Report to check open reservations for production orders where GI not posted

Hi experts,
Can we get reservation details from any report/ table for production order where material has not been issued, report should also display the value of the reserved material.
I could not find desired details in RESB (it has price but not value) and MB25.
Thanks in advance, useful ansers will be rewarded.
Thnx
Anand

Hello Anand,
there is no report but you may use the production order info system with list "components" and create a layout contaning the issued quantity and/or the final issue indicator. With a correct sorting, the list should show all orders with non-issued components at the top.
Regards, Andreas

Similar Messages

  • Exclude stock reserved for production order from availability check

    Hi Experts,
    We have a problem in the availability check.
    There is a material used as selling product and components in the same time.
    When the material has been reserved completely for a production order, the new sales order still get confirmed despite there is no physical stock at all!
    Please advise how to exclude the stock reserved for production order from the availability check in sales order? Many thanks!
    Regards,
    Qiang

    Go to MM02 and check what availability check is maintained for that material.  Next go to OVZ9, select that available check with the combination "A" and maintain "X"  or  "F"  in the field  "Incl.production orders".
    thanks
    G. Lakshmipathi

  • Manual Reservation for Production orders with automatic reservations

    Hello SAP Experts, i have a question regarding Order Reservations, in my company when we create a Production order the reservations for each component are created automatically and assinged to a reservation number, the thing is when i try to create a Reservation through MB21 for the same Production order the system says that" for that type of production order i cant generate manual reservations", can you please guide and tell me if i can change this in the configuration ?? , if you need additional info please tell me , thank you in advance.

    Dear German,
    Your system working according to std SAP setting, u don't need to change any config setting. Because wehn u release order, it automaticaly genarates reservation for each and evry component of the order.
    when u do goods issue to order or to reservation either way it gets issue to the order.
    suppose if u need to issue any extra component to the order u can just add in order componet overview before u release the order. so reservation gets genarated for this componets too along with BOM components.
    In case afer release, if u need further components go to MB1A give mov type 261 and S.Loc and then click on new item push button, it pop ups one more window give all required parameters and post the goods. These goods issue will also gets updated in the order.
    But for the order uc an not manually create the reservations
    sree

  • Reservation for Production order

    HI experts..
    The system will reserve the qty once the planed order get generated.
    Will it be possible after the production order release.. the reserved stock should get blocked
    and we sud not use the planed reserved qty for other production orders.
    pls guide me how to do this..

    Sri Ram,
    Availabiltiy checking can give you the functionality I think you seek. 
    Available To Promise (ATP) doesn't exactly 'block' stock.  Instead, each order (planned order, or production order, or Sales order) can be configured to execute an ATP check for components.  You can configure that production orders cannot be released unless they pass an availability check for components.  So, the first production order is released, and because of the way you have set the ATP up, there is no more component stock available.  Now, when you try to release an additional production order, the ATP will fail, and you may not release the order.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/fc/836ae8f66111d2b6a70000e8359890/frameset.htm
    Rgds,
    DB49

  • Issue/Bug in reservation for production order

    Hello,
    We have a bug with the reservations for a production order, which in turn is causing a problem with clearing a cogi error. I have a COGI error for material 123 in plant A.they are trying to remove 14,312 lbs that was confirmed to production order 1000123. According to the error message the production order only has 6,400 lbs that can be removed. in CO14 my material 123 show two quantities in different batch 14,312 and 6,400. In Reservations shows only 6,400 as being consumed. this amount should be 20,712 (14,312 + 6,400). The reservation did not get updated correctly. Why this happen? How could we correct this RESERVATION to add up 14,312 in my material 123)?
    Please give me feedback ASAP, need help.
    Thanks and Regards,
    JJ

    Hello,
    thanks for the answer you have given me..
    as to make sure, does it is safe to delete the error? even that it tells that RE qty moved exceeded by 7.912 lb? it so weird how come was the reservation was complete since when they raised it it just 6,400 it shows? how could i make sure that document goods movement for my production order as mr. pradeep told me to do? what should i do?
    thus when deleting the error in COGI, it will change the my material in CO14 COMPLETED and have QTY WIDTHDRAWN and will be encluded in the same RESERVATION NUMBER?
    Anyone please revert back to me.
    Thanks
    JJ
    Edited by: John Jay Palisoc on Jul 22, 2008 7:08 AM
    Edited by: John Jay Palisoc on Jul 22, 2008 8:02 AM

  • Inspection lot for production order lot and not for single pieces

    Dear all,
    I have a production order , for example, for 12 pieces / serial number . Material is produced in lot , in this case 3 lot of 4 pieces.
    Pieces in a lot are linked toghether in a grap.
    Production order create an inspection lot where I can store quality data for every pieces / serial number.
    I need to store quality data at lot level ( for example the grap weight );
    Is it possible ?
    Regards

    Can you not create Char/MIC like weight & attach the task list to the inspection lot?

  • PP-MM issue in material reservation for production order.

    Dear Friend,
    I am in confusion that this is PP issue or MM issue.
    If any issue if any one knows please provide me solution.
    I run report -MO24- missing part info system.
    System givening me material and requirement date and requirement quantity.
    If stock is availble then it is comming in commited quantity. Thats is agreed.
    But My problem is that that committed quantity is repeated daily though stock is not available in system. Why this is happening???
    Regards,
    Mahesh.

    First, there no such transaction as MO24!
    And secod, please try to clarify your question; what do you mean that committed quantity is there every day without stock?

