Hi,
What is standard flow of PS ? Can Anybody tell in detail the process flow for Project System?
What is the process flow difference betn PP & PS?
Awaiting for Reply,
Rg
SM

Dear,
Please follow this
1.Project Structure Creation
Creation of Project Definition, WBS Element, Network, Activity(Internal, External, Cost, Service) (Tcode: cj20n)
2. Planning:(Tcode: cj20n)
Date Plannnig
Material Planning
Service Planning
3. Execution (Tcode: cj20n)
Change Project Status / Project Release
(status change CRTD-REL)
Confirm Activities (status change REL-CNF)
4. Reports:
Progress: cne5
Plan/Act/Variance s_alr_87013432, s_alr_87013542
5. Project Closing
Settlement (Tcode: cjb2, cj88)
Close Project (status change CNF-TECO-CLSD) (Tcode: cj20n)
For PP please refer this,
[PP FLOW|http://www.sap-img.com/production/discrete-manufacturing-the-step-by-step-tcodes.htm]
Regards,
R.Brahmankar

Similar Messages

  • Problem regarding SAP Project System & Material Management

    Hello Experts,
    please check our process as below:
    Order confirms than sales order and project will create
    material of BOM is assigned to any activity in project so these material (RM) will be procured and consumed
    assign activity for all work done on material to produce FG or SFG.
    confirm activity whenever any work done like fabrication done so confirm and its cost comes to WBS.
    than we have to subcontracting process so dispach SFG from this and receive after activity done by third party.
    than more work is done and confirm these activity. than after all work done we get FG in stock. than delivery from project.
    We are facing issue in above business process of our client as below:
    1. process of subcontracting using project system as we are not using production planning. how we get any SFG for subcontracting process.
    2. if we confirm all activities and consume all Raw Materials than how we will get finished good in our project stock for delivery.
    3. after delivery from project how sales order affects with regards to completeness of this sales document.
    Please help for this.
    Note: Remember we are not using PP cos customer require detailed report of these process and capacity planning etc.
    Thanks
    Sunil

    Hi Sunil,
    Assume this is my project structure & attached components. I will procure this components externally. After GRN, This components will be issued to network with 581 Q movement type.
    Now we need to assemble this raw material to produce our FG, As these SFG are in our project stock. What we need to do for assembly process through PS.
    Also throw some light over benefit of using PS-BOM interface ( CN33 ) for attaching material components.
    Project
    WBS
    Network
    Activity A
    Gears
    Qty - 1
    Activity B
    Blades
    Qty - 2
    Activity C
    Stand
    Qty - 1
    Activity D
    Connectors
    Qty - 1
    Regards
    Gaurav Ahuja    

  • What is project systems are related to fico

    hi sap gurus anybody clesrly tell me about  project systems are related to fico   ,  and what are the relations to these sap fico and ps?
    regards
    venkatareddy

    The Project System guarantees close and constant monitoring of all aspects of your project.Projects are generally part of the internal processes of a company.
    There is no orgnization structure of project system like in FI ( Company code), CO ( Controlling Area), Funds management ( FM area).  but it depends upon other.
    Therefore, The high degree of integration between the Project System (PS) and other SAP  application components means that you can plan, execute, and account for projects as part of your normal commercial procedures. This means the Project System has constant access to data in all the departments involved in the project.
    Further, in project system mostly controlling & ligistical is more important.
    Plz assign point as way of thanks

  • Buget Exceed problem regarding material transfer in project system

    Hello Sir,
    I have a problem regarding budget in project system.
    when i do budget and release . and do any transaction
    with that budgeted wbs element in particular project.
    i get budget excced errors usally.
    however, budget remains more than exceeded buget.
    Let us touch with a example in brief, we have a buget for a L&T project 10 Lakh.
    Buget                                         Release                                          actual cost                                            total cost commitment
    10Lakh                                       10Lakh                                             8lakh                                                         1Lakh
    when i transfer a material from another project to this L&T project material worth is 50thousands.
    i get a errors for L&T project budget exceed with 40thousands.
    however in project budget remains 1Lakh remaining .
    why system shows errors for this material transfer worth rs 50thousands
    Please help me regarding this problem where is 1lakh budget
    with regards
    sanjay agrawal

    Hello sir,
    there is no any problem regarding budget supplement but if project sometimes
    remains 20lakh buget price remaining out of 50lakh.
    and need 1 lakh material price for transfer in project
    then why need to do budget supplement for 1 lakh if project
    remains 20lakh price rest.
    please guide me for above problems
    with regards
    sanjay agrawal

  • Regarding the process flow of project system

    Dear Sapgurus,
    I am working new ps project in our client place . The process which i mentioned for a ps flow is sales enquiry,
    design approval, procurement, production, deliveryetc apart from this anything i mention so i request anybody to suggest the business process while starting a customer project and new project development.
    regards,
    muralidhar.t

    Dear Murali,
    Welcome to PS World.
    See link which is given by Venkat Sir.(It shows process)
    Its very tough to explain whole process.
    Plz refer this link.
    Deffntly it will help you.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/80/ea89395eb58c4f9d0c3e837cf0909d/frameset.htm
    PS cycle
    Re: Enterprise structure for PS
    Re: Why we use Project system?
    Regards
    Chandra

  • Regarding Project systems

    Hi,
    i am not getting the required any info from help.sap.com for Project system module...can you please share any docs if you have?
    Thanks & Regards,
    Vijaya

    Is <a href="http://help.sap.com/saphelp_nw04/helpdata/en/b9/60073c0057f057e10000000a114084/frameset.htm">this</a> not enough?

