Release of production orders
i have created production order with order type amit but i get messages in log that no checking rule is maintained for operation,Availability check cannot be executed for capacities how to proceed
In transaction OPJK, maintain the checking rule say PP for acombination of plant and order type for business function 2 and 1, and also see that checking group is miantained in MRP3 view of product material master in the plant.
Similar Messages
-
Error while release of production order u201CNext period is not openu201D
Hi Experts,
Need your opinions on this issue where my client is facing a problem while create and release a production Order on the last day of the month (Last day of period change).
While create and release of production order for Plant xxxx, system uses to give the error; period Next (e.g. 12) is not open. Same thing if I have created the order using T. code CO01; but when I tried to release and save the order through T. code CO02 then it gave me the same error (Next period is not Open), it checks for the next period to open.
The above scenario happens only on last day of the month. Earlier this kind of error was not there so the question is why the period check is happening while saving the production order.
After speaking to the user, it is determined that they are facing this problem since upgrade (Since last 8 month). Hence need to check what additional check has been implemented with upgrade from R/3 4.7 to ECC 6.
Error Message No F5201
Appreciate your help how to dig up this issue.
With Regards
AnantHi Guys,
Please throw some light why on the last day of the month (Last day of period change) at the time of release the order user is getting error: Period Next (FI Next period) is not open ( message No. F5201).
My question is why system carried out period checks at the time of release of Production Order.
With Regards
Anant -
Re:No release of production order without standard cost estimate
Hello Experts
I do not want to release any production order without standard cost estimate
I have come acroos the same problem raised by some other users and can you please suggest how to achieve this?
Is there any way to achieve this without user exit?
Thanks and Regards
SubbuHello Subbu,
In this case, you need to put the status as "B4" Blocked in costing 1 view of material master, when you create the costing view and change it to "03" status when you released the cost estimate.
Please note that this field can be overwritten in MRP view also. Hence please get the good control of material master and good coordination with PP team to achive this.
Please let me know if you require any clarifications.
Thank you,
Regards,
Santosh
Please reward points if helpful. -
IDOC on create or release of production order
Hi All,
I want to create IDOC on creation or release of production order (CO01), can anyone provide me steps and setting that i need to do to achieve this functionality. Business object used for his is BUS2005, and on release of Production order RELEASED event of object type AFVC_PM is getting triggered.
ThanksCheck below badis.
AFABD_CHANGE
CAUFVD_CHANGE
SIDAT_UPDATE
Regards,
Mkhan -
Automatic release of production order for perticular work center
hello,
any body please help me how to set automatic release of production order when creation for a particular work center. please suggest me.
Thanks & Regards
BhaktaDear,
Use T Code COHVOMRELEASE here select work center as ZPACK then in header menu Program--Schedule in background here define as perodic job and set ferquency as Hr.
Or Use Transaction SE38 to create the variants for program PPIO_ENTRY and schedule it through SM36 or use standard variant as SAP&RELEASE.
Please try and come back.
Regards,
R.Brahmankar -
Problem while releasing the production order.
Hai gurus,
When i release the production order , SAP doesn't block when i have a deficit of stock for some materails.I checked all the customizing and found every thing is fine.
As the materials that has defict stock has back flush indicator, is that the reason why the system is assuming the stock when releasing.Hi,
You need to consider the following customization settings
(1) OPJK - For the Plant/Order type/Availability check-2 for the material availability - Release material - set the indicator '3' No release if parts are missing
(2) OPJJ - For availability check & checking rule - check what all elements are considered as part of ATP check.
With these settings - in the production order if the order header has status MSPT - Missing parts (i.e. components are missing) only then system will stop the release of the order.
I hope this addresses your query
Warm regards,
Umesh -
Control availability check during release of production order
friends,
Can you guys help me find the user exit/BADI which will allow me to control the release of production order after the availability check is complete.
In detail, the scenario is that : based on a flag on material master, I should be able to ignore this product's availability during release. I cannot change the availability check to "KP" ( No check) as this product can be sold seperately. So what I thought was that if I get to control the availability check during production order release I would be able to ignore this product before check or may be after check and before the status change.
