Hello Gurus,
We are in SCM 4.0 and currently we are facing an issue in safety stock calculation.
We run a macro to calculate the safety stock. The safety stock for a particular bucket is calculated by the sum of total demand of next consecutive 4 buckets. The problem is that the macro works fine if we select a single product-location combination but when we select a product at multiple locations combination (aggregated level) the macro doesnt work. The value is not displayed in the planning book. However, we could see the total demand value for that particular bucket.
Hope I am clear and please help me on this.
Thanks,
Sai

Hello all,
I have a quick question:
Do we need to maintain the data at Location-Product Group level to go for Aggregated Safety Stock Planning?
Let me explain my case:
We have the following selections at Location-Product level:
Sel1: Prod1 at Loc1
Sel2: Prod1 at Loc2
Sel3: Prod1 at Loc3
When I make either of these selections individully in the Planning book the safety stock macro works fine but if I make any of these two selections or all the three selections at a time, then the values does not show up at the Total but I can see the values at 'Details' level if I select Location at the Header Information.
We are thinking of Aggregated Safety Stock Planning and We do not mainatain the data at Group level. Can we still go for Aggregated Safety Stock Planning?
Could anyone give me some suggestions on this?
Thanks
Sai

Similar Messages

  • Approval for issueing safety stock

    Dear Experts,
    I have one requirement...
    I need a control / approval... while issuing the material from Saftey stock level..
    I 'll explain in detail.. If i mentioned a mtl A with safety stock 10.... till the time it reaches 10.. it needs to allow the issue...
    Once it reached the limit of 10..(stock).. then it needs to restrict the issuing process.. And the issue can be further performed only after approval...
    Please explain the possibility and how to configure for this in SAP.
    Thanks and regards..

    Hi,
    In OPJJ, you can control the availability check of safety stock for the combination of Availability check and Checking rule.
    But for the consumption and issue you have to manually do goods issue.

  • Issue with -ve safety stock not allowing items of smaller demand to be isue

    We have a material with  a safety stock value of 300 with only 119 available in inventory.  Looking at MD04 the available qty immediately goes negative (-181). We have requirement of 30 but was prevented by the system from ussing the material - no iventory available message.  The workaround, which is not acceptable, was to reduice the safety stock to zero, create the delivery and then re-instate the safety stock level back to 300.
    So the issue is that  material could not be issued to PrdOrds.  Is there a possibilty that we have some missing config / master data settings that are preventing the issuing of material when safety stock is factored in and available quantity is less than zero?

    From planning perspective, there are two options available for your scenario.
    You may try if the dynamic safety stock works for you. You may have to configure the minimum, maximum  and target stock levels. The system calculates the average daily requirements of the material and determines the proposals.
    If your business process demands only static ss, you can configure the % share of ss that can be used for smaller requirements. Check the config node Production >> MRP >> Planning >> MRP calculation >> Stocks >> Define SS availability. This way the smaller requirements would be considered for use from SS by planning. You will have to define the % share of SS that can be used by planning based on MRP groups.
    Edited by: Arun.CBE on Feb 17, 2012 9:25 AM

  • Whether it is possible to make auto goods issue below safety stock level

    Hi SAP Gurus,
    I am implementing MRP for generating stock transfer Planned orders from a Main Mother Plant to different Plants. We have defined a Safety stock level for materials at main Plant level.
    There is a auto program available for generating auto goods issue against Purchase orders.
    System picks up Qty as long as unrestricted stock exists for the material during auto goods issue.
    System dont pick up any Qty below safety stock level (manual goods issue works below safety stock level).
    We are defining safety stock to meet sudden requirements and have time for new procurement.
    But it should allow us to do auto goods issue below safety stock level.
    Whether this is possible and what need to be done ?
    Thanks and Regards,
    R.Velmurugan.

    Hi Velmurugan,
    I don't think auto GR is a problem from safety stock. Auto Gr can be done by two ways.
    1. Control key and assigning the control key in operation(Preferably in last operation)
    2. In production scheduling profile you can do it. You have to assign the production scheduling profile in material master work scheduling view.
    Regards,
    Krishnendu.

