I created a process chain that has 3 text file master data loads using the LOADING process type on version BW 3.0B.  If I delete the text file for one of the loads, the load will fail and I would like to restart the load from the failure point.  When I go to the view log mode, I do not to see the option to restart for the failed load when I right click on it.  I checked the LOADING process type and "repairable" is not checked off.  I can't modify this since it's a SAP entry.  I copied the LOADING process type and named it as Z_LOADING.  I checked "repairable" on Z_LOADING.  I changed all 3 data loads to Z_LOADING.  The problem with Z_LOADING is that it will execute the infopackage succesfully but it won't proceed to the next process.  I checked the chain log and it says the it ended with a status of "undefined".  Please let me know what I'm doing wrong.  Thanks.

Raymond,
Unless it is very critical text, have all your text Proc Chains have the "both" option to go to the next load meaning t he next infopackage load will execute even if t the last one terminated. I dont see why this wouldnt work. In your case, it seems to me that the problem was too many dialog processes in your BW Client. Try to activate and schedule the process chain again.
SRD

Similar Messages

  • Restarting Process chain from the middle

    Hi all, I have a question about process chain in BW7.0.
    When the error has occured in the process chain, is there any way to restart the process chain from where the error has occured?
    One of the way I came up with was to set the process type into Repairable from Repeatable,but when I try to change the status,the warning message shows up and I can't change it.
    Is this the right idea,or is there any other way to do it?
    Can any one tell me?
    Thanks in Advance,
    Hiroshi Iwanaga

    First of all, find out the rootcause of the failure of the process step that failed and finish it manually. Then, go to the process chain...
    Open the messages of a failed step by right clicking on it and selecting 'display messages'.
    In the opened popup click on the tab 'Chain'.
    In a parallel session goto transaction se16 for table rspcprocesslog and display the entries with the following selections:
    1. copy the variant from the popup to the variante of table rspcprocesslog
    2. copy the instance from the popup to the instance of table rspcprocesslog
    3. copy the start date from the popup to the batchdate of table rspcprocesslog
    Press F8 to display the entries of table rspcprocesslog.
    Now open another session and goto transaction se37. Enter RSPC_PROCESS_FINISH as the name of the function module and run the fm in test mode.
    Now copy the entries of table rspcprocesslog to the input parameters of the function module like described as follows:
    1. rspcprocesslog-log_id -> i_logid
    2. rspcprocesslog-type -> i_type
    3. rspcprocesslog-variante -> i_variant
    4. rspcprocesslog-instance -> i_instance
    5. enter 'G' for parameter i_state (sets the status to green).
    Now press F8 to run the fm.
    Now the actual process will be set to green and the following process in the chain will be started and the chain can run to the end.
    Of course you can also set the state of a specific step in the chain to any other possible value like 'R' = ended with errors, 'F' = finished, 'X' = cancelled ....
    Check out the value help on field rspcprocesslog-state in transaction se16 for the possible values.
    Assigning points is the way of saying thanks in SDN.

  • Restart process chains and infopackages

    Hi
    Our system was down from last 5 days and I have to check the loadings and reschedule the crashed loads.
    The person who used to check and monitor loadings is on a holiday and I am not too sure how to go reschedule process chains
    We have 4 hrs, 12 hrs and daily loads in a process chain.
    Can anyone advice me how to reschecule them.
    Many thanks in advance

    Hi
    You have to Start them manually by Start -- Change selections -- Immediate -- No other go in your case as far I know.
    You can  manage through sm37 also -- in the Initial screen check only Scheduled -- You will get all the scheduled jobs -- release it and change it to your time to start automatically for this day.(Make sure that you are following system time for it)
    Hope it helps.
    Edited by: Aduri on Dec 18, 2008 5:59 PM

  • Error while Activating a process chain

    Hi,
    I have just modified the existing process chain with the new info package for loading into ODS and then delta update into the Info Cube.
    when i am clicking on the option schedule and activate.
    Its giving error as :
    "InfoPackage ZPAK_49RJW545FSO2MB3NF1MIZ9NJ9 is
    generated; NOT able to be used as loading variant"
    This is a IP, which is used for delta update from ODS to cube.
    I have checked the IP, its fine like i can do the delta through this pacakge manually.
    Please help, points will be rewarded....