I found PPCO0021 exit and function module EXIT_SAPLCOZR_003 which is actually intended for release control for automatic batch determination. I am not sure if I can use this.
Please let me know if you guys have any idea.
Thanks
Prod_PlannerLet me rephrase the scenario :
I have a production order for a product P1 which consumes raw materials R1 and R2. R1 is supplied by a nearby vendor every 1 hour to my plant so I do not need to worry about the availability of it when releasing the order but R2 availability should be taken into consideration. So, function 1 or 2 in OPJK will not work (as release need to be stopped if R2 not available) hence I will be using 3. If I use 3, R1 availability is also considered hence the whole order is not released. I will maintain a flag on material master so if R1 has flag, I need to ignore R1's availability but still considering R2.
As mentioned, I found PPCO---21 which could help me but need your help to understand if there is any other way.
Thanks
Prod_Planner -
Exit or Badi: On release of Production Order
Hi,
Module PP.
Q) Say, equipment is under maintanance so it should give warning message while releasing the Production order through CO01.
Note: it should give message while releasing the Production Order and not when saving it.
Regards,
SujitCheck below badis.
AFABD_CHANGE
CAUFVD_CHANGE
SIDAT_UPDATE
Regards,
Mkhan -
Error when release the production order
Hi all,
while release the production order i am getting the error :- Plant 1000 is not the only plant assigned to valuation area 1000 , how to resolve this error .
& can we release the prod order without calculating the cost ?
Thanks & regards
satishHello,
I'm facing the same issue when trying to create a production order using tran. CO01 with inputs (Material: P-100, Production plant: 1000, Order type: PP01. Next the total quatity of material is chosen freely, Dates/start is set to todays date, Scheduling is set to Forwards scheduling).
Error message :
"Plant 1000 is not the only plant assigned to valuation area 1000"
Message no. CK238
As explanation SAP says:
"Diagnosis
You are attempting to use material costing or order costing. However, the system has determined that plant 1000 is not the only plant assigned to valuation area 1000.
Costing is only possible when each plant has its own valuation area to which no other plants are assigned.
System Response
It is not possible to cost in your system.
Procedure for System Administration
Go into Customizing for the Corporate Structure and check the valuation level. The valuation level must be the plant level"
The error message implies that the user is not given the opportunity to create and save a production order.
I have secured the followings:
1. Valuation level is set to Plant level so that the valuation is now done at plant level. (The other option was at Company code level, which is not checked.)
Question:
Is there a solution to this problem?
Thanks and Regards!
Edited by: WilliamG on Feb 16, 2010 4:04 PM -
Sap pp-releasing the production order?
at are the activities carried out while releasing the production order?
Hi,
Order Release
Use
A production order must be released, before it can be processed. You can use the time period between creating and releasing a production order, for example, to carry out company checks and preparations. If you do not require this time period, you can automatically release the production order when it is created (see Automatic Release).
A newly created production order initially receives the status CRTD (created). The following restrictions apply to a production order that has been created:
Confirmations for the order cannot yet be executed.
Shop floor papers cannot be printed.
Goods movements for the order cannot yet be executed.
Releasing the order lifts these restrictions.
Features
Order release can be executed at the following levels:
With Release at Order Header Level all operations are released. The order and the operations receive the status REL (released).
With Release of an Operation the operation receives the status REL and the order receives the status PREL (partially released). If all operations in an order have been released, the order has the status REL.
Hope this helps.
Revert if you need more information.
Regards,
Tejas -
Release a production order for partial quantity
Hi gurus,
Can you please tell me how can i release a production order for partial quantity without splitting the order?
Regards
Rajib PathakDear,
Best way you can conver the planned order to production oreder in partial in CO40.
Or from MD04 screen click the planned order, choose pratial release and enter the quantity you want to release and press Generate button. the order gets converted to production orders of yr specified quantity and rest planned order remains for further processing.
