Result Recording for inprocess lot

Hello SAP gurus.
For in process inspection lot i have 3 operation for testing my requirment is if i goning for result recording for second operation without result recording for first operation system should restrict me. we are using 100 inspection point for inprocess inspection please suggest how can we do this?
Regards.

Dear,
Goto OPK4 -Select order type /Plant - Select 'Generally valid setting' for 'Operation sequence-Select 'Error when operation sequnce is not adhered  and also QM Error message if no inspection result exists.
Or you can use the exit CONFPP05 PP order conf.: Customer specific enhancements when saving .
Regards,
R.Brahmankar

Similar Messages

  • CRTD CHCR SPRQ-how to do result recording for that lot.

    Hi All,
    i am having issue.
    i did  GRN,lot is created with this status-CRTD CHCR SPRQ
    i tried for Result recording but  error is showing.
    Then came to know QP01 is not assigned for that material.
    then i created the QP01,but still i am not able to to Result Recording to that Lot.
    is any way to do that.without cancell the lot can we do.
    Regards,
    siddharth shanker

    Hi,
    Your lot is at created status so you need to relesed lot. May be insection plan /task list has not been assigned to lot.
    In Qa32 go in inspection lot Change ( Or T code -QA02 ) .where in tab Inspection specification tab click on task list/speci where you can assign plan theri ( You can assign plan with usage that you have created plan  )
    Save transaction.
    refresh QA32 then try result.
    Regards
    SANIL
    See QP02 with what usage you have cretaed plan.
    as earlier I told you in QA02 tasl inspec tab  in usage field select same usage by which you have created inspection plan.in QP01.
    Regars
    SANIL
    Edited by: Sanil Vadke on Mar 29, 2010 8:40 AM

  • Goup result recording for inspection lots

    Dear All,
    Is there an option of recording results simultaneously for a number of inspection lots????
    Please help out....
    Regards ,
    rishabh

    Dear!!
    Please Check QE51n with Plant as selection And unchecke With out usage decision below and execute ull get all the Inspection Lots
    with regards
    Pushpalas

  • Result recording for 10th lot for specific MIC

    Hello SAP Gurus,
    Our requirment is we want to record result for one MIC for every 10th lot E.g 10th 20th 30th lot etc like this how can we do this?
    Please suggest.
    Regards,

    Hi
    Create DMR in QDR1, for usage decison. Make two stages, like stage 10 normal inspection and stage 20 skip. Mark stage one as initial and 20 as skip.
    For stahge change of 10: No. of inspection lot 1, and new inspection change 20. For stage change of 20: no of lots 9 and new stage 10. For both stages 10 and 20, rejection will b 1 and new stage for that will be 10.
    In inspection plan header data, there is a section for DMR level. Select DMR at characteristic level there.
    So when you create lot: 1st lot will be be inspected, next 9 lots will be skipped. 11th will be inspected, next 9 lots will be skipped,...
    Hope you will be able to do this, otherwise please revert back.

  • Three Physical Samples withdraw from inspection lot 04  and then result record for all three

    Dear Gurus,
    We have 3 quality labs and each lab is sent a separate samples to inspect certain characteristics once we receive material from production. I have created an inspection plan and mapped these three labs as  work center in operation and then assigned MICs under each operation to inspect.
    Now my issue is how to map separate 3 samples to inspection lot generated from production  ( type-4) and also how to configure that to inspection plan.
    I have to result record for all these three physical sample as withdrawn from Lot based upon inspection plan as mentioned above.
    I can mention sample drawing procedure in inspection plan but how to map actual sample there.
    Any help will be greatly appreciated.
    Regards,
    Satish

    Hi Satish
    You are creating three operation for depicting three testing Labs.
    Against each lab (operation) you had assigned MICs as per your requirement.
    Now you have to assign a SDP along with inspection point type 200 for physical sample in task list.
    After prod confirmation system will create inspection lot along with a sample by default for 1st operation.
    For other operations you have to create samples manually referring the same inspection lot (QPR6).Remember to click ' Create Insp points' and mention operation.
    Release the samples in QPR4.
    Now when you go for result recording system would ask first for operation, so select the operation , then system will ask for insp point (sample no).There click on assign insp point , so system will provide the Sample no which were created in QPR6 for that particular operation.
    Please follow the steps and revert.
    Regards
    D Mohanty

  • Multiple results recording for Delivery inspection lot

    Hi Gurus,
    My requirement is to configure for quality results recording for sales delivery document. Where client wants to record Customer, supplier, Umpire, etc results record for inspection characteristics.
    I got response from few Sapiens that I should use Inspection point concept for multiple results recording. Could anyone cna tell me how can I do this.
    Your help will be highly appreciated.
    Thanks,
    Kumar

