Release Strategy-estimation cost and po cost

Hi
Client issu like...in RS
We are maintain our estimation cost in Ztable(Zdev).Purchase order net value is Actual Cost.
My Purchase order cost is less then Estimation cost .NO Problem. We config the RS some Level.
But My PO cost is Greater then Estimaton Cost ,that time client wants some RS in purchase order.
How will i configure Release Starategy Negative Deviation occur in comparison Statement?
Example estimation is RS 10000 (ztable)
Actual PO cost is RS 13000(Ekko)
Now Run Zreport (ZComp) The system Will give 3000 is negative deviation
Nagative dev  RS 3000
Above The RS 3000 ,How will i configure Release Strategy In PO?
Rds
Kavi

Hi kavi,
can you please eloberate your issue,
as i under stood you are setting the releasestrategy for PO price.

Similar Messages

  • Estimated Cost and Actual Cost

    Hi Friends,
               Can someone tell me, which MM tables(logically database) has these fields stored?? Estimated cost and Actual cost??
    Note : Where and How can I find the logical data base??
    Thanks alot in advance,

    Yes thank so much for your quick help.
    I see here we can get 1- Plan cots , 4 Actual cost, But in PMCO, how can we get the estimated cost, I see that WRTTP = 1 also contain the value for estimated cost but not plan cost . Please help me.
    Thanks

  • Target cost and actual cost not picking in production order

    Hello,
    The target cost and actual cost is not updating in production order when I display it in CO03 in cost analysis.
    Even though we have maintained planned price in KP26.
    Please suggest how it can be populated.
    Best Regards,
    Tapan

    Hi Tapan
    For Target cost
    1. Your std cost must be released before Goods Receipt
    2. There must be goods receipt posted on the prod order
    3. You must calculate variances in KKS1/2
    For Actual Cost
    1. Post Goods receipt and Goods issues
    2. See if any mat movements are pending in COGI
    3. Ensure that operation is confirmed in PP and no entry is lying in COFC
    Regards
    Ajay M

  • Target Cost and Actual Cost

    Hi All,
    When is the target cost and actual cost gets populated and from where does the data comes from liek labour,machine,overhead cost comes?
    Thanks in advance

    Dear Friend,
    speaking from controlling point of view, target and actual costs will be flown from "costing variant planned" and "costing variant actual" respectively.In above mentioned varinats, whats the process has to be followed to calculate  material costs,activty costs,overhead costs etc will be defined. These variants will be assigned in order type dependent parameters OPL8.
    Target Costs - In standard cost estimate(ck11n),target cost will be calculated  in the following way
                              -material cost from material master and BOM
                              - activity costs from routing( for this u need to plan the activity costs in KP26)
                              - other costs from the definitions of planned costing variant.
                       - after running the standard cost estimate,u need to mark n release(ck24).
    Actual Costs - material costs frm goods issues (via goods mvmts thru MBIA,MB1B etc) against
                          production/process order.
                              - activity costs(as per the price u plannned in KP26)through  operation confirmation in
                                COR6N/CO11N.
                              - any other costs like overheads,cost center issues etc as per the process defined
                                in 'actual costing variant'.
    Hope this will clear your doubt.
    Rams.

  • Preliminary costing and Simultaneous costing

    hello gurus,
                  can any one explain the difference between Preliminary costing and Simultaneous costing in Product cost by Period.
    Regards
    rihana

    In product cost by period you are generally using product cost collectors.  The preliminary cost estimate is the estimated cost for the product cost collector prior to manufacturing.  The cost estimate is calculated when the product cost collector is saved and the estimate is based on the costing variant that is assigned.  Simultaneous costing happens as a result of manufanufacturing and the confirmation process.  It represents the cost of the materials, activitities, and overhead that are actually charged to the product cost collector.  Typically, with product cost collectors materials and activities are backflushed.  The amount of the backflush can be based on the preliminary product cost estimate or a standard cost estimate.  Simultaneous costing uses a different costing variant then preliminary costing, so valuation strategies for materials, activities, and overhead can be different for both as well.
    thanks,

  • What Is The Difference Between Budget Cost And Regular Cost For Resources?

