Sales order link to MRP run

Dear gurus,
I have one query regarding sales order link to MRP run.
I had created sales order by VA01 & also independent requirement in MD61.
Both are acknowledged in MRP run.I know the requirement in MD61 transferred for MRP run(MD02/MDBT/MD01).
But my question is how sales order requirement considered in MRP run i.e. link to MRP run.Is there any customization?
Pl.suggest the same...
Rg,
Tushar

Hi,
Strategy 11  :-
Sales Order creation - no impact.
BSF    Gross planned independent requirements 
KSL    Sale from stock without independent                                                                               
Requirement reduction
Goods Receipt - minus the quantity for the oldest planned independent in demand management. For e.g. if PIR is 100 and delivery 90, PIR becomes 10 (withdrawal 90).
Delivery - no impact as delivery is issue from sales order.
Hope clear to you.
Regards,
R.Brahmankar

Similar Messages

  • Sales order block for MRP run when the Customer payment terms is in Advance

    My client needs to block some sales order for MRP which customer payment term is advance. But it should be based on the customer payments terms (In case of Advance). After getting his advance amount, we would be release it and it also be consider for MRP.
    Option 1.Status profile  this concept is will controlled by sales document controls VOV8 not by customer's payment term Advance
    Option  2: In CMR sales area Billing Document tab  by using payment guarantee procedure and in VOV8 in billing tab Payment guaramtee procedure by using this setting , i am getting a pop up message" No Finanical document assigned" in sales order when u try to save. Now sales order is blocked for delivery but not MRP run.
    i am to ask the abaper to develop "here in the information box we will maintained required text say example u201C customeru2019s Payment term is in advance please check the reason for rejection number u201Csay ex: 13u201D: advance " after this is happen go to change mode of sales order put reason for rejecation" now MRP run will not generate the requirement for the sales order.
    for Undo these this flow :
    Va02 : remove the reason for rejection keep it in Blank
    VKM3 : release the sales order.
    Options 3: Development 
    Kindly suggest me the second options is only alternative for solving this issue but really i m not used specific feilds to solving this issue.

    Cleint is not using the field  in CMR Payment granatee , i gone for user-exit and closed this issue

  • Planned order creation with sale order assingment at the run time of MRP

    some material item not planed with sale order stock in MRP run time. all setting in material master are corrected as i knowing.having some mistake in setting other configuration.

    Planning strategy is Make to order individual collective as individual but still come as make to stock plan orders
    Incase of Header material- Plan order is creating in MTS
    Check the sale order procurement tab, Is The requiremnt type is relevant to your Stratergy?, if not chnage it to correct requiremnt type and rerun MRP again
    Incase of component material- Plan order is creating in MTS
    Check for the component material MRP 4 View, individual/Coll.req- as 1. If not set as 1 and rerun the MRP again

  • Sale order exclude from MRP

    one requirement from user
    He want to stop future sale order include into MRP
    For example sale order delivery date is 31.03.2012
    Based on the backward scheduling , planed oder created(lead time is 4 weeks) proerly for the component and Purchase order for raw material
    It leads to more inventory,as per the delivery date the sale order should include into MRP on January 2012
    My requirement is future sale order should exclude and it include as per the lead time
    now they are using NEUPL procesing key for MRP run
    they run the MRP run daily

    Hi,
    try with below option
    In sales order have field Schedule line category to set CN
    Schedule line category
    A classification that distinguishes between different kinds of schedule line. The category determines how the system processes the schedule line.
    Use
    The schedule line category determines, for example, whether the system passes on requirements to materials requirements planning (MRP).
    Regards,
    Sankaran

  • Type of planned order created by MRP run

    hello,
    I have one concern regarding planned order creation through MRP run..
    our MRP creates  automatically order type LA
    I wanted that for some materials,  the MRP creates  planned order type PR ( with account assignment Q ->  WBS element, coming from sales order)
    what is the customizing point to make this ?