  • Material or any links regarding Project systems

    Hi Guys,
    Can u provide me the basics and the detail info abt the Project systems,and also the datafowand terminology in the project system.
    Cheers
    Sunil Reddy LCP

    Hi,
    Please refer to the below URL which is quite exhaustive.
    http://help.sap.com/erp2005_ehp_02/helpdata/en/04/926eae46f311d189470000e829fbbd/frameset.htm
    Hope this will help you.
    Best Regards,
    Rakesh Pradhan

  • Regarding configuration cycle for sales order linking with project systems

    Hai Sap professionals,
    i have a scenario like engineer to order. where i manufacture PC's for my customer as per their request.
    Some may order AMD's and some Intel processor etc... now how i should start linking everything a brief idea if any can tell it will be helpful...
    with regards

    hi,
    In make-to-order production with cost management using a project, all costs and revenues relating to the make-to-order item are collected and allocated to a project in the SAP Project System. The costs are allocated to profitability analysis.
    Prerequisites
    Make-to-order production is controlled by the requirements type. The requirements type is determined on the basis of the MRP group and the strategy group in the material master record.
    Up to Release 3.0, the requirements type is determined on the basis of the item category. For this reason, special item categories are used up to Release 3.0 for controlling make-to-order production. To carry out make-to-order production for a material with cost management using the project, you must maintain the following fields in the material master:
    MRP 1
    MRP Group
    MRP 2
    Strategy Group
    Screen
    Field
    In addition, a plant must be assigned for make-to-order items in the sales order.
    for detailed set up please refere the foll link:
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/dd/5600b1545a11d1a7020000e829fd11/frameset.htm
    regards,
    Siddharth.

  • Sales order in Project system

    Hi All,
    Can u tell me please how can we create  a sales order,Quotation in projects and what are tcodes for that.
    As i am here involved in Capital projects i dont have any idea of customer projects ican u pleease let me know the customizing part too.
    Assured of rewarsd points
    Thanks in Advance.
    Regards,
    Abraham.S

    Hi,
    to create quote from project system there is quite a bit of PS ( project system ) SD integration is required. i will try my best to deliver with whatever time i have right now.
    1. t-code -CKCM - your will define easy cost planning here whihc will be your pricing factor in in sales order.
    2. ODP1- you define DIP profile here you will also define your costing elements here. this DIP profile is attached to sales doc type. and on main menu you will find button that says quotation. click on that. this willd irectly take you to quote and from there u can take it forward.
    I hope it helps u little. Though i know its not enough.

  • About reversal of Outbound delivery generated from Project system due to sale return

    Hi SAP Expert ,
    We have made delivery from project system using t.code CNS0 and billing document is generated with reference of sales order. Now Goods is return by customer due to some technical reason, We created return sales order with reference of billing document  and Credit memo with reference of Return sales order.
    What is T.code for making return delivery or reversal of  Delivery /PGI generated from Project system in sap r/3 ?
    Pls. suggest to me.
    regards
    VKM

    Hello,
    it depends whether in the billing document the material codes identifies the goods delivered and to be returned or not.
    If it's so, you can create a Return Sales Order with reference to the billing document, create the return delivery, and then the credit memo.
    If it's non so, you can create a Return Sales Order with reference to the billing document (but without copying the material items, and entering manually material code and quantity to be returned), then create the return delivery. Then you can create a Credit memo request with reference to the Billing Document or with reference to the Return Sales Order.
    To create the return delivery, you can run VL01N with reference to the Return Sales Order (just like for outboud deliveries), or from VA02, following the menu path "Sales document --> Deliver".
    Best regards,
    Andrea

  • WBS Elements not getting created in ECC Project System from CRM 7.0

    Dear all,
    We are trying to integrate SAP CRM 7.0 with SAP ECC-PS module. The objective is to bring in the marketing plan and elements data from the CRM system, and to create the corresponding WBS in project system. We have done most of the configuration as recommended by SAP in both the systems, and we see that the BDOCS are getting generated and sent to the ECC system. The following steps have been successfully completed:
    1.       Set up the RFC connections between the two systems
    2.       Selected the connection type as Middleware in CRM system.
    3.       Installed the cProject Add on in CRM box.
    4.       Created a project scenario (with project and network profiles) in the PS system and assigned the same in the CRM system.
    5.       The Project Scenario in PS config has the same name as the Project Type in CRM config.
    6.       Created and released the campaign ids being created in the CRM system.
    As already mentioned, we can see that the BDOCS are coming to the ECC system and are getting stored in BDOC_TRACK table. However the issue is that the corresponding WBS elements are not getting generated in the ECC system. Is there anything that that we are missing in the ECC box which would trigger the WBS element creation?
    Request you all to share your inputs which would be immensely beneficial for us in achieving this integration.
    Thanks and Kind Regards,
    Aditya Shrivastava

