Relation between PO Qty and Minimum Lot size of material master

I have maintained "100" in minimum lot size ( MRP1 View, table MARC and field BSTM) for the material.
I am also succssed to create the Purchase order for 2.5 Qty for the same material. '
I wanted to know, how system is allowig to create the PO with lesser qty or is this view is maintained only for sales?
Please give your expert comments on the same.
Thanks,
Vikas
99301 03991

Used for claculate the procurement qty during MRP and depends on the lot size procedure you select. quota arrangement also uses this lot size.
[http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d26ad44af11d182b40000e829fbfe/content.htm]
Edited by: Karthik on Jul 8, 2011 9:47 PM

Similar Messages

  • Issuance (pack size) Qty and Minimum Lot Size

    Hi Experts,
    I have a problem, I have to maintain Minimum Lot Size and issuance (pack size) in the material master. Suppose Minimum Lot size of one material is 2000 and Pack size vendor provides is 400.
    Means, when we place order, minimum order can be made for 2000 Nos and when we issue the material to WIP from Main Store the minimum issue quantity should be 400.
    How can we map in the system.
    Please help me.
    GR

    Dear,
    I would like to suggest as :
    Maintain the Base unit of measurement for material as PAK/CARTON/EA.
    In additional data, unit of measurement mention 400pc = 1 ea/carton.
    Whenever issue the material from stores, the quantity should be 1 ea (i.e 400 pcs) basing on base unit of measurement.
    Now comes to minimum order quantity should be 2000 pcs.
    Maintain ORDER UNIT in purchase tab of material master as PC.
    To restrict the order quantity must be 2000 pcs, In that vendor master
    Order optimisation restrictions u2013 quantity. This is useful while ordering the vendor.
    For example if the quantity to shipped from this vendor you enter as 2000 pcs. When creating purchase order, if quantity is less than 2000 the system will give message.
    Try this in quality with a full cycle of documents.
    Regards,
    Syed Hussain.

  • Rounding value and Minimum lot size

    Hi all,
    Finish material is X and Raw material is Y.
    Bom- For Preparing Xu2019s 1 Qty, 1 Qty of Y is required 
    In Material Master of Y - Rounding value and minimum lot size is 10,
    Project needs 5Qty of X.
    When MD51 for Project execute u2026 PR of Y must be of 10 as per rounding value and minimum lot size, but it is creating PR of 5 qty.
    Above scenario working properly if I take MRP run with MD02 for material X for 10qty, after MRP PR of Y will be created for 10qty.
    With Regards,
    Ashish

    Dear,
    By default, the lot size works as lot-for-lot quantity in the make-to-order and project scenario.
    Go to OMI4 select your Lot size and define Lot Size: SOP  1 or 2Lot-for-lot with rounding. Better create new Lot size as ZX with these setting.
    If you always want lots to be created for the multiple of the rounding value, you must specify a minimum a multiple of the rounding value.
    Example: minimum lot size: 10 and rounding 10.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Fixed lot size and Minimum lot size

    Dear senior,
    My client has the following scenario. His supplier provides the item in a fixed lot size of 100. The minimum lot size to be ordered is 300.
    The supplier is a fixed vendor.
    I tried to maintain this information in the Material Master MRP views. Lot size  - FX, Fixed lot size - 100, Minimum lot size - 300.
    However, everytime, the minimum lot size will get reset.
    Is there any way , I can maintain this scenario via configuration or any other method?
    Thank you.

    Hi,
    Fixed lot size - 100 means for every 100 quantity system will create one purchase document.
    If you selected Lot size - FX - Fixed order quantity , then no need to maintain Minimum lot size & Maximum lot size fields.
    Then you have to maintain Fixed lot size filed only.
    Ex: 
    Lot size = FX
    Fixed lot size = 100
    There is a requirement of 300. Then system will create 3 PO's with quantity of 100 each.
    If Lot size is Ex - Lot-for-lot order quantity, then only need to maintain Minimum lot size & Maximum lot size fields in the MRP 1 view.
    Ex: Lot size = EX
    Minimum lot size = 60
    Maximum lot size = 100
    There is a requirement of 250. Then system will create 3 purchase documents, two documents with the quantity of 100 and third one with the quantity of 60.
    That's why, in your case system is reseting Minimum lot size every time.
    If you want to maintain Minimum lot size, then maintain
    Lot size as EX
    Minimum lot size = 100
    Max lot size = 300
    It will solve your problem.
    Regards
    KRK

  • Lot for lot(EX) with minimum lot size

    Hi Experts,
    Is it possible to have Ex with minimum lot size. I have a situation where an FG cannot be produced over a certain qty but can be produced in any numbers beyond that. Please explain.
    Regards,
    Sachin

    Hi,
    You can use Lot size key EX- lot for Lot order and Minimum lot size as per the requirement. If the lot size is smaller than the Minimum lot size qty procurement proposals will be created for the minimum lot size quantity.
    Hope it resolve your issue. Kindly revert for further clarification.
    thanks and regards
    muru

  • Rounding Value,Minimum Lot Size and Maximum Lot Siz parameters

    Hello Gurus,
           Please explain me the what is the use of the parameter Rounding Value
    ,Minimum Lot Size and Maximum Lot Size parameters in the product master and how does it in impact during the Heuristic Run?
    Thanks.

