Reg: Combined work center / Capacity requirement planning .

Hi,
i need few informations  regarding work center.
1. Can we create Resource (for process industry) similar to that as Work center which we create for (discreate industry)
   can i use the workcenters (CR01) instead of Resource(CRC1) to my master recipe. is there any impact by using workcenter instead of resource to master recipe..?
2 In foundry we are using some Iron Plates for resting of Moulds. And these Plates we are having in limited numbers in Foundry.
Arond 30  Now  i want to create a resource for this..? How to consider this Plates for resource..? Whether M/C or what..?
We are planning to carry out Proper scheduling and capacity planning for this resource.
3. And May i know how to carry out Proper scheduling and capacity planning of resource.. So if capacity is not available ,i should be not able to go-head even with the releasing of order. How to carry out this. Is any customization required.
4. Can we create combined resource  Ex: Crane  and laddle.
I need to create these two resource has single resource ..is it possible..? may i know how the costs/ time to capture.?
Please let me know.......THANK U IN ADVANCE.
Edited by: dan01234 on Dec 30, 2010 6:21 AM

Dear
Frist of all , I would appreacite if you can create seperate theard as you have multiple question .Refer : http://wiki.sdn.sap.com/wiki/display/HOME/RulesofEngagement
However , please find the answers :
1.. Can we create Resource (for process industry) similar to that as Work center which we create for (discreate industry)
can i use the workcenters (CR01) instead of Resource(CRC1) to my master recipe. is there any impact by using workcenter instead of resource to master recipe..?
Yes you can with Usage Type 009.But there may be diffienece in Standard Value Key and Formula Key  which will be used  for calcuating activity  and also Capacity Reuiqemenet .
.2 In foundry we are using some Iron Plates for resting of Moulds. And these Plates we are having in limited numbers in Foundry.Arond 30 Now i want to create a resource for this..? How to consider this Plates for resource..? Whether M/C or what..? We are planning to carry out Proper scheduling and capacity planning for this resource.
A resource is plance where certain operation will happend sequentially as per Master Recipe or Routing .If you have Plate where you carry our certain engineering optiaon rather utlising thoem at requorce to excute the opration , then you can very well create them as resource or work centre .This Resource /Work centre will be having optaion , material , scheuling , CRP etc .Do u think that u will doing the same for Plate ??
If you are interested to carry out CRP/Scheduling the refer this theard : Capacity Leveling of Work Center
4. Can we create combined resource Ex: Crane and laddle.I need to create these two resource has single resource ..is it possible..? may i know how the costs/ time to capture.?  :
Yes you can  if both of them are intregal part of the resource /work centre as per as Setup , Machine , labour hrs is concern based on selection of Standard value Key and Formula Key .Wor centre or Reosurce cost captured through Actvity type ( KP26  with fixed or variable rate aginst costing elenemts) and Formula Key as assinged in the reosurce or work centre -Costing tab .
Check and revert
Regards
JH

Similar Messages

  • Long-term planning: planning details of work center capacity

    Hi,
    we need to know what is the effect on planned production orders (generated by MPS, transaction MD40) of the flag <b>&#8220;long-term planning&#8221;</b> in planning details of work center capacity (table name: RC68K; field name: KAPLPL). We made a test  analyzing planned orders scheduling details in <i>Stock requirements list</i> (MD04) and in the <i>Planning table</i> (CM21) in both cases: with "long-term planning" flag set and without this flag for the same work center.
    The schedule of planned production order on that work center is the same in the two instance.
    Could you suggest us something?
    Thank you.

    Hi Rudy,
    Purpose for carrying out Long Term Planning to simulate impact of Future Demand Program on
    u2022 Material Requirements
    u2022 Capacity Requirements
    u2022 Material Cost budgeting (activity by Accounts dept.)
    T.Codes used -
    u2022 Demand      MD61, MD62, MD63
    u2022 Scenario Creation     MS31, MS32, MS33
    u2022 LTP Variant  Creation & Execution     MSBT, SM37
    u2022 LTP statistics Evaluation     SM37, MS04
    u2022 Data Set Up     MS70, MSB&
    u2022 Evaluation based on Set up data     MCB), MCEA, MCEB, MCEC
    u2022 Capacity Evaluation     CM38
    To Summarize -
    u2022 In long-term planning, production plans for future demand programs are simulated using MRP runs with reference to the planning scenarios.
    u2022 The parameters for the simulation in the simulation planning area are defined in the scenario.
    u2022 The Evaluation of LTP Statistics enables identification of Material for which LTP processing was terminated.
    u2022 The Data set for purchasing & Inventory Control enables reports for demand analysis
    u2022 LTP run with setting for u201CLead time scheduling and capacity planningu201D enables simulation of capacity situation/overload on work centers.
    Hope it is helpful to you.
    Srini

  • Blocking of work center capacity for capacity planning

    How can i block a work center capacity for capacity planning during Machine breakdown( via a Preventive maintenance order)?
    i believe it will reduce machine capacity, yet how can i view this, against the previous capacity? is there a possible report or can it be shown through a transaction?