    Dear himanshu arora  ,
    Go and check whether the Info Package exist ,
    You can check in Rsa1 and give IP name and find it.
    If your IP is not there please create it,
    If tehre please check the all parameter associated with it.
    Also go through these
    Process Chain Errors
    /people/mona.kapur/blog/2008/01/14/process-chain-errors
    Process chain creation - step by step
    /people/juergen.noe/blog/2008/01/11/process-chain-creation--step-by-step
    Data Load errors and Process chains
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    ope the following links will give u a clear idea about process chains and clear ur doubts.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Siggi's weblogs for data load error and how to restart process chain
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Hope it helps
    Regards
    Bala

  • Error while executing the Process chain

    Hi Friends,
    The process chain that I scheduled is getting failed at the Infopackage loading stage.
    On checking the diplay message, I found the following log:
    Cannot stage requested data for datasource
    Error in source system
    I activated the datasource in source system, then replicated the same and tried to load data.
    But the issue remains the same.
    I checked in RSA7. The status corresponding to this datasource is in yellow status.
    Can I delete this entry and try again?
    Please suggest.
    Thanks in advance.
    Surjit P

    Hi,
    /people/mona.kapur/blog/2008/01/14/process-chain-errors
    Deadlock
    http://help.sap.com/saphelp_nw04s/helpdata/en/2e/44934257a5c86ae10000000a155106/frameset.htm
    Dead Locks
    2. Error in unit conversion
    Units of measure
    3.Error 1 in update
    When Src file is already open or not accessible.
    4.Processing no data
    theres no data selected after extraction
    5.Caller 70 missing
    "• This error normally occurs whenever BW encounters error and is not able to classify them. There could be multiple reasons for the same
    1) Whenever we are loading the Master Data for the first time, it creates SID’s. If system is unable to create SIDs for the records in the Data packet, we can get this error message.
    2) If the Indexes of the cube are not deleted, then it may happen that the system may give the caller 70 error.
    3)Whenever we are trying to load the Transactional data which has master data as one of the Characteristics and the value does not exist in Master Data table we get this error. System can have difficultly in creating SIDs for the Master Data and also load the transactional data.
    4) If ODS activation is taking place and at the same time there is another ODS activation running parallel then in that case it may happen that the system may classify the error as caller 70. As there were no processes free for that ODS Activation.
    5) It also occurs whenever there is a Read/Write occurring in the Active Data Table of ODS. For example if activation is happening for an ODS and at the same time the data loading is also taking place to the same ODS, then system may classify the error as caller 70.
    6) It is a system error which can be seen under
    the “Status” tab in the Job Over View.
    solution:
    "• If the Master Data is getting loaded for the first time then in that case we can reduce the Data Package size and load the Info Package. Processing sometimes is based on the size of Data Package. Hence we can reduce the data package size and then reload the data again. We can also try to split the data load into different data loads
    • If the error occurs in the cube load then we can try to delete the indexes of the cube and then reload the data again.
    • If we are trying to load the Transactional and Master Data together and this error occurs then we can reduce the size of the Data Package and try reloading, as system may be finding it difficult to create SID’s and load data at the same time. Or we can load the Master Data first and then load Tranactional Data
    • If the error is happening while ODS activation cause of no processes free, or available for processing the ODS activation, then we can define processes in the T Code RSCUSTA2.
    • If error is occurring due to Read/Write in ODS then we need to make changes in the schedule time of the data loading.
    • Once we are sure that the data has not been extracted completely, we can then go ahead and delete the red request from the manage tab in the InfoProvider. Re-trigger the InfoPackage again.
    • Monitor the load for successful completion, and complete the further loads if any in the Process Chain.
    6.Idoc not processed completely.
    Here the request remains yellow (in process) and with the same details (as seen in the details tab of the monitor) for an abnormally long time. Many-a-times, the port for communication is not open and re-starting the load helps. For long running jobs, it may not be advisable to restart the extraction
    Contact the BASIS administrator to push the IDOC.
    look into these links:
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    For common data load errors check this link:
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    Majority of the issues will be based on these things only..
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Siggi's weblogs for data load error and how to restart process chain
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Hope this helps.
    pls award me some points
    thanks.
    Thanks