    Rounding value is the incremental quantities in which the order can be produced/procured. Eg. if orders are possible with quantities 40,60, 80, 100 etc..then rounding value is 20.
    Min lot size is the minimum quanity in which order can be produced eg. 40 in above example
    Max lot size is the maximum quanitity in which the order can be produced/procured. eg. 100 in our example
    Impact on Heuristic run: heuristics takes all the above parameter to plan supply order. eg. if requirement is 55, it will supply plan for 60. If requirement is 120, it will produce two orders - one for 100 and the other for 20. if the reuqirement is 10, the order size will be 40.
    Hope this helps.

  • Difference between Fixed order qty and Fixed Lot multiplier

    Hi All,
    Can someone explain me the difference between Fixed order qty and Fixed Lot multiplier in general planning tab at item level with example.

    Hi,
    Thanks for the reply. Just bit more clarification i need to understand the difference.
    Like for example let us assume two cases.
    Case 1:- order less than Fixed order qty (Fixed order qty =50 and the FIxed lot multiplier =50)
    Let us assume that we have set Fixed order qty equal to 50. We have a physical order of 40 then still MRP will place a order of 50 only. In case of tumhi snagaSame is the case of Fixed lot multiplier it will place a order of 50
    Case 2:- order greater than Fixed order qty (Fixed order qty =50 and the FIxed lot multiplier =50)
    Let us assume that we have set Fixed order qty equal to 50. We have a physical order of 60 then still MRP will place a order of 50 twice. Same is the case of Fixed lot multiplier it will place a order of 100.
    eventually we are doing the same in both the case so what is the exact differnece.

  • Minimum and max lot size

    Hai All,
               Can anyone please tell exactly from which table we can get the data "Minimum and max lot size".
    Is it "MAST" or "PLKO" or "MARC"?

    Hi Kavitha,
    check with the table MARC and the fileds BSTMI (Minimum lot size ) BSTMA  ( Maximum lot size )
    for more info
    Re: Table for Lot size.......
    hope it helps you.
    Thanks!
    Edited by: Prasanth on Mar 7, 2009 7:26 PM

  • Minimum Lot Size Ignored

    Hello All,
    To replicate scenario, I have created new material with minimum lot size 10 pcs and created independent requirement (LSF) and then created scheduling agreement.
    Independent requirements as 8 pc for every day.
    Now when I run the MRP and check in MD04, for the last requirement, planned order was raised for just 9 pcs, ignoring minimum order qty/minimum lot size functionality.
    Just for information, Lot size -EX, MRP type PD, Strategy group 10 (though these factor doesnot influence).
    Any more settings/customizing required?
    BR,
    Krishna

    Dear Krishna,
    I guess you must have activated the check box for Last Lot Exact for the Lot size - EX in T.code OMI4.
    If so means remove this and then check with new requirements and MRP run with planning mode - 3.
    Regards
    Mangalraj.S

  • Minimum Lot Size with Rounding Value

    Hi I have an interesting scenario.
    I just want my procurement proposals to be generated in multiples of 40000. But I have agreed to my vendor on Minimum Lot Size of 75000 qty. My aim is to generate the proposals with 80000 qty even for the demand of 25000.
    But when i am carrying out the MRP run for the demand of 20000, ssytem is plan only for 75000. But when i increased the demand to 50000 or more system plans in multiples of 40000, i.e. 80000 qty.
    Is there by anyways can we plan in multiples of 40000 eventhough the min lot size is 75000 and the demand is 20000?
    -solai

    Hi,
    Maintain lot size as EX, Minimum lot size as 80000 and rounding value as 40000 in the MRP to get the procurement proposals in multiples of 40000.
    Regards
    Venkat.V

  • Relation between STD Price and Costing

    Hi,
    Could anyone explain about the relation between STD Price and Costing & when and where it gets effected.
    Points will be rewarded.
    Regards

    Hi ,
    Std. Price :-
    A constant price at which a material is valuated without taking goods movements and invoices into account.
    Costing:-
    The value of use of economic goods both tangible and intangible for the creation and sale of goods and services, as well as the acquisition and maintenance of plant and machinery.
    A process that calculates the cost of goods manufactured, or the cost of goods sold, in relation to a product or cost object.
    The results of costing are used to determine the following information:
    Target costs
    Variances for materials produced
    Contribution margin for materials sold
    The costing process is based on the order quantity or the costing lot size in the material master record.
    Edited by: vk on Apr 24, 2008 7:17 AM

  • Relation between GL Account and Invoice?