    Hi Kumar,
    Okay!
    First of all letu2019s try to understand whether inspection points are really suitable for your requirement or not. Accordingly further errors can be eliminated. I just try to understand.
    A- Using Inspection Points
    1.     Inspection points are used when you inspect the same parameters again and again.
    2.     When you click on results tab in QA32, system asks you put some identification number. Letu2019s say you put A1 and then press enter. Thereafter you record the actual results (LENGTH, WIDTH etc.) You save this without giving UD.
    3.     For the next time when you again click on results for the same inspection lot, system again asks you to put identification number. This time suppose you put A2. Then again you record the results (LENGTH, WIDTH) for A2.
    4.     Likewise you can retrieve the inspection results from system with respect to inspection point (identification point).
    5.     Typically this can be used for chemical industries where you record the temperature of the same chemical after every ½ an hour. Here 10:00 am, 10:30 am can be used as identifications numbers. As a result of which you can get the information that at 10:00 am temperature was 40 Deg and at 10:30 am it was 75 degree Celsius.
    If your requirement resembles this situation, then only the use of inspection points would be fruitful.
    B- Without Inspection Points
    But if you want to record the readings by various agencies like customer, umpire (refer following pattern)and want to compare them there are other ways.
    1.     Reading by your inspector
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    2.     Reading by customer
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    3.     Reading by umpire
    a.     LENGTH u2013 100, 101, 102mm (average is 101mm)
    b.     WIDTH     - 10.50, 10.50, 10.60mm (average is 31.6mm)
    You can achieve this without using inspection points also. For this in QP02 you need to create 3 operation; Inspector, Customer and umpire respectively. Feed the MICs in each of these operations. When you click on result tab system will throw pop up for these 3 operations. Double click on Umpire if you want to record results noted by umpire. Likewise for rest of the operations. You can do this even after UD also (after 1-2 months also). You need to use MIC with control indicator as long term characteristics for this in QS23.
    Regarding averaging of results u2013 This can be achieved using single result recording MIC with or without inspection points. Use appropriate sampling procedure. When you feed results in QA32 system automaticaaly averages out the reading. This can be viewable against phi symbol.
    Finally you did mention that u201Chere I am not getting the newly created inspection lotsu201D. Does that mean inspection lot (10 origin) has not created?
    Regards,
    Anand Rao

  • Result recording for quantitative inspection characteristic

    Team
    Greetings!
    Please find the following requirement.
    We are using quantitative characteristics inspection.
    Inspection lots are created automatically and the sample size for each characteristics are determined based on the sampling proceedure.
    when we do result recording for a characteristic, say the sample size is 5, even if any one of the sample does not fall under the limit, we need the characteristic to be rejected.
    How can this be addressed.
    Gobinathan G

    .

  • Report of result recording for multiple batches in a given time span .

    Dear team ,
    I am looking for a standard SAP report that gives the details of result recording with all the characteristics for mulitple batches in a given span of time . The MICs will show the actual values recorded for each of the batches.
    The colums may be like this
    material/batche/lot/quanity/mic1 value/mic2 value/mic 3 value...........
    A standard report is prefered and we would also like to have a trend analysis done for the batches .
    Looking forward to hearing from you .
    Ram

    Thanks for the answer Firefighter.... cheked the t code and seems to be useful . But I would like to have the report in the folowing format . Kindly guide.
    SN     MATERIAL     BATCH     INSPECTION LOT      QUANTITY     CHARACTERISTIC 1     CHARACTERISTIC 2     3     4
    Ram

  • Error while result recording for test equipment

    Dear Gurus
    My scenario is to do unplanned maintenance for test equipment and recording the result.
    For that I have done the following steps
    1)     Created Notification for the test equipment (customized notification type TE).
    2)     For that notification I created order.  (customized order type TE01).
    3)     Attached General maintenance task list for that order. Task list has inspection point 300.
    4)     Released the order and saved.  Inspection Lot is created.
    5)     In QE51N / QA32 when I tried to do results recording, it shows the following error.
    "Equipment VERN01 do not exist in the object list for order 4001214"
    Please help me to correct this error.
    Regards
    Babu R