  • Approval hierarchy to issue Minimum safety stock

    Hi Guys,
    We have a requirement to have an automated approval hierarchy for issuing the inventory below a safety stock limit defined. How can we achieve that. I know that there is some option as "minimum safety stock" in SAP, but we need that a workfklow to be activated when the stock reaches to this level and only after approval it should be allowd to be issued. Is it possible to implement?

    Hi,
        There is no approval concept in this case. But you may check the below work around, Activate availability check for the material. Then you may maintain the message  M7181 as user specific and maintain it as error message for the users who are NOT supposed to issue the goods below the safety stock. Refer the thread: message to be make error for specific user id
       You may create a program to find the materials with stock equal to safety stock and send the result. You may schedule the job in background with specific interval.  Also refer the thread: Material alert workflow
    Regards,
    AKPT

  • Report on current stock and safety stock

    Hi,
    I want to have the report on current stock and safety stock.
    In MC.9 it gives wrong safety stock. When I go to cross check the safety stock in material master & in MC.9 I see differences.
    Thanks,
    Kiran

    You can user tcode MC.9 or MC.5 to know valuated stock available at given plant. Stock lying in Returns (MB52) will not be a part of this report as it non-valuated stock.
    The stock in the accounting view of the material master considers stock at plant level including stock in Transit (Intra & Inter plant stock trasnfers) & special stock like stock issued to vendor , consigment stock etc which is valuated at plant level.
    whereas and stock in the plant stock view of the material master does not consider such special stocks hence there will always difference in both veiws.
    For Physical stock as on particular date you can consider MB5B report with radio button "Storage location/Batch Stock" wherein you will get Quantity issued & Qunatity received in those SLOC along with Opening stock & Closing stock for the specified period.
    use tcode
    MBLB to know stock at vendor.
    MB54 - Consignment Stock.

  • Calculation of Safety Stock and Reorder Point under Forecast Model T

    Hi Gurus!
    Happy Holiday!
    I would like to ask for your assistance on how the the safety stock and reorder point was calculated with the following values available. I would really appreciate it if you could give me details on the calculation.
    Below are the values:
    Basic data
    Forecast date        01.12.2009        Unit                  CTN
    Forecast model       T                 Service level         0.0
    Period indicator     M                 Paramtr profile
    Control data
    Initialization                                Tracking limit        4.000
    Model selection      A                 Procedure selection   2
    Parameter optimizatio                Optimization level    F
    Alpha factor         0,10               Beta factor           0,10
    Gamma factor       0,00              Delta factor          0,30
    Basic value           5.464-           Trend value          5.603-
    MAD                      4.758            Error total              4.722
    Safety stock         1                   Reorder pnt.          1
    No. of values
    Consumption           6                Forecast periods       1
    Initial. periods      0                Fixed periods          0
    Periods per season   12
    Historical data
    Period                Original     Corrected value
    11.2009                3.000              3.000
    10.2009                0.000              0.000
    09.2009                0.000              0.000
    08.2009                9.000              9.000
    07.2009               21.000             21.000
    06.2009               20.300             20.300
    Forecast results
    Period                Original     Corrected value
    12.2009                0.000              0.000
    Appreciate your assistance!
    Thank you and Happy Holidays!
    Ji

    Sweth, you are asking for consulting, and in my opinion it is way beyond what can or should be reasonable to achieve in such a forum. You are asking complex questions, that most probable have more than one possible answer.
    I suggest that you get on-site help from a knowledgeable and experienced consultant. These are crucial business issues, and should be dealt seriously.

  • Delivery Against safety stock

    Hi All experts,
    In my REM buisness scenarion, I want to deliver the quantity from safety stock for sales order. I did setting for MRP group :- Share saety stock 100% and assigned this MRP group to finish product. But delivery takes place but picking quantity is not coming as per the sales order quantity. Thats why delivery is not taking place for sales order quantity.
    How to solve this issue? is there any setting in MM or SD side?
    Thanks in advance,
    Milind

    Hi,
    Please refer the below link,
    [link|Goods Issue Problem - Mvt Type 645;
    [link2|Error in post good issue??????;
    Hope sole your issue.
    Regards,
    R.brahmankar