    Hello Aditya,
    We too are facing this issue.. if you have resolved the issue could you please let us know the solution ?
    Some inputs related to our system,
    We have upgrade from CRM 4.0 to CRM 7.0 SP07 and R/3 backend system is on 4.7 SP27, earlier we have completed the upgrade on sandbox without any issues which was upgrade to CRM 7.0 SP04 but with SP07 we are facing the problem of WBS Element not getting created in R/3.
    Your help is highly appreciated.
    Thanks & Regards,
    Sumukh Kapoor.

  • Sub-contracting through Project system.

    Hi
    Can some one please help me in understanding how Project system (PS) is supporting sub-contracting scenarios.
    I am looking for activity sub-contracting and also sub-contracting with Project stock materials.
    I am aware of normal sub-contracting through production order and also sub-contracting through MM. I am specifically looking for sub-contracting in PS.
    Thanks and warm regards,
    Jagadeesh

    Hi,
    If requirements for subcontract items (or services) are generated automatically from PS just make sure that the right document category is used (subcontract) then any requisitions or planned orders etc. will have the right category.
    There is no difference between PP, PS and PM effectively, they all use subcontracting in the same way it is just how the requirement is triggered that is slightly different.
    If you need details on how to trigger the right type of requirement through PS then you may need to use one of teh financial forums that cover PS? (is there one?)
    Steve B

  • Creating Project Profile in SAP R/3 Project System

    Hi All
    While creating a project definition in Project System in SAP R/3, it is the mandatory to select a Project Profile from a pick list. How can I create a new project profile for myself?
    Thanks
    Sheenam

    It is mandatory to select a Project Profile while creating a Project Definition. Project Profile can be created using OPSA transaction.
    regards
    Shravan

  • Project System Cash Management in combination with statistical WBS element

    Hi,
    within  a customer project, we have to solve the following issue:
    Customer runs projects and statistical projects in combination with internal orders.
    We want to use the PS Cash Management for planned and actual payments.
    With statistical projects we have the following problem:
    Invoice and actual payments will be processed with the transaction CJFN.
    Actual payments are shown only on the internal order (transaction CJIA), but not on the statistical WBS element.
    We want the information about the actual payments with in the project system reporting (S_ALR_87013574).
    Projects, not flagged as statistical will deliver the expected results.
    Many thanks for your ideas, to solve this problem.
    Steffen

    are u posting to some other cost object also. normally they wud have to be posted to a COPA also with the cost element being 11 category.
    the wbs will receive the statistical posting, so there needs to be a real object also.
    see whether the real object is getting derived.
    the system is nt finding the real object and trying to post with the WBS in real, but since its statistical, the error.
    any other calrifications. plz post.
    regards
    anantha

  • Milestone payment for vendor in project system

    Dear sapient
    As per our client requirement vendor payment is based on the basis of milestone i.e activity based. As per the contract agreement payment is made on the basis of certain percentage as mention below.
    1st payment 5% of total order value (with out tax)
    2nd payment 10% of total order value  (with out tax)
    3rd payment 65% of total order value (Including tax 100 % )
    4th payment 20% of total order value (with out tax)
    Is there any standard or workaround functionality available in sap for vendor payment in project system ?
    Regards
    Soraj

    Thnx for reply
    As per our requirement payment is based on completion of work. can i use payment term on the basis of completion of work/activity not on due date basis?

Maybe you are looking for

  • My IPad 2 doesn't recognize the camera connection kit

    My ipad2 does nit recognize my camera connection kit. Actually the kit is recognized but when I put the chip or plug in the USB camera cable nothing happens. I'm using a Sony Dsc-Tx10 camera. It worked before but now it doesn't. Please help. I'm tryi

  • What is the difference b/w CDMA A 1429 and GSM A1429??

    m uning the iphone 5 A1429, it is made from california and assebled in china, how can i differentiate wich one is it ( CDMA) or  GSM???

  • How can I transfer contacts from htc wildfire to iPhone 4

    How can I transfer contacts from htc wildfire to iPhone 4?

  • Email output type.

    We have created a custom output type to send an email confirmation. The config was done with transmission medium 7. RSNASTSO has been copied into ZRSNASTSO as processing program and the routine being called within this program is SAPOFFICE_AUFRUF_VX.

  • IDOC status 62 -  IDOC passed to application

    Hello Experts, Am posting a inbound sales order custom/extended IDOC into the system from WE19, but, when I saw it in WE02/05, its showing status 62 - IDOC passed to application, i checked ST22 run time error. there is no error and also checked trigg