  • How do you run a Process Chain using parrallel processing group

    Does anyone know the answer to the above question please?
    The problem i am getting is that currently the Process chain is running on the client server and is timing out!
    is there a config setting or some other setting that is needed to stop it from timing out?

    Hi Jas Matharu,
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Siggi's weblogs for data load error and how to restart process chain
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    ****Assign Points If Helpful****
    Regards,
    Ravikanth.

  • Process Chains Screen Shots

    Hi friends,
                         Can anyone send me Screen shots of process chains in detail,  How we created process chains and what type of errors we face in the process chains... Can anyone send me..
                               My mail Id  -     <i>[email protected]</i>
    Answering getz appreciated,
    Thanks & Regards
    Aluri

    Hi Aluri,
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Siggi's weblogs for data load error and how to restart process chain
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    ****Assign Points If Helpful****
    Regards,
    Ravikanth.

  • I WANT TO KNOW SOME PROCESS CHAIN ISSUES

    HI ALL,
    WHAT IS PROCESSCHAIN?IN THIS WHAT THE PROBLEMS OCCURED? WHEN WE R EXECUTING PROCESSCHAIN WHAT THE ISSUES WILL COME?

    Hi
    Go through these links...
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum 1 (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    Restarting Processchains
    Siggi's weblogs for data load error and how to restart process chain
    Data load errors - basic checks
    Restarting Processchains
    Restarting Processchains
    GTR

  • Repairing/Repeating Terminated Processes - Process Chains

    Hi,
    Can any one please explain me with a simple example about repeat and repair in case of process chain.
    I’ve referred http://help.sap.com/saphelp_nw04s/helpdata/en/f3/0d4a975f450443be900e89a47ad48e/content.htm but yet I am not very clear about the two.
    Which option do we use under what circumstances?
    Thank you,
    sam

    Hi Sam,
    Normally with Repeat option next processes automatically trigger. But after manual update u should do them manually.
    Check this Function module.
    Look into this FM - RSPC_PROCESS_FINISH and execute with G(complete) this will start the next process automatically without doing anything manually.
    or
    Go to the plan view of that chain, in trasaction field enter '=copy', it asks for the name and description, then u remove the processes which r already ran, connect a start process to which r yet to run ( means to the first process in that). select the immediate option in maintain variant for start process then trigger it.
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/events/sap-teched-03/using%20process%20chains%20in%20sap%20business%20information%20warehouse
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Siggi's weblogs for data load error and how to restart process chain
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Hope this helps.
    Regrads,
    Ravikanth

  • Process Chain step repeat/restart

    I have a process chain which schedules 3 loads to psa and then loads the data into ods/cubes. it often fails here due to data problems. now there are at least 4 subsequent steps that are not executed due to this failure which is correct but i don't want to have to fix the problem with the data by deleting the requests from the ods/cube and correcting in the PSA and then have to do all the subsequent steps manually.
    Once i have corrected the data in the PSA:
    if i repeat the load to ODS step will it continue through the rest of the chain?
    if i restart the chain will it repeat the extract to PSA steps which i definitely don't want it to do?
    or can i schedule the subsequent part of the chain to run from the planning view?

