Scenario A - Change in a Production System

Hello friends,
  We are already live in production, but we did not define the correct scenario at the beggining of the project. There was simply no configuration for the integration scenario between CRM (4.0) and R/3 (4.7).
  Now we found we need to have the "Scenario A" activated.
  Do you think we are going to have any problems or issues if we change the scenario in a live production environemnt?
  I think the system's behaviour is like "Scenario X", so it will be changed to "Scenario A".
  Much thanks in advance!
Best regards,
Douglas Cezar

Hello Douglas,
This has to be taken care of well in advance, but if your rquirement is some thing like this you are going to have issues. creating Orders in CRM system as well as R/3 system and changes made to the orders in any of the systems have to be reflected in the other system.
Please refer notes 889051 and 888665 and see if this helps.
regards,
Muralidhar Prasad Chatna

Similar Messages

  • Change SID of Production System

    Hi guys,
    Does somebody know if SAP supports the change of the * Production SID *?
    Thanks for your help.
    Murat

    Just to add:
    Restrictions to renaming apply for the logical system (Tx BD54) name for your production client. In most cases the logical system contains the (then old) SID. Changing that is not supported in production environments.
    Markus

  • Customizing open in production system for tcode KOT2

    Hi gurus!
    I have a problems with tcode KOt2
    The problem is that the modifications are aviable also in production system, and you can change it in production system.
    How can i put it again just  with the seeing mode? I want to modify it just in test system.
    Thanks

    Hello Nereab
    Transaction KOT2/_OPA is a so-called 'current setting' in SOBJ, the settings in
    SCC4 do not influence this. This is the reason why the transaction can
    be called in 'change' mode in your system; the philosophy concerning
    this has changed since release 4.0B (where it was not a 'current
    setting').
    If you want to prevent changes for this transaction, you have to follow
    the information given in note 420909 accordingly.
    br, Guido

  • Hack release strategy customizing on production system?

    Hello Gurus,
    I have a problem - I made a mistake in release strategy customizing for purchase requisitions and now I need to repair it (the change is possible only on development system, but our development system is now under upgrade process and no development customizing is possible for one month).
    So I need change the release strategy customizing directly on production system. Please, is there some possibility (some hack or whatever) to change it on production system ?
    Thank you,
    Ondrej
    Edited by: Ondrej Hladek on Jul 11, 2008 2:37 PM
    Edited by: Ondrej Hladek on Jul 11, 2008 2:38 PM

    In SPRO Materials Management / Purchasing / Purchase Requisition / Release Procedure / Set Up Procedure Without Classification / Assign Release Indicators
    For one strategy there is entered 4th level, which is redundant. I need to edit line which sets in 3rd level blocked state (it should be set for Purchase Order) and then I need to delete the line in 4th level which mistakenly sets Purchase order (actually there shloud be no 4th level entered for this strategy).
    Edited by: Ondrej Hladek on Jul 11, 2008 3:01 PM
    Edited by: Ondrej Hladek on Jul 11, 2008 3:01 PM

  • Difference in the performance of Quality and Production system

    Hi All,
    We have a scenario wherein we refreshed the production system data into quality system 1 month ago.
    Few days back we noticed that when we are trying to fetch data from COMM_PRODUCT database table (in CRM Production system) based on the product description.....it was taking 2-3 mins.
    However, when we try the same in quality system, it takes only 10 secs. Any idea as to how there is such a difference when both the production and quality contain nearly same data (was refreshed only one month ago).
    Any thoughts on this?

    You should really search the forum before asking. Exactly the same question was asked and answered here two weeks ago: Performance of the program is very good in Quality but Very poor in Prod.
    Rob

  • Resolution required for an issue found in Coherence Command pattern in a production system

    We have a Trade and position processing system. Command pattern is used as it's core mechanism to distribute and execute these Trade and position commands acros the Coherence Cluster. So far the design pattern has worked very well for us.
    However, a scenario was encountered in our productions system, which disallowed to execute commands on a command node.
    Attached is a document which contains a complete detailed analysis of the cause. The end conclusion was that currently command pattern is not able to manage the context state correctly, when there are cluster failures.

    Hi Sandeep,
    If you've not done so already, please raise an issue in the issue tracking system for the project: https://java.net/projects/cohinc/
    Alternatively, raise a Coherence Service Request (SR) and it will be forwarded to us with the appropriate information.
    -- Brian
    Brian Oliver | Architect | Oracle Coherence

  • Change of decimal places in productive system

    Hello
    We are on ECC 6.0 in a post Go Live environment.
    In our productive system we have set the decimal places to 2. For our business requirements, we would like to maintain 3 decimal places to 3 for Logistics modules (SD / MM & PP) where as we would like to maintain 2 decimal places for Financials module.
    Pls advise us of the methodology of this changeover as well as the possible side effects as a result of this change.
    Thanks & Regards,

    Hello
    The number of decimal places saved on the database is determined by the Global Settings made in Customizing for that unit (unit of measure or currency unit). If no entry has been made in Customizing, the number of decimal places saved for this key figure and characteristic value is the number of decimal places shown in the planning table at the time of saving. If the key figure has no displayable unit (for example, if it is a percentage), all the decimal places are saved.
    However, you need to perform some testing of scenarios to really know the impact 2 different decimals. Definitely, there is one aspect, whether any conversion is required or is it just a display of values in decimals.
    Data from FI to other modules is not a issue, but data from other modules to FI should be able to take this extra decimal.
    Although personally in my opinion it is not going to cause any errors, please test the same.
    Check documentation on Key Figures
    Reg
    assign points if useful