  • Safety Stock (o reserved) to a Customer Cluster

    Hi Dudes...
    I have a need to define in our Stock Levels the next requirement:
    1. We have a 2 big Customer type or kind in the Company: Self Services (supermarkets) & Wholesalers
    2. In our inventory Model we are considering as follow:
         - Reorder Point
         - Safety Stock
    3. We need to get that when the stock level fall down the safety Stock, this remaining stock stay only to Self services customer and till the replenishment be triggered then, the stock could be again for the 2 kinds of customer.
    Is there any setting or customizing ti get this scenario?
    This is really important to the company, I'll appreciate your soon support.
    Please let me know if my question is clear.
    Thanks in advance
    O Perea

    Hi Dave,
    Try this note suggestion, possibly help you in resolving your issue.
    How to Avoid Getting Safety Stock Replenishment Too Early in an ASCP Plan [ID 301629.1]
    In order to line up the safety stock supply with the changes in safety stock, a combination of the profiles must be used:
    MSC: Use FIFO Pegging as yes
    and the plan option
    Peg Supplies by Demand Priority is checked.
    The profile MSC: Use FIFO Pegging as yes will perform the following:
    For all demands and supplies, it proceeds item by item and
    pegs supplies to demands on a daily basis. Daily supplies
    and demands are not sorted. When supplies or demands
    on a given date are used up, it picks from supplies or
    demands on the next date. The unpegged supplies are
    pegged to excess.
    The peg supplies by demand priority combined with the profile above will prevent the system to plan ahead for safety stock.
    Also no safety stock smoothing is setup.
    To implement the solution, please execute the following steps:
    1. Please set the profile:
    MSC: Use FIFO Pegging as yes and
    2. Under the plan settings in the main tab the set the following options:
    Enable Pegging ON
    Peg Supplies by Demand Priority ON
    Warm Regards
    Sivaraman.G

  • Static Vs Dynamic Safety stock

    Hello Gurus
    I want to know the following
    1. Whats a Dynamic Safety Stock ?
    2. The basic difference between  Static Vs Dynamic Safety Stock
    3.In which business scenario do we use a Dynamic & in which cases Static safety stock -

    Dear Raja,
    There are two types of availability checks
    1) Availability Check for stock types in Inventory Management (Static Availability Check):
    This check takes only the existing stock at the time of entry into account. This check is carried out automatically & no setting can be made for it in the system .It covers the relevant stock affected at the plant, storage location & special stocks level. The stock affected is determined via the movement type.
    Ex: If you enter transfer posting with mvt 321 for 20 nos from Quality to unrestricted the system checks whether 20 nos.are actually available in Quality stock
    2) Check of available stocks from the view point of MRP (Dynamic availability check):
    In this case in addition to stock physically available in warehouse, here planned receipt & issues can also be taken into account. This check enables you to prevent an already reserved quantity from being withdrawn or reserved for another purpose.
    For Ex; Today we have a stock of 100 nos. 25 pieces are reserved for withdrawal tomorrow & another 25 nos are reserved for day after tomorrow which means only 50 pieces are available today. If you try to create another reservation of 60 nos today system will give warning or error message.
    Hope this will clear your concept
    Vivek

  • SAP Retail: Material Master, tab Logistics: DC, Safety stock

    Hello,
    I need some help on the following: In the field Safety Stock (MARC-EISBE). It is possiblre to fill in this field without choosing a specific DC. Is it also posible to maintain this on a generic level (without giving the DC) and that this is copied to all the (relevant) DC's which are created for a specific material? At this moment it is not being copied to all the DCs.
    Thanks
    Oktay

    Hi Yannick,
    I am trying to do the exact same thing. Have you gotten any further on this issue?

  • Minimum safety stock

    Hi,
    I maintained minimum safety stock as-50 in MRP2 view while creating material master, my client requirement is this minimum safety stock should not be issued at any cost, without enhancement from abap consultant i need to maintain this safety stock.
    can anyone help me to cose this issue.