    What's the difference betwee budget cost and regular cost for resources?
    Here is the explanation which I didn't understand from the book;
    In planning your departmental retreat, suppose you
    have specific budget targets
    for certain cost categories, $2,500
    for travel expenses, $500 for printing,
    and $1,000 for conference room rentals. Using Project’s budget resource
    feature, you can define your budget
    for different categories
    of items. You can then group your resources to
    com-pare your budgeted
    costs to your planned costs. This way, you
    can view your travel budget
    of $2,500 side by side with your planned
    costs of, say, $3,700,
    and immedi- ately see that your next
    goal is to find a way to trim those travel
    costs.

    Hi,
    You have to differenciate the proejct budget from the project cost:
    The project budget is the amount of money which has been allocated to your project by the executive board based on the estimation you provided. This is not meant to be changed unless you go through a change request process, justifying why you need to change
    (increase) the budget, meaning asking more money. Consequently it will not be related in MS Project with the tasks, assignments. It is entered on the project summary and can be meanly used in portfolio reports where you can consolidate yours budgets (you can
    have several different budgets) among a set of projects.
    The project cost is something which lives, changes along the project lifecycle. It is meant to be updated on a weekly or biweekly basis from the team members tasks updates approved by the project manager. Then the PM updates the remaining work thus the project
    cost.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |
    You say that the budget cost is total money which committee gave you for the project.
    But the book refer budget cost for every resource. I don't understand that.
    " In planning your departmental retreat, suppose you
    have specific budget targets
    for certain cost categories, $2,500
    for travel expenses, $500 for printing,
    and $1,000 for conference room rentals. Using Project’s budget resource
    feature, you can define your budget
    for different categories
    of items. You can then group your resources to
    com-pare your budgeted
    costs to your planned costs. This way, you
    can view your travel budget
    of $2,500 side by side with your planned
    costs of, say, $3,700,
    and immedi- ately see that your next
    goal is to find a way to trim those travel
    costs. "
    For example here travel budget cost is 2500 whereas planned cost is 3700. Planned cost of travel expense is created by the project manager. Who does define travel budget cost?
    Let's say an employee's cost is 20 dollars per hour and I write it on the project. So how much is this employee's budget cost, Who does define it, From whom do I learn that data?

  • In which table production order planned cost and actual cost i can see?

    Dear PP Guru,s,
    from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
    Regards,
    sree

    Dear,
    Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • Costs and settled costs layout in standard reports

    Hello guys !
    what needs to be done in order to have a report, for example, S_ALR_87013543 , splitted by costs and settled costs (debit/credit) ? I can't find a layout or smth.
    Thanks guys.
    Laimonas

    Hi
    Include this ZPP2 in a separate report group (GR51)... After that,
    1. Create the transaction code,say, ZF01_TCODE from Se93
    2. Choose "Transaction with parameters".. Press enter
    3. Enter START_REPORT in the Transaction field and press Enter
    4. Select the Skip initial screen and Inherit GUI attributes check boxes
    5. On the same screen, scroll down to the Default Values table and select parameters D_SREPOVARI-REPORTTYPE and
    D_SREPOVARI-REPORT.
    6. Enter RW for the report type and your report group ZCC8 as the report value
    7. Now you can save your transaction and transport it to other systems
    Regards
    Ajay M

  • Release strategy for PR and PO

    I have release strategy for PR and PO, suppose there is 3 levels of Release, at second level I want to set an alternative Release code,  if either of the employee releases then it should go to third release.
    How to configure for PO (with classifications) and PR (without classifications). 
    I am not using workflow than how to do it ???

    follow the steps below.
    Release prerequisites should not be checked
    Release statuses do the following settings for alternate release
    based on your requirement
    you can make the release or blocked status manually in release config
    than it will work.
    without classification it will not work

  • Target cost and planned cost

    What is the difference between Target cost and planned cost in discrete production orders? Please advise.