    Hi,
    I think that this happens automically when the requirement is created in the WBS SEGMENT, AND cOLLECTIVE INDICATOR IS NOT SET TO 2

  • Incomplete Sales Order requirement to MRP

    How to stop transferring Blocked Sales Order requirement to MRP?
    We have scenario there we entered 100 line on orders, due to one or other reason we need to block the orders and do not want to transfer the requirement to MRP till the time the particular blocked removed manually.
    How to do this? There is suggestion to use VOFM - Routine for transfer requirement. But not sure as that is the solution.
    Thanks
    PP

    Hi,
    Define a new delivery block whee check the Confirmation and assign the block to the order. System will not pass the requirement to the MRP.
    Path: LE >>Shipping >> Deliveries >> Define reason for blocking.
    Thanks
    Sri.V

  • What happens sales order linked with wip job is cancelled

    HI,
    what happens sales order linked with wip job is cancelled ?
    actually if wip job is cancelled then sales order lines is on hold ?
    i wanted to know what if sales order of that wip job item line is cancelled say example  if that wip job already is in processing .
    please help me
    Thanks in Advance.

    If WIP job cancelled or Requisition/PO is cancelled, corresponding order line reservation will be cleared and will go to 'Supply Eligible' Status. Progressing this line will again follow the WIP/Requisition path based on item.

  • CIC Activity and Sales Order Link Tables?

    Hello Experts,
    Can somebody let me know the CRM Customer Interaction Center(CIC) activity and its leading Sales Order Link tables or the data model?
    If somebody could point me to CRM CIC Data model it would be real helpful.
    If you have any document please send it to [email protected]
    Thank you
    Arun

    Arun,
    You should be able to use the document flow function mod : 'CRM_DOC_FLOW_READ_OB' to get any leading documents
    CALL FUNCTION 'CRM_DOC_FLOW_READ_OB'
         EXPORTING
           IV_HEADER_GUID  = wa_activity_guid
         IMPORTING
           ET_DOC_FLOW_WRK = lt_doc_flow.

  • Email Sales order link from SAP Work Place

    Dear SAP Gurus,
    Well guys i have to mail the sales order link through the work place but its not working for the sales order. but its working for delivery order and billing document...so i want to know that why its not working?
    Regards,
    Mohsin

    Dear All,
    Can u please help me on this situation? I will be very thankful to u....
    Regards,
    Mohsin

  • Reduce Sales Order element from MRP using MIGO (Movement Types)

    Hi Folks,
    I was wondering if its possible to remove the Sales Order element from MRP through a movement type using transaction MIGO.
    Basically we don't want to use a delivery document to do this.
    Thanks in advance for your help.
    Regards,
    Gilberto Li

    to remove the Sales Order element from MRP through a movement type
    Sorry I am not sure whether I understood your requirement correctly.  You need to reduce the inventory by doing MIGO instead throgh PGI which means, the movement type will also differ.  Better if you can brief about your requirement, a suitable suggestion can be given.
    Incidentally, this is not the right forum to post.  You can post in the following forum
    [Forum: ERP - Sales and Distribution (SD) General |SAP ERP Sales and Distribution (SAP SD);
    thanks
    G. Lakshmipathi

  • Sales Order costing error to prevent Plan Order generation in MRP run

    Dear PP Experts,
    We are into sales order costing due to Variant Config implementation.
    Problem Statement: After sales order entry /Characterisitc value selection, while saving sales order , SO costing is auto triggered. Many a times one of the new Raw material price is not maintained( Purchase info record), hence SO costing occurs. SO costing is still saved, SO incompletion is not configured , so it is detected when Production order has 'No Target Cost'. This creates inconsistancy in FI postings.
    My questions
    - Can we set SO imcompletion for SO costing error( Standard Config?)
    - Is there a enhancement to prevent MRP from processing Sales order with incompletion log i.e. Prevent MRP from generating Plan Order.
    Best Regards,
    Jatin

    Hello Jatin
    You can use BAdI MD_CHANGE_MRP_DATA to make the sales order not relevant to MRP.
    Check the following document for an overview of the BAdIs available on MRP:
    BAdIs for MRP
    BR
    Caetano

  • Purchase order status in MRP run

    Hi Gurus,
    I have a doubt in MRP run.
    While doing the MRP run, can there be any open PO s or is it mandatory to close them.
    Can you also please suggest me on how to run the MRP.