    Hi,
    Minimum Safety Stock
    The quantity that defines the lower limit for safety stock. This value cannot be exceeded.
    Use
    Defining a lower limit can influence the following:
    material master data maintenance
    The safety is checked to see if it is greater or equal to this lower limit.
    forecasting
    The lower limit is checked if you use an availability indicator which shows, according to customizing settings, if the safety stock is to be calculated again in a forecast.
    If the safety stock is lower than this level in forecasting, the safety stock is automatically increased to the value of the lower level.
    Dependencies
    The safety stock must always be greater or equal to this lower level.
    Hope this helps.
    Revert if you need more details.
    Regards,
    Tejas

  • Reg safety stock

    Hi experts,'
    I am maintaining safety stock in material master.
    I want the warning message at issue ,when the stock below safety stock.
    How to resolve the issue?
    Rgds
    Bhuvan

    What MRP type are you using? If stock falls below the safety stock, there will be a procuremet proposal for the same (internal or external) if you have mainted the MRP type as VB, then system will plan the same when MRP is run at plant level.
    So please check your MRP parameters & monitor the stock level in MD04.
    Hope the above clarifies.
    Regards,
    Vivek

  • A report on Safety stock

    We have mass updated the safety stock using the T code MP38. The same is getting reflected corectly in to MD04.
    We are looking for a report to provide the safety stock material wise per plant.
    We have tried MCBE which do no reflect the correct quntity. Any reason?
    Thanks in advance.
    Vasu

    Hello Vasu
    MCBE is for the analysis of Receipt and issue during the specified time frame.
    Try out the following reports -
    MB53
    MC.1
    I hope it helps.
    Regards
    Avinash

  • How to make MRP run based on Target Safety stock

    Dear Experts,
    For our MRP-planned materials with safety stock we would like MRP run to take into account  target stock level defined for each month.
    for example: we know the target stock level values will be for M1 = 1000, M2 = 0, M+3 = 5000 etc.
    MRP should then propose orders to replenish up to the target stock level at the end of each month:
    needs for current month = (target stock level defined for current month  minus safety stock)
    needs for M1 = (target stock level defined M1 minus safety stock)
    needs for M2 = (target stock level defined for M2 minus safety stock)
    etc
    Do you know if there is any simple way to achieve this?
    Thanks you!
    Elynn

    Dear Experts,
    in my company, we are facing exactly the same issue,  we would like the MRP to consider a target stock exaclty as described by Elynn.     To be more clear, if we could reproduce the TDSS like in SNP in MRP, we'll be happy !.
    We imagine already to manage the target stock level in APO DP and released into ECC6 as a different MRP element than Forecast.  this target stock should not be considered as forecast neither consumed by any sales order.   Only to force the MRP to generate planned orders to increase the final stock when needed.  This is only an idea, we have nothing tested yet.
    someone have an idea if there's a standard solution for make this ?  I mean, why this fonctionality exist in SNP but not in MRP?
    thanks for any help
    Celia

Maybe you are looking for

  • Why are Loops and Drum Kit greyed out on GarageBand 10?

    I've looked and researched every forum and help section on fixing this issue but to no avail, I see some people having success but they seem to have different situations. Unless I'm missing a step or something. Here is my situation: I have OSX Maveri

  • TS3989 how can i activate icloud photostream on 2 macbooks?

    I have 2 MBP's, and was wondering: how can i activate icloud photostream on both? it works fine with 1 MBP, 2 iphones and 1 ipad, but when i try to activate icloud in iphoto on my new mbp, it says i have to deactivate icloud on the 1st MBP.

  • Error while generating Rules in GRC5.3  RAR Component

    Hi While generating the rules in Foreground from the GRC 5.3 Risk Analysis & Remediation, we are getting the following error. Error in Rule Generation! Reason:ResourceException in method ConnectionFactoryImpl.getConnection(): com.sap.engine.services.

  • Got error when trying to generate Java proxy jar file for webservice

    Hi, I am having a warning message when trying to generate java proxy jar file on weblogic8.1 webservice test web app, the message is as follows: "Warning Failed to generate client proxy from WSDL definition for this service. Prescription Please verif

  • Console.app not updates in LOG DATABASE

    After a forced shutdown of the MacBook Pro, the console.app displays all logfiles and also LOG DATABASE QUERIES, but the content of the LOG DATABASE only date back to the fored shutdown point in time. Afterwards, system.log, etc are updated, but the