    Hi Richard,
    I guess when there is some data issue, there is always need for manual intervention.
    "if i repeat the load to ODS step will it continue through the rest of the chain?"
    <i>You have to delete the failed request manually from DataTarget before doing this.</i>
    "if i restart the chain will it repeat the extract to PSA steps which i definitely don't want it to do?"
    <i>Yes. Restarting chain will extract the data again.</i>
    or can i schedule the subsequent part of the chain to run from the planning view?
    <i>I don't think you can start a chain from the middle from planning view.</i>
    Regards,
    Sree

  • Restart the process chain

    Hi Experts,
       Pls let me know how to restart the process chain
    Regards
    Vishal

    Hi,
    u can restart the process chain thru function module also :
    Fucntion module : RSPC_API_CHAIN_RESTART
    Also chk this link :
    Re:  Process Chain Kill, Schedule & Restart  Function modules
    Regards

  • Restart a processin process chain

    hi
    can anybody tel me how to restart a process when a process fails. I want to know the load and other processes
    thanks in advance

    Hi Pradeep,
    Hope the following links will give u a clear idea about process chains and clear ur doubts.
    Business Intelligence Old Forum (Read Only Archive)
    http://help.sap.com/saphelp_nw2004s/helpdata/en/8f/c08b3baaa59649e10000000a11402f/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/8da0cd90-0201-0010-2d9a-abab69f10045
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/19683495-0501-0010-4381-b31db6ece1e9
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/36693695-0501-0010-698a-a015c6aac9e1
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/9936e790-0201-0010-f185-89d0377639db
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/3507aa90-0201-0010-6891-d7df8c4722f7
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/263de690-0201-0010-bc9f-b65b3e7ba11c
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    Errors in monitoring of process chains can be categorized into 4 different sections...
    Master data - Full Update
    Master data - Delta Update
    Transaction data - Full Update
    Transaction data - Delta Update.. in terms of loading of data which can be due to server shut down or system maintenance... errors due to incorrect entries in the OLTP system in which case you'll have to fix the errors in the PSA and manually load the data...
    Otherwise it can have errors on Attribute change run being locked by some other job... Aggregate Roll up failing because of attribute change run being run at the same time... Problem with hierarchies and save hierarchies...
    There can be problems with the data store activation if the ODS object contains any incorrect request sitting inside it... then, you need to delete the incorrect request and reload the data again...
    In case of Transaction Delta failure, you'll have to request for a repeat either manually in the infopackage or using the repeat option if available on right clicking the load event...
    For Master Data Delta failures, you need to do an Re-init by deleteing the previous initalization condition in the "initalization option for source systems" in the menu scheduler or reschedule the enitre chain... because, master data generally do not support repeat of last delta ...
    U can even look into these links:
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    For common data load errors check this link:
    /people/siegfried.szameitat/blog/2005/07/28/data-load-errors--basic-checks
    ****Assign Points if Helpful****
    Regards,
    Ravikanth.

  • Function module used to restart the process chain in the middle?

    Hi all,
    can anyone pls let me know the function module to restart the process chain in the middle of the process chain?
    I need to run the process chain from the middle which can be done through a function module can anyone pls let me know!!
    Thanks
    pooja

    what exactly your requirement is?
    You can't trigger the process in the middle either it should be trigger by start variant or it's predessor.
    If your chain failed in the middle - you can fix the prob and can do 'Repeat' option or you can also use FM 'RSPC_PROCESS_FINISH . (this FM will work only if the chain fails)

  • Process Chain hangs on AND process

    Help Super gurus!
    I've tried several versions of a chain that loads multiple InfoPackages serially then multiple DTP in parallel using filtering from the PSA to a DSO. All load successfully. Then I have the DTPs all meet at an 'AND' process before processing should continue to a cube.
    The 'AND' process also shows green but it does not continue to the next process step. It just stops there, no more jobs running, no yellow, nothing. It thinks it's all done, everything after that is still blue.
    Why does it hang there and what can I do to get it to continue?
    Thanks,
    Al
    Points available.