    Hi,
    MRP Run
    Purpose
    The Material Requirements Planning (MRP) function enables you to plan material requirements for complex manufacturing processes. You use the MRP Wizard to create and run MRP scenarios. The MRP Wizard generates recommendations for the production and purchasing orders required to produce the final product on time and in the required quantity. You then use these recommendations to create production and purchase orders in the Order Recommendation Report.
    The order recommendation cannot be issued for requirements that happened in the past (before the present day). Since the purchasing or production process cannot be completed in time, the MRP does not mix the real past data with new recommendations for the same period.
    Prerequisites
    ●     You have defined the
    ○     Planning system
    ○     Procurement method
    ○     Order mutliple
    ○     Minimum order
    ○     Lead time
    See also: Item Master Data, Planning Data Tab.
    ●     You have set the time interval between orders. See also: Define Inventory Cycles.
    ●     You have defined the appropriate items as non-production bills of materials (if required). See  also: Item Master Data, General Tab.
    ●     You have defined default warehouses. See also: Define Warehouses.
    ●     You have defined forecasts. See also: Forecasts.
    ●     You have selected the Consume Forecast option to make the system exclude existing sales orders from the forecast. If this is not selected, the forecast considers existing sales orders as an additional requirement. See also: Sales Order.
    ●     You have set the planning definitions. If you chose Consume Forecast, you have defined the consumption method, days forward and days backward. See also: General Settings, Inventory Tab.
    Process Flow
           1.      Start the MRP Wizard.
           2.      Create a new MRP scenario or select an existing one. (See also: MRP Wizard: Select New or Existing Scenario.)
           3.      Define the parameters for your scenario, such as the planning horizon and item details.
    You also choose your display preferences. (See also: MRP Wizard: Scenario Details.)
           4.      Define the data sources for requirements that you want to include in your MRP scenario.
    For example, you define whether you want to consider the existing stock or the minimum stock level. You can also include a predefined forecast. (See also: MRP Wizard: Data Source.)
           5.      Save the scenario or run it.
    After you run the scenario, the system displays the MRP Results.
    If there are red figures in the result table, solve the problem and re-run the MRP.
           6.      Analyze the MRP results. You can display the final stock quantity before the MRP run or after it.
           7.      Save the recommendations and exit the MRP Wizard.
    Result
    After completing the MRP Wizard, you still need to create the purchase and production orders in accordance with the MRP recommendations. See also: Order Recommendation Report.
    Hope this will help.
    Reward Point if helpful
    Thanks,
    Raja

  • Sales order Link to Production order

    Hi
    Expert
    We dont have MRP and not MTO but it is MTS item categary maintain is NORM.
    In this i want to link the Sales order to Production Order.
    I tried Co08 but i got error like this sales order has no CO object
    Message no. CO323
    Is there is need to done customization in PP point of view or in CO point of viewplease tell me.
    Thanks & Regards
    Pert

    Not answered closing thread

  • WBS element , Production Order and Sales Order Link

    HI,
    I have to get the name of the customer mentioned in the sales order. In Sales order line item assignment WBS element has been assigned as this is a sales order for customer specific.
    Now I am doing MRP run against WBS element and getting the planned order.
    After that i am doing Conversion of planned order into production Order with transaction code MD04.
    In the production order, Assignment tab WBS element is showing.
    My query is that against the WBS element and that particular production order how can i trace sales order as well as the customer name.
    Note: The WBS element can be assigned to more than one sales Order line item.

    Asutosh Mahapatra,
    Since each production order is created for 1 unique Sale order number you should see the sale order number on the header screen in production order ( General data tab). Also customer number & name will appear there.
    Hope this helps. Else please come back.
    Thanks,
    Ram

  • How to exclude Sales Orders from a planning run

    Hi,
    I run MD02 and i discover that planned orders are being created as procurement proposals for sales orders and the planned independent requirement.
    I want planned order to be created only for the Planned independent requirements ONLY.
    Is there a way that sales orders can be excluded from the planning run?
    Thanks in advance for your suggestions.

    Dear,
    Check the requirement type of your sales order line item in VA02 procurement tab it should be Reqmt type of customer reqmt   KSL
    Also check the strategy assign in material master and MRP group OPPR and then check the setting of strategy 10 in OPPS there should be
    Customer Requirement planning
    Reqmt type of customer reqmt   KSL  Sale frm stck w/o ind.req.red.
    Requirements class  030  Sale from stock
    Allocation indicat.     No consumption with customer requirements
    No MRP   :-               1 Requirement not planned, but display.
    Please try and come back.
    Regards,
    R.Brahmankar