    Hi Experts,
    I am working with the FI reports for the first time and I do not have any idea on FI functional flow. I have some basic questions like
    What is the Relation between GL Account and Invoice?
    When will an Invoice be posted into BKPF, BSEG, BSAD, BSID, BSAK and BSIK? Is there any field in these tables which gives the Invoice number against which a GL Account is created?
    For example if I want to calculate " no of vendor invoices without PO how can I do that"? How can I know what are vendor invoices created against a PO or without PO?
    Thanks for any help in advance and I am bound to reward points.
    Sri

    <b>What is the Relation between GL Account and Invoice?</b>
    SAP's Glossary for GL Account is
    "A structure that records value movements in a company code and represents the G/L account items in a chart of accounts.
    A G/L account has transaction figures that record changes to the account during a posting period. These figures are totals that are used for G/L reporting."
    In accountancy, an account is a label used for recording and reporting a quantity of almost anything. For example when a company pays salary to its staff, They debit Salary account. This is to identify what is the nature of an expense.
    An invoice is a message to the buyer of goods or services that contains, among other things, Name of the goods or services, Quantity sent, & Remuneration due.
    Invoice is also a SD document used to charge a customer for a delivery of goods or for services rendered.
    <b>When will an Invoice be posted into BKPF, BSEG, BSAD, BSID, BSAK and BSIK? Is there any field in these tables which gives the Invoice number against which a GL Account is created?</b>
    If it were a vendor invoice. (i.e you purchase items or service and recieve invoice)
    Invoice get posted to the tables once someone makes a Logistics Invoice verification through t-code MIRO etc. The teble RBKP gets the first posting.
    If it were your own invoice to your customers, then VBAK and VBAP get the posting.  The connectivity of tables are available in http://www.erpgenie.com/abap/tables.htm As far as SAP is concerned an invoice is a document, so you can only trace invoice as a document number, field name is usually BELNR. Even if a vendor invoice arrive, an internal invoice number is generated where the vendor invoice is entered only as a reference field. This is because, each vendor can have inovices of different size and pattern.
    <b>How can I know what are vendor invoices created against a PO or without PO?</b>
    For a purchase order you can find in table EKBE for BEWTP = Q any invoice document.

  • Creating a master-detail relation between a view and a table

    Hi all,
    I have a problem with creating a master-detail relation between a database-view with lots of customer data and a small table with per customer a list of entities of our companies who may work for that customer.
    Somehow I seem to be unable to create a relation between these two. I can't find where I can make a foreign key using Toplink to implement the relationship. And neither can I get a Viewlink object doing the job using ADF Business Components.
    Somebody any suggestions on this problems?
    Regards,
    Birgit

    There is a key relationship between two fields which form the primary key in the main table of the view and two fields in the second table.
    I created a viewlink manually, but I still couldn't get the data correct i.e. a form with one record of a customer from the main view and a small table with all entities of our company who can make performances for that customer.
    I tried to find a manual or a how-to on this topic but I didn't find anything helpfull yet.
    Regards,
    Birgit
    After a couple more tries, I got the master-detail working. With all the fiddling I am not sure what caused the problem but I think the finally action was checking which fields of the view were marked as primary keys.
    Now everthing is up and running.
    Birgit
    Message was edited by:
    user492355

  • MRP Settings - Minimum Lot size / Saftey stock /Lot Size

    Hi
    I am confused about some of the settings , We set M1(Monthly lot size ) and PD MRP type settings, We maintained the Minimum lot size as 2500 lb and the safety stock as 300.
    I tested by changing the Parameters , I am confused.
    Please clarify me
    Did MRP is going to suggest the PR once if the stock went below 300 ?
    Did MRP is going to wait for the PIR to get accumulate the Minimum lot size settings ?
    What will happend if the time bound is beyond a month ?
    Please help me to understand the concept
    Thanks
    JJ

    Hi,
      Use tcode OWD1 to create rounding profile.
    Select create icon for creating new rounding profile.
    Input new profile name.
    In that Threshold value & Rounding value is available.
    Input your value & save.
    In MRP1 view give the input of rounding profile.
    Example given below for easy understanding.
    Threshold value  Rounding value
        1- 20 -
    >                20
      60- 100 -
    >              100
      900-1000 -
    >           1000
      8000-10000 -
    >     10000
    If your requirement is 7, it will convert to 20.
    If your requirement is 23, it will convert to 40.
    If your requirement is 76, it will convert to 100.
    If your requirement is 435, it will convert to 440.
    If your requirement is 844, it will convert to 860.
    If your requirement is 910, it will convert to 1000.
    If your requirement is 8045, it will convert to 10000.
    Hope it will helps you.
    Regards,
    Dharma

  • The relation between table mbew and mbewh

    MORNING!
      I wanna know the relation between table mbew and mbewh.
      I finded some materials in table mbewh have total valuated stock , but these materials don't have value .
      Thanks a lot !

    Hi Roy, please check this link.
    http://www.sapfans.com/forums/viewtopic.php?p=4330&sid=a1b0e2c950bb90aa410b796d9ce0a13c
    REgards,
    Rich Heilman