configuration, by managing the rescheduling horizon, and by setting the rescheduling tolerances. These config can be found in
    OPPQ select Rescheduling
    or, for MRP groups
    Please check and come back.
    http://help.sap.com/saphelp_erp60_sp/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar

  • Create a production order

    Hi All,
      I tired creating production order using CO_ZF_PRODUCTIONORDER_CREATE. But It doesn't work. I tried using another function module CLOI_CHANGES_UPL_31. If anybody has used any of these FM or knows of any other FMs, please get back to me.
    Thanks,
    Hema.

    Try Using one of the following BAPIs:
    BAPI_PRODORD_CREATE            BAPI: Generate Production Order                         
    BAPI_PRODORD_CREATE_CAP_REQ    BAPI: Create Capacity Requirements for Production Orders
    BAPI_PRODORD_CREATE_FROM_PLORD BAPI: Convert Planned Order into Production Order       
    BAPI_PRODORD_CREATE_FROM_REF   BAPI: Create Production Order with Reference Order      
    REgards,
    Ravi

  • Capacity Requirement From Released Production Order

    Hi PP Gurus,
    Can i limit capacity requirement only from released production order ? I don't want to count requirement from production order that just created but not yet release.
    Regards,
    Arman Lie

    Dear Arman,
    As a standard practice the system creates the capacityrequirements once the production order is created.
    Check this,
    When a production order is created the following actions are carried out:
    ·        A routing is selected, its operations and sequences are transferred to the order
    ·        The bill of materials is exploded and the items in the bill of material are transferred to the order
    ·        Reservations are generated for bill of material items held in stock
    ·        The planned costs for the order are generated
    ·        The capacity requirements are generated for the work centers
    ·        Purchase requisitions are generated for non-stock items and externally-processed operations
    Regards
    Mangalraj.S

  • How to put sales order on hold

    HI sap minds ,
    help me how can i put a sales order on hold , through va01 .

    Add delivery block and/or billing block.

  • How to create production order for multiple items having common raw materia

    Dear all,
    We are running a sheet metal fabrication company at Vadodara Gujrat.
    Please guide us how to create single production order for multiple items using single raw material??
    For example, We want to produce baby shirt(item code AAA001), shirt with full sleeve(item code AAA002), shirt with half sleeve(item code AAA003),shirt slim fit (item code AAA004),shirt loose fit(item code AAA005) from single raw material say(item code XXX001).
    Right now we have to create 5 production order to produce above 5 items of single sales order  in SAP B1 though it is made from single raw material which is foolishness and time consuming too. (Please also note that to produce any finfish good item, raw material required for that item may vary every time in our process.)
    Kindly guide us how to solve the problem.
    Thanks.
    RUPESH  +91-9227744273
    WEB : www.gorasia.co.in

    Hi Rupesh Gorashiya,
    This is possible through MRP for that you have to put Sales Order first and Run MRP Wizard
    MRP Wizard Put Multi Production Order as per Item Taking in Sales Order just click it on and execute.
    Thanks,
    Srujal Patel

  • CO Production order(KKF1) Status Profile

    Hi,
    We are using CO production order(KKF1)
    as per user requirement eventough order status is REL they want to run the settlement(KO88)
    but once we run KO88 system showing the error like order status should be DEL or TECO 
    I think its possible through STATUS PROFILE but I donu2019t know how we can put the conditions in the Profile
    so any one help me on this
    Regards,
    Ram

    Hi Ram,
    You may consider to deactivate the message KV011 by using transaction OPR4_KKS and
    OPR4_KKS1???
    Regards,Declan

  • Production Order CLOSED

    Dear gurus
    How can I modify SAP to be able to put a Production Order that is delivered to a
    CLOSED status (& not TECO) to avoid future cost being added to them and
    by the same token avoid any future settlement in subsequent periods.
    Regards

    Hi,
    Immediately after DLV, if you do your Settlement then you can set DLFL (Deletion Flag).
    With this no future costs can be posted to your orders.
    If your Order Status is CLSD then also no posting of costs allowed for your Orders.
    If your Order status id DLV or TECO then only the Order will be cosiderd for Settlement.
    If you want to block the Costs posting for TECOed Orders then you can go with : T. Code BS22
    This is the T. Code wherein you can modify the Standard SAP Behaviour with reference to Production Order System Statuses.
    If you want to the DLFL ststus to your Order then you can execute the program : PPARCHP1.
    Hope this helps..
    Revert for further discussion.
    Regards,
    Siva

  • Object table for production order

    Hi all,
    I want to create a print program to create a barcode label (sapscript) triggered out of a shop (production) order.
    I know for example for deliveries, all delivery data are stored into the NAST table.
    Is there a similar table for production order that holds the necessary data?
    Thanks
    Anne

    Hi,
    Tables for production order
                         AUFK                    Production order headers
         AFIH                    Maintenance order header
         AUFM                    Goods movement for prod. order
         AFKO                    Order header data PP orders
         AFPO                    Order item
         RESB                    Order component     
           AFVC                    Order operations
                         JEST                    Object status
         AFRU                    Order completion confirmations
    Regards,
    Vishal

  • Automatic production order creation and confirmation

    Dear all,
    I am in a situation where i have to configure the SAP system in the following ways:
    1. From the planned orders automatically production order should be created today for the next day production and the end user will re-declare the quantity if there are any changes in the production order.
    2. If there are no re declarations to be done SAP should automatically release production order and save it.
    3. After the goods are produced the confirmation of the order should happen automatically from the measuring points.
    4. In the order confirmation, the storage location for goods issue should be automatically captured from the goods issue slip.
    5.After the confirmation of the order the goods receipt should happen automatically.
    Please suggest me whether these are possible in SAP or not.  If yes please tell me the procedure.