    Hi,
    In capacity header details screen not exactly as "can be used for capacity evaluation " but
    "relevent to finite sceduling"
    "can be used for several operations"
    "long term planning"
    these all indicators you can deflag this and check the results ,it may helpful to you.

  • Work center-CApacity-Work force planning

    Dear Expert !
    Please tell me all necessary steps to configure Work center , Capacity and workforce planning .........please provide me all the information of business scenerio where I can use this at user level....with screen shot.
    Thanks in Advance
    ROBERT SMITH "HP"

    Check out below links....
    http://help.sap.com/bp_bblibrary/600/Documentation/Q60_BB_ConfigGuide_EN_US.doc
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPPS/PPCRP_PS.pdf
    Venkat

  • Work Center Capacity Intervals

    HI,
    Where can I get the work center capacity interval dates i.e. valid from, valid to and corresponding week days that are being populated in the table control when you follow the following path in transaction IR03->Enter Work Center and Plant-> Press Enter->Go to Capacity Tab-> Press Capacity Button on the lower left hand corner->Press Intervals and shifts
    My requirement is to calculate the weekly capacity of a work center. I have to find the valid interval for current date then find the number of working days in this interval so that I can use it in calculating the weekly capacity.
    Regards,
    Bharat.

    I de-bugged the main program behind IR03 and found out that the Valid-from-date is being calculated during runtime for all the records from table KAPA for given work center KAPID.
    Anyway thank you all who cared to check the thread.
    Regards,
    Bharat.

  • Work center capacity header freezed

    Dear Gurus,
    we're  not able to edit the work center capacity header. not able to edit the start and finish times.
    it is happening only for one work center. in other work centers same capacity category is editable.
    Please help us in resolving this.
    Regards,
    Gowri

    Hi,
    Check your work center categeroy definition for which edit is not possible.
    The work center category determines which data can be maintained in a work center.
    Each work center category is assigned to the applications (for example, production, plant maintenance or quality management) whose menus allow you to maintain work centers with this category.
    Each work center category has a number of screens assigned to it which the system displays when work centers of this category are displayed. The screens contain groups of fields (for example, scheduling data). Depending on the work center category, you can make field selections on these screens (for example, defining required entry fields).
    Thanks,
    nandha

  • Work Center Capacity Shift Interval

    Hello,
    I'm looking for a function or Tables from which I can get Work Center Capacity Shift & Interval data, Transaction CRC3.
    Any help in this regard will be highly appreciated.
    Regards,
    Hashir Ahmed.

    hi,
    check these tables.
    AFIH     Transparent table     Maintenance order header     Application table (master and transaction data)
    AFKO     Transparent table     Order header data PP orders     Application table (master and transaction data)
    AFRU     Transparent table     Order Confirmations     Application table (master and transaction data)
    AFVC     Transparent table     Operation within an order     Application table (master and transaction data)
    CABN     Transparent table     Characteristic     Application table (master and transaction data)
    CBPR     Transparent table     CO-ABC: Activity Master Table     Application table (master and transaction data)
    COEP     Transparent table     CO Object: Line Items (by Period)     Application table (master and transaction data)
    CRCA     Transparent table     Work Center Capacity Allocation     Application table (master and transaction data)
    CRHD     Transparent table     Work Center Header     Application table (master and transaction data)
    CSKS     Transparent table     Cost Center Master Data     Application table (master and transaction data)
    CSSL     Transparent table     Cost Center / Activity Type     Application table (master and transaction data)

  • Work center capacity

    Hello experts
    I am truing to compare between actual Work center capacity (I am using data source 2LIS_04_P_ARBPL).
    And standard work center capacity (transaction cro3 in the R3)
    I canu2019t find an info cube or data source that will help we extract the standard capacity.
    Thanks.
    Tal shalom

    Hello,
    You can use [0PP_C13 InfoCube (Capacity Load Utilization)|http://help.sap.com/bp_biv170/BBLibrary/documentation/B58_BB_ConfigGuide_EN_DE.doc]
    Thanks
    Chandran

  • Block PP Work Center capacity  when breakdown maintenance order create on that work center

    Hi All,
    My Client want to Block PP Work Center  capacity when breakdown maintenance order create on that work center, how can i do it ..
    Please help me.
    Payal

    Dear Sir,
    I have Done Every think but still Production Order is create.
    CM50
    OIOI
    CO02
    Payal

  • Any ideas what tables work center capacity gets its data?