  • Reservation for Sales Order

    Hi All,
    We have a scenario with reservations in make to order:
    I have a
    Sale order1 for material A: 100 Kgs (Confirmed Qty)
    Sale order2 for material A: 200 Kgs (Confirmed Qty)
    I have created delivery document number 50kgs for sale order 1 and saved. Now when I'm trying to transfer post stock using 413 E movement type from "Sales order 1" to "Sales order 2" system is giving me an error that reservation already exists for 100Kgs. Please clarify on this:
    1. How to reduce the reservation quantity so that I can transfer stock from one sale order to another?
    2. Where can i see the list of reservation created for a sale order?
    3. Can we stop system from creating reservations for sales order? If so what will be the effect of it?
    Regards
    Ayyallas

    Hi,
    Please 1.use MBBS report to get the reservations for sales order. 2.In OVZ9  for availability check don't include SO requirements, to avoid reservation creation for SO. 3.To reduce the stock don't create reservation against movement type(231). To reduce the quantity for sales order, its better to delete the reservation for that sales order and issue the material. For the rest of the quantity recreate the reservation for SO, if needed. If you stop reservation creation for SO, the material might not available if any immediate demand arrises. Thanking you.

  • Reg.Authorisation for Production Order

    Hi all,
    Please tell me that whether Authorisation can be set for Production order Releasing or not.
    My requirement is One person will generate Production But he is not authorised to release it.
    The Other Person who is senior to him is the only person who is authorised to release the Prod.Order.That is once the Prod. order is generated & saved ultimately a message should reach the senior person with the details of prod. order for him to release.
    How to do it.
    Kindly Give solutions .
    Thanks in advance,
    M.Badrinarain.

    Badrinarain,
    You can use user exit PPCO0007 to serve your purpose.
    Regarding the info to reach the senior person, you can talk to your Basis consultant to have the required settings, when any new order is created, it will be informed via mail to the senior person.
    Hope this helps you.
    SmanS

  • User Exit/BADI for Production Order Availability Check

    Hi PP experts,
    Is there any user exit or BADI which can be used for Production Order Availability Check during order creation/release or while running collective availability check (COMAC) to include additional check conditions such as do not commit quantity (commitment qty = 0) if storage location for a component is missing in the production order due to storage location is not maintained/specified for that component in the material master.
    Note: In this case the availability check is set (configured)  to check at the storage location level.

    Dear ,
    Availablity Check is not Plant Specific or Storage Loaction spefic .ATP does not check the stock for any particualar stock in storage loaction rather it cheks various stocks based inward and out ward movement time through PR/PO/Dependent /Planned Order /Stock Type  irrespective of any Storage Location .
    BAPI which can be used :
    1.BAPI_PRODORD_CHECK_MAT_AVAIL
    can we exclude materials of prod order in availability check
    what is availability check concept  how it is used in SAP
    Check the above if it is useful
    Regards
    JH

  • XL Reporter - Prompting for Production Order Number - How to?

    I have watched the FlashBook's for creating reprots, and following the directions. When I go to create a new Paramater, the Document Number is not an available Dimension.
    Can anyone point me in the right direction in setting up an XL Reporter report that prompts for Production Order number / Document ID? How do you create prompts for record ID's?
    Thanks.
    Mike
    Edited by: Mike White on Jun 16, 2008 11:11 PM

    Thank you for the help. This gets me closer then I was before.
    To test, I am list listing the Production Order Document Number and the Due Date. Looking to list only the Production Order and Due Date from a prompted Production Order.
    I tried both Cell Expansion and Row Expansion using the parameter you suggested. Cell Expansion returns all documents, but with a document number of 0. Row expansion gives me an error.
    I have captured all the screen shots and posted them to the web. If you wouldnt mind taking a quick look. I am sure something I am doing is off, but feel I am close with your help.
    http://www.level8systems.com/xlerror.jpg
    Thank you.
    Mike

  • Material availability  check for production order

    Hello,
    Is there any functional module to check the material availability of production order. So that it can be used in developments.
    Regards,
    Ganesh

    Hi,
    Following are the available Function Modules for avaibility checks in Production orders,
    BAPI_PRODORD_CHECK_MAT_AVAIL -  BAPI: Execute Material Availability Check for Production Orders
    And for Process Orders,
    BAPI_PROCORD_CHECK_MAT_AVAIL - BAPI: Execute Material Availability Check for Process Orders
    Regards,
    Dhaval

  • Authorization check for production order settlement

    Hi All,
    Production order settlement currently can be done by any user of any company code. there is a high risk involved in the same since unauthorized postings may happen. Hence we need to add authorization check for production order settlement. Can we maintain the same at the plant or the company code level?
    Waiting for your replies. Thanks in advance!
    Regards,
    Aman Goel

    hi
    What venki has told abt the exit, its absolutely correct.Even i have used the same exit
    •     From table CAUFV pick Material(PLNBEZ),Basic Start Date(GLTRP),Plant(WERKS) .
    •     Pass parameter Material(PLNBEZ) and Plant(Werks) in table MBEW in respective fields i.e. Material(MATNR) and Plant(WERKS).
    •     Pick the latest record for the current period(LFMON) and year(LFGJA).
    •     Pick Product Cost Estimate number(KALN1) from the record and pass it to table KEKO.
    •     Check if Production Order Basic Start Date(GLTRP)<= BIDAT, if NO post Error Message.
    This is the FS for EXit PPco0007
    Reward if useful
    Amit

  • Collective ATP check for production orders

    Hi Gurus,
    I tried the MDVP tcode, but I can only do the collective ATP check for planned orders. we wanted to do the collective check with production orders, can you tell me how I can do this?
    Thanks.

    I've posted this question but didn't get any response. Can some one please give me an idea how to do the collective ATP check for production orders.
    Thanks
    Vijaya

  • Need to change Storage location for reservations in production order

    During Production order creation we need to assign storage location against all the reservations in production order. Is there a way it can be done??

    Hi,
          check the user exit EXIT_SAPLCOSD_001.
    Sudheer.A