    Hi
    I applied oss and today I got reply. When 1278254 notes is implemented it is solved. 
    I have one more question, now in QE51N, I did result recording and when saved it is asking for order confirmation, I have given all data and came back to the same screen.  There is one more option for Valuate Inspection Point.  In that I have selected Can be used option and saved. Now if I goto maintenance order and TECO the order, it is saying that A usage decision has stll to be made. 
    Whether I want to take UD once again in QA32 ?
    Also is there any settings to TECO the notification automatically when the maintenance order is TECO'ed. Now the notification is not TECO'ed when order is TECO'ed.
    Babu R

  • Automatic Results Recording for Inspection Plan

    I'm trying to activate automatic results recording, at the beginning I get this meassage: "In customizing for default value of inspection type(400) you have to activate the following check boxes, " check characteristics", "Inspection with task list" & "Automatic assignment", I've done that. Yet, it sill doesn't work and the lot status is "CRTD" however it should be updated to "REL" status.

    Hi,
    Did you search enough before posting this query? There is plenty of discussions over this matter.
    Based on the details given above, I don't think you have created an inspection plan.
    Automatic assignment will assign the task list automatically to the inspection lot once it is created. You didn't mention if you have created one or not. Pl check that.
    If the inspection plan is created, there could be possibility that material is assigned to more than one task list (inspection plan). If that is the case, you wouldn't get inspection lots with REL status but CRTD only.
    ntn

  • Result Recording for In Process Inspection

    At the time of taking Usage Decision for In Process Inspection, system gives warning message if Results have not been recorded. Can this Warning message be changed to Error message so that user could not able to take UD without recording the results.
    Thanks in advance
    Srini

    Dear Srini
    1)Use status profile for restricting the user to do UD without doing RR. use this link for doing it
    Link: [https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20fbc091-ea3a-2b10-f0a3-877ffbf36436]
    2) you can use this auth object for doing the same restriction - Q_INSP_FIN
    Link: [Re: Preventing UD without results recording]
    Regards
    Gajesh

  • Result recording  for calibration

    Hi
           In the result recording , actual reading say 179.5 and set reading as 180 , the system valuate it as rejection means system
    round off  and valuation accepted . But it should be rejected.
    with regards
    Gaurav

    Hi
    In the Quantitative data please enter The decimal places atleat 2.
    It seems that you have entered any thing so system will consider it as "0" decimal places hence rounding off takes place.
    I hope this will add some value
    Regards
    Sujit

  • Multiple result recording for Manual inspection Lot using inspection point

    I want to record inspection result for inspection type 89 against *inspection point*. Then I create new inspection point and assign it in quality plan. Then I have done the multiple result recoding against one manual inspection lot in DEV server. But when it is going to QAS server then error is coming during result recoding. Error is "The results transaction cannot be used for
    inspection" Message no. QE094.
    Plz give me the solution to record the result.

    Reason is very simple : the  the inspection point definition in the task list header is incompatible with the sampling procedure assigned to the characteristic.Make sure that you select the appropriete radio button in QDV1 while creating sampling procedure and assign the same against each of the MIC's in the task list.
    Make sure that the sample tab in QA02 is pressed while assigning the inspection specification & status of the lot is REL

  • Result recording

    Hi all,
    Once Usage decision is done , the inspection lot is closed.Then i want to see result recorded for that lot,How to see the Result?
    Thanks,
    Sid

    hi,
    You may also use QGA2, for hierarchial Result display against the lots.
    Regards

  • Result Recording without release of physical sample

    Hi,
        SAP Gurus,
        I have one query regarding result recording for some lots.
       I have created one sample drawing procedure and assigned to inspection plan.
       In SDP I have maintained primary size factor 1, Fixed number 1, Acc.to smplng scheme-PM, Insp. severity-4.
       In pooled sample  size factor 1, Fixed number 1.
      At header level Consider No. of Containers Tick, Confirmation Required Tick, Used in Task List Tick.
    I have done One GR for raw material and assigned that inspection plan to the created 01 origin 01through QA02.
    One primary and pooled sample is created in CRTD status. I have not release the sample.
    When I go to QE11 for result recording system assigns the physical sample by default and branch me direatly to the result recording screen.
    My query is that, i have acivated confirmation required tick in SDP then system should not accept the sample which is in created status and should not allow me to do result recording. But system is skiping this and allowing me to do Result recording.
    Please let me know what necessary settings i have forgot.
    Thanks in advance,
    Harriesh

    Dear Shyamal,
                   The scenario i mapped is that, I need to release the sample manually. User should not go for RR without sample release.
    It is working fine also. But for few lots it is not asking the sample release. It ir skiping the sample status stage and directly going to RR.
    Please let me know way system is behaveing like this for few lots only.
    Thanks and regards.
    Harriesh.

Maybe you are looking for