    Hi,
    Not sure what is the root cause in your case.
    Try this. It may work. Normally this is done after a step turns red and no repeat is available.
    Method 1 (when it fails in a step/request)
    /people/siegfried.szameitat/blog/2006/02/26/restarting-processchains
    How is it possible to restart a process chain at a failed step/request?
    Sometimes, it doesn't help to just set a request to green status in order to run the process chain from that step on to the end.
    You need to set the failed request/step to green in the database as well as you need to raise the event that will force the process chain to run to the end from the next request/step on.
    Therefore you need to open the messages of a failed step by right clicking on it and selecting 'display messages'.
    In the opened popup click on the tab 'Chain'.
    In a parallel session goto transaction se16 for table rspcprocesslog and display the entries with the following selections:
    1. copy the variant from the popup to the variante of table rspcprocesslog
    2. copy the instance from the popup to the instance of table rspcprocesslog
    3. copy the start date from the popup to the batchdate of table rspcprocesslog
    Press F8 to display the entries of table rspcprocesslog.
    Now open another session and goto transaction se37. Enter RSPC_PROCESS_FINISH as the name of the function module and run the fm in test mode.
    Now copy the entries of table rspcprocesslog to the input parameters of the function module like described as follows:
    1. rspcprocesslog-log_id -> i_logid
    2. rspcprocesslog-type -> i_type
    3. rspcprocesslog-variante -> i_variant
    4. rspcprocesslog-instance -> i_instance
    5. enter 'G' for parameter i_state (sets the status to green).
    Now press F8 to run the fm.
    Now the actual process will be set to green and the following process in the chain will be started and the chain can run to the end.
    Of course you can also set the state of a specific step in the chain to any other possible value like 'R' = ended with errors, 'F' = finished, 'X' = cancelled ....
    Check out the value help on field rspcprocesslog-state in transaction se16 for the possible values.
    Thanks,
    JituK

  • Jobs in a Process Chain

    Hi All,
    I have a scenario where 5 jobs needs to be executed one after the other in a PC.
    3 are getting executed correctly. 4th job is failing and due to this PC is shows failed status.
    If i restart the Process chain. I dont want the first 3 jobs to execute again. It should start with 4th job .
    Do i need to goto SM37 and cancell the first 3 jobs after scheduling the PC or is it something to do with Proces type maintenece?
    Regards
    Satish

    Hi,
    Iam wondering why you wnat to start the process chain all over again. If your first 3 steps have run successfully, and your 4th step faield for some reason, you can just fix the issue and then continure the process chain from there as provided by the above link.
    If that is what you want and all the processes are IP's then you need to create a IP group and then re reun  the IP group by de selecting the first 3 IP's to run the 4th onwards.
    Regards,
    Srini

Maybe you are looking for

  • How to connect my sony blue ray play to wifi via my airport utility?

    how to connect my sony blue ray play to wifi via my airport utility?

  • Open Sales Order Balance incorret

    Dear All, When you copy a Sales Order to an AR-Invoice and then increase the line quantity on the AR Invoice, the Open Sales Order Balance on the Business Partner Master Data shows a negative amount. E.G. Sales Order 10 Chairs @ R1000 = 10000 (Open S

  • How do I remove the HP rewards virus from my system?

    all this does is pop up when you are trying to do something important like plot my days delivery route in streets and trips, when you try to close it it crashes my pc, if i accept it says my pc is not connected to the internet then crashes my system,

  • New to J2ME, dont know how to read files on phone mem

    i check all the .io packages, still cant find any class that would help me to read files on phone memory. and i see that javax.microedition.media.Manager.createPlayer(String locator), require a string input argu. how can i make this string locator po

  • Getting started with 8i Lite Trial

    I have a copy of 8i Lite that I downloaded from the Oracle site and I have a few questions that I have not been able to answer in the documentation. I want to use this in conjunction with Codewarrior on a Palm platformave a Symbol 1740 Palm-based sca