    HI,
    I hope this will give you the clear picture
    actually my scenario is:
    Finished good= x
    work centers involved = WC1, WC2.
    HERE BOTH THE WORK CENTERS ARE IDENTICAL, INPUTS ARE SAME AND OUTPUT IS THE FINISHED GOOD "X"  FOR BOTH THE WORK CENTERS.
    I HAVE A ROUTING FOR THE FINISHED GOOD "X" WITH TWO GROUP COUNTERS AS (1)WC1 AND (2) WC2
    When i create plan in md61 for 1 month and when i do mrp run in md02 it will create the planned orders and we can see the stock requirements in md04 and when we double click on the planned order we can convert them into production orders.
    But my users requirement is, he want to run the mrp in md01 and after that automatically each day the production order should be created.
    example with the above work centers and materials:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 200 kg on 30.11.2011.
    so SAP should generate production order for WC1 AS 100KG AND WC2 AS 100KG on 29.11.2011 at 5 pm automatically  and the user will release the order.
    similar example:-
    i have done the mrp run for "x" for November and December months
    i want to produce "x" of 400 kg on 03.12.2011.
    so SAP should generate production order FOR WC1 AS 200KG AND WC2 AS 200KG on 02.12.2011 at 5 pm automatically and the user will release the order.
    Please suggest me how to do the configure settings for my users requirement.
    Thanks,
    Aravind.C

  • Goods receipt not ticked in production order converted from sales order req

    Hi all,
    In MTO scenario, where requirement trigger from Inquiry -> Quotatation -> Sales Order -> Plan Order -> Production Order, goods receipt indicator in production order was not checked if requirement is triggering from sales order, however it is ticked if requirement trigger from inquiry, therefore we are not able to do confirmation. Appreciate if anyone able to assist us as soon as possible.
    Thanks in advanced.

    Hi,
    I understood that---
    If u r creating Sales order directly without Quotation u r  not able to do the GR.
    If u create from Quotation, u r able to do GR. right?
    I think, Problem with Settlement. Please Look into that.
    Kiran.

  • Goods receipt not marked for production order trigger from sales order

    Hi all,
    In MTO scenario, where requirement trigger from Inquiry -> Quotatation -> Sales Order -> Plan Order -> Production Order, goods receipt indicator in production order was not checked if requirement is triggering from sales order, however it is ticked if requirement trigger from inquiry, therefore we are not able to do confirmation. Appreciate if anyone able to assist us as soon as possible.
    Thanks in advanced.

    Hi,
    I understood that---
    If u r creating Sales order directly without Quotation u r  not able to do the GR.
    If u create from Quotation, u r able to do GR. right?
    I think, Problem with Settlement. Please Look into that.
    Kiran.

  • Material backflush in production order after finished goods GR

    Dear all,
    I once started similiar topic several months ago, but didn't recieved any response. I'm gonna give it another try, so maybe you'll be able to support me after all.
    So, the situation is like this. We have a production order, in which MC team maintained the materials to consume. The problem is, that very often it comes that we have to use same material part, but under 2-3 different partnumbers. E.G.:
    Production order target: 1000 finished goods
    Required materials: Part A 1000 pcs, Part B1 700 pcs, Part B2 300 pcs, Part C 1000 pcs, Part D1 150 pcs, Part D2 450 pcs, Part D3 400 pcs.
    So yes, in case when it is Part B1, B2 and etc. it means that we're using physically the same part, but under different partnumbers. The problem is, that those material are all coming in pieces, not in meters or anything, and we can't allow to have, for example, 0.7 pcs of any of those materials (cause obviously you can't have 0.7 pcs of LCD panels stored in the warehouse).
    It wouldn't be a problem if we could just confirm all operations in production order in 1 batch, but production order is being confirmed partially, every time the pallet with finished goods is being released from production line (we have integrated system, that sends requests to SAP to confirm specific quantity of finished goods in production order). So, as an example, if 1 pallet contains 15 pcs of finished goods, you have 67 confirmations for production order [(66*15)+(1*10)]. And, since all those materials come in PCS, SAP is rounding up consumption if it has decimal, which leads to wrong materials consumption.
    Initially, I had an idea of adding 1 more operation in production order, which was supposed to be a manual use only, after finished goods GR, and MC team supposed to assign those B1\B2 and etc. material to this operation  E.G.:
    Operation 0010 - consume material from work center A
    Operation 0020 - consume material from work center B
    Operation 0030 - finished goods GR (milestone)
    Operation 0040 - consume material from work center C
    My idead was rejected, since I was told that after GR for finished goods is done and you continue consuming materials in production order - it will not be shown in financial reporting (don't know the details, it was quite a straight reject, without much explanation).
    So, question is - is there a way to consume materials after finished goods GR without creating mess in financial reporting, or if not - what other options do I have?
    thank you in advance

    Hi Valentin,
    After GR also you can do goods issue. Till the order status is CLSD (Closed) you can book cost on to the order.
    Two ways to consume materials on order.
    In order component overview maintain the required part number with quantity. GI as can done with reference to order MB1A 261 movement type.
    Directly do GI with MB1A -261 movement type - Input the order number, material number and qty.
    Refer to the below discussion on unplanned GI which was discussed yesterday,
    http://scn.sap.com/message/14850196#14850196
    Thank & Regards,
    Ramagiri