    Dear
    Planned costs will be updated after creation of production order.
    Target costs will be updated after delivery of the production order.
    Plan cost    = Plan qty X Planned price (std. cost estimate)
    Actual cost = Actual qty X Actual price
    Target Cost = Actual qty X Planned price (std. cost estimate)

  • Huge Variance between Target cost and Actual Cost

    Hi,
    In Product Costing,I am getting Huge variance between Target cost and Actual Cost.It is showing the Target Cost as ZERO.Why i am getting this target cost as Zero? what could be the reason? Kindly help me in fix this issue.
    Thanks
    Supriya

    Dear,
    First do the GR final DEV for Production order
    You need to do the variance calculation in KKS2, then when you save the variance, the target cost is calculated.
    Target cost appear after GR.  And you will get the Variance also right.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Function Module to Find Actual costs and Total Cost Commitments

    Hi PS Experts ,
    Please let me know if there  is any function module to  find Acutal costs and Total cost commitments by passing WBS element as Input .
    Regards,
    Karan

    Hi Karan,
    I think for actual cost - there is definately one FM availbale. Try to find it out.
    Just ensure - if you are using Network Activity then you may have to pass NWA OBJNR into this FM to get actual cost. As some entry posting happens against NWA like Timesheet. Hope it will give you some idea to get rid on your issue.

  • Actual costs and Planned Costs

    HI Friends
      I want to know the Main Tables from which i can get the <b>Actual costs and Planned    Costs</b>     for the given Cost element or object number
         I tried with table COEP and i got actual costs up to all cost elements in the given controlling area and in given cost center , but for some cost elements, this tables does not have any entries...
    So is there any other way to get these Actual costs and
    from where i can find the Planned Costs
    Reagrds Rk

    Hi
      I already checked these tables but i didn't get the exact data
      for actual costs i checked COEP but some costs are missing there
      and i could n't find the field BENKZ in coep table
         I am comparing these values with the standard transaction <b>S_ALR_87013611 </b>
      but not getting exact details  in my program
    can you please help me in this regard..
    Does anybody worked on this transaction <b>S_ALR_87013611 </b>, then please explain me the logic how it is getting the actual and planned costs
    Regards Rk
    Message was edited by:
            Rk Pasupuleti

  • Current PO cost and std cost :------ in which table this will be present

    current PO cost and std cost :------ in which table this will be present

    Hi
    For PO cost check it in tcode SE16
    Table name EKBE field Name WRBTR
    For Std price u can check it in Table MBEW - VERPR, STPRS
    Check it out.
    Regards,
    Raman

Maybe you are looking for

  • Stock Aging?????????????

    Hi Experts, Can anybody tell me any standard t-code or procedure to get the stock aging i.e. the current stock lying at any plant is when (on which date) received at that plant. Regards Kuldeep Dahiya

  • Multiple Photos or Labels

    This is a very Newbie question, regarding iPhoto. I can have a photo in Events, Photos,Faces, Places, Photo Stream and Albums. Are they multiple photos or just labels on the same photo. I suspect that it must be the latter, but would like that confir

  • Any Slingboxers out there who can help me?

    I have a new Slingbox Pro and it works with my network plug and play, but I can't get it configured for remote access. I have an Airport Express attached to an iMac, with a second Express acting as WDS. I plugged the SB into the WDS AE and as I said

  • Multi-Clip Scrub Sync Problem

    So im editing an 18 multi cam music video... Each clip I didn't sync by time code, but I made a sync mark at each beginning track so I have a basic rough outline reference point. I marked in each clip so it syncs up to that sound marker... And then I

  • Photostream: Memory issue

    I have a "New Ipad" (i.e 3rd gen) and have turned off photostream and deleted the camera roll after importing the pictures to Iphoto and backing up to my MB Pro in an attempt to regain space on the iPad. There are no photos visible in the photo's app