    I am looking at cube 0pp_c13 in BW and it looks at capacity.  I can't seem to find the underlying table it pulls from to populate the structure.  would anyone know where to look?  I've looked in the code and it seems like it is already filled by the time it gets to the extractor so i can't tell where it pulls.
    thanks

    Hi,
    Pl check table:CRCA
    Work center capacity is allocated here.
    Regards,
    Senthilkumar SD

  • Work center capacity graphical view

    Greetings!
    How do I see work center available capacity in graphical form?
    Also how can I see work center capacity utilization in graphical form?
    -Hemant

    Hi
    I don't exactly remember, the T-CODE is CM02 or CM03.
    Regards
    MUHAMMAD HUNAIN AHMED

  • Maintenance Work Center : Capacity Planning CM01

    Hello Gurus,
    We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
    After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and  capacity of these not Released orders also taking into consider.
    How to restrict CM01 Order selection based on the work order System status or User status ?
    I found below discussions on SCN but couldn't get precise answere.
    Plant Maintenance: Capacity planning CM01/ CM07
    Configuring profiles in CAPACITY PLANNING (CM07)
    Please help.
    Thanks in Advance
    Ashok M

    There are a few ways:
    Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
    Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
    The above settings can then be defaulted via the various capacity planning profiles.

  • Combine Work Center Link Groups in one Work Center

    Hello Experts,
    our requirement is to combine the Work Center Link Groups of several Work Centers into one Custom Work Center.
    For example, the work centers Knowledge Management and Managing Operations. (IC-MGRKM, IC-MGRMA)
    They have Work Center Link Groups like IC-MGMA-CR or IC-MGKM-CR. Now we defined an own work center Y-IC-MGRMA and assigned these links groups (and others) to the Work Center.
    However, when we open the Work Center we only ever see links of one work center type (for example only the links of Knowledge Management).
    Is it even possible to combine the different work centers into one big work center with many links? What would we have to do to achieve this?
    Help would be appreciated!

    If I am not wrong you are assigning standard work Center Link Groups like IC-MGMA-CR & IC-MGKM-CR to newly created Work center Y-IC-MGRMA .If I try the same, all related links can be made visible. The process you are following is correct.
         You may have confused with the nomenclature of your work center ID - Y-IC-MGRM. Please look into the "Group ID" column, if you are assigning standard group links as mentioned above you will find three logical link ID for Knowledge management & two for MGMA too. In short if five logical links are available in second level navigation then things are correct at you end. I tried it and its working fine.
    Pease check.
    Thanks & regards,
    Amit

  • PP work center capacity and link in Equipment master

    Dear All
    My client has five equipments which he is clubing them into one work center with five capacities. In equipment master i have given for respective equipments i have given PP work center locations but when i create a maint order for one equip then in planning the capacity avalability is affecting the entire work center for ex if the total work on one equip is 12 hrs then only 8 hrs of capcity should be deducted for to day and 4 hrs for tommorow but in plannig all 12 hrs are getting deducted in todays capacity itself.
    Pls give some inputs from your experiances
    Thanks and Regards
    Pankaj

    Hi,
    Even if we have more than One Equipments in the same work center, PP-PM integration will work.
    This is the standard scenario in any Process Industry or in case of an Assembly line of a Automobile manufacturing industry.
    So it should work. Please check the following points again,
    1. Assignment of Work Center to Equipment Master
    2. System Condition - '0' Not in Operation in Both header as well as against Individual Operations (in Work Order for that Equipment)
    3. Work Order has been released.
    4. Same Work Center is used in Routing and the same is Planned for a period.
    If we have all the above points right, then while dispatching the Production Order system should show the Period of block and should shift/plan the PO accordingly.
    Regards
    Sam

  • Work Center(Capacity Level) Change Documents

    We have a requirement to capture work center change documents at the capacity level which I understand is not supported by standard SAP; note 352485(point 15). Is there, though, a customized solution that can be developed? Any thoughts would be greatly appreciated.
    Thank you in advance.

    Hi Usman,
    I have already tested the method you are mentioning. You cannot save a order without work center. So, you need to use a dummy work center and change all the open orders.. if you want to change capacity category from A to B. New capacity category should be mentioned in dummy or original work center.
    When you replace the work center, order will be gng for scheduling.. which leads to change of Basis start date and earliest start date... this is an inconsistency...
    To avoid it... i followed below steps
    1. Uncheck the capacity requirement indicator in all open orders
    2. when u try to delete, it will say "Capacity is still being used"
    3. Table KBED, use capacity ID and run, it will list out the pending orders
    4. When the table has no entries, delete the capacity category
    5. check all capacity indicator
    - Pithan