Or,
Create order
Goto operation overview
Select the operation and click on release button...which will release the opration alone instead of releasing the order. If you release the order, then all the eperatios are released onec for all.
If you go for operation release...you can release operation by operation, which will be partial release of order at header level.
at operation level - partial release
Hope it will help you.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Nov 12, 2008 9:44 AM -
Error during release of production order - AFS Specific
Hi SAP gurus,
Iam getting error during release of production order in AFS specific system during COHV transaction. Error is ''Error calling ATP server'' and message no is AG022. But when we read the PP master data then this error is cleared and production order is released.
Thanks & Regards,
N. Laxmanhi
1. When mass conversion of AFS planned order to production order is performed via COHV, the resulting production order does not contain the SKU details of the component.
2. When a planned order is converted to a production order & an ATP is carried out on the production order, Message no.AG022 - 'An error occurred during Remote Function call on the ATP Server' is issued by the system.
so you need to use the note 1087613.
read the note and apply with the help of technical team ABAP and BASIS
-ashok -
Batch release of production orders
Dear PP Gurus,
Is there any program / functional module which i can execute in background to release production orders.
I would like to release the production order automatically in background (I do not want to perform custmization setting which relase production orders when created). I would be glad to have a program / logic to perform the same - Thanks!
Regards
SeshuThanks for your quick response.
I would like to know if we can run CO05N in background ? I dont want user to execute CO05N.
Do to client business it is not possible to configure SAP system to auto release.
Regards
Seshu -
Release a production order thru sales order
Hi all,
Hope everyone's doing well.
Can anyone guide me as to how we can release a production order thru a sales order and henceforth confirm it?
Thanks in advance,
Thanks & Regards/Aryanyes it is [possible to convert sales order to production order directly.
You can use strategy 82 for this. -
No release of production order without standard cost estimate
Hi All,
I have an requirement, that is production order for a material should not be released or saved if standard cost estimate for that period is not released. Basically it should not allow to release or save the production for that material, is SCE is not run for that period. I tried various options, i also overheard its possible through user exit and many people have succeed in that.
Has anybody overcome this problem, please do let me know. And which user exit??
Thanks in advance
With Best Regards
GJ.Hi...
I have faced the same problem in my previous project. What i have instructed to my client is to take control of Master data and put the status as "03" Blocked for movement till the statndard cost is released for this material.
You can relase the status to "E2" in Cross Plant Status Field in Costing one view once the cost estimate is released for the material.
I hope this works for you.
Please let me know if you require any fruther information.
Thank you,
Regards,
Santosh
Rewards points if helpful. -
Releasing of Production Order without Cost-Run
Dear Sir,
We want to incorporate a check in the system so that no Production-Order should be released unless the Manufactured component (component being manufactured in the Production Order) has the proper cost run . By proper cost run mean that standard cost for the component is greater than 0 .
Kindly guide us . Full marks are asssured for the suggested solution please .
Regards
B MittalHi,
Try with user status and the conditions specified in Bs02
Regards,
nandha
Maybe you are looking for
-
iMac 27" 2009 intel core 4 gigs of ram, 1tb HD, Current operating system. 2 user accounts, myself, my fiancee's. Each with iPhones so each setup to utilize iCloud. I have disabled 3rd party plug-ins once with only short-term effects. There are other
-
SQL Server 2005 Vista Problems
I have 3 databases in SQL Server 2005 that I want to connect to. Everything works fine in XP, but when I try to set it up on Vista I get all sorts of problems. All software is latest version with all available updates installed. After restarting the
-
Third party application for Intel-based iMac
Greetings y'all...anybody out there know of a list of third party apps for Intel-based Macs???
-
can someone help please? I am trying to do a factory restore. I have tried the reboot/plug in to laptop and do it through itunes method and i got a failed message saying there was a glitch with the phone. I have never set a 4 digit security code in t
-
hi gurus, iam unable to load data into heirarchies...can u plz help in loading the data to hierarchies and creation of hierarchies thnak u in advance