  • ChaRM scenario for only one productive system

    Hi CHaRM-experts!
    I would like to know whether or not is it possible to use the Change Request Management scenarion for only one productive system?
    It means we have systems and cases where we should apply the emergency correction only in productive system, without any transport from DEV or QAS system.
    Does ChaRM support such case?
    Thank you very much!
    regards
    Thom

    Hi Don,
    thank you very much for your answer.
    No, I do not plan any transport in the productive system.
    I would just make any adminstrative changes without transport.
    Does ChaRM support such scenarios?
    Thank you!
    regards
    Thom

  • PD-ORG: changing user assignments in a productive system

    Hi,
    We get the following: in our productive system obviously it is prohibited to do any changes to customizing.  When in PPOME we change a user assignment to a position and try to save it, a message appears that the system is closed for changes. After cancelling this, the changes are saved correctly. This is very confusing to our maintenance guys.
    Can this message be avoided (only for user assignments)>

    with WFOBJ only tasks's agent assignment are out-of-transport
    using CORR, everything else is open.
    This is the setting that the SAP has programmed to solve this kind of requirement, having the agent assignment done in the production system, while maintaining the organizational model in another way (e.g. by ALE scenario).
    Before 4.6B, only CORR was available.

  • Not able to change the data of test data containers in production system

    Dear All,
    We have created eCATT scripts in Development SolMan System and moved the transports to Production SolMan System.  Customer wants to change the data at Test data containers and run the scripts in production system but we are not able to edit the data. 
    May be the reason is SCC4 transaction code has set the below option.
    Changes and transports for client-specific Objects
    u2022 No changes allowed
    Customer doesnu2019t want to change the above option and wanted to change the test data containers to give different datau2019s and run the eCATT scripts.
    Could you please let me know the solution for this?
    Your help is really appreciated.
    Thanks,
    Mahendra

    eCatt has the feature where you don't need to transport the scripts or test configuration to our target system. We can keep all our scripts and test data in Solman and run this script any other system in your landscape using the System data container and target system.
    Maintain the production as one of the target system in System container in Solman and point that system while running the script. Change the test data in Solman to run this script.
    Let me know if you need more information
    thanks
    Venkat

  • Support message and change requests only for production system

    Hi guys,
    I would like to connect the solman helpesk with CHARM ( CHARM is still running ).
    In CHARM I have to create a CR only for production system. ( don't know why - but works as designed).
    In SAP helpdesk I can create support messages for every kind of system type but if I want to connect both (HD and CR) , the source system (ibase component) of the issue will copied to the CR and runs in error because of the rule (only p-system) of CHARM.
    Of course I can change the ibase to production system manually in SDCR but it seems a very error-prone method.
    Now my question: is it possible to change the ibase component due to the creation of CR by copy rule or something like this?
    Kind regards
    Rayko

    Hi Rayko,
    We do not have this option.
    Once in ChaRM, we assume that the changes will always correct an issue in the PROD system.
    I would recommend to open the tickets directly with the PROD system IBase, once the issue is also happening there.
    Best Regards,
    Fernando

  • Logical System Change for Production System

    Hi experts
    We have new CRM and BI project.  Logical System name of our ERP production system is not in naming standart. So we want to change logical system name and run BDLS in production system.
    Is there any risk about this prosedure?
    Best Regards...

    Hi,
    It is not advisable to change the logical system in production client once its assigned.
    Regards,
    Nisit

  • Transaction Launcher: Logical System in Production System does not change

    Hi,
    I created a transaction launcher in the CRM development system (CRD) to launch the transaction IL02 in the ECC 6.0 system (ECD). Then I transported the changes from CRD to the CRM production system CRP. I also transported the changes from ECD to ECC production system ECP.
    However, when I see the transaction launcher in CRP system, it is still configured for the URL of ECD. I want the transaction launcher to connect to ECP. One option I have is to change the class name in the CRP system. However, I am not allowed to create a new ABAP class in the production system. Is there any other way to change the target system automatically in production system?
    Thanks,
    Rohan.

    Thanks Piyush. Could you be a bit more specific? I followed these steps:
    1. In transaction CRMS_IC_CROSS_SYS, created a logical system URL for production system
    2. In customizing setting Copy/Delete Launch Transactions, deleted the transaction launcher id.
    3. In customizing setting Configure Transaction Launcher, created the same transaction launcher id newly.
    I still am not able to change the logical system. However, I can do it if I change the class name.
    While deleting the transaction launcher id, should I be deleting all dependencies?
    Regards,
    Rohan.

  • TWO Changes In Production System

    Hi , there are two changes in Production system,
    one is there is a report i have to do some modification in PROD,for this have to do in DEV,QA,PROD Respectively , here whether i have to use old request to new one , is this is the right practice or not,
    second in  transfer rules there is a conversion routine , i have to do some modification , How can i do like once again DEV,QA,PROD
    Hope u understand the problem
    With Regards
    MAHI

    Hi,
    Normally we dont have any authorization for changing the objects directly in production.
    You need to make the required changes in Dev and then move to Quality and then to Production. Hence you need to create a new requrest for all the changes you made in Dev and move to Quality and then to Production.
    Hope this helps.
    Regards,
    K.Manikandan.

  • How to change the worklist in schedule manager in production system

    we are using schedule manager (SCMA) to arrange the daily process in SAP system. but we have to config the worklist and transport it to the production system every time cause in production system if we press edit worklist there would be a message called " TK430 The system administrator has set your logon client to the 'not modifiable' status.Client-specific objects can not be changed in this client."
    Is there any way that I can directly change the worklist in production system?
    Thanks.
    Jiajia

    Hi SUN,
    Take a look at 11g Grid Control: Steps for Migrating the 11g Grid Control Repository from One Database to Another [ID 1302281.1]. Step 4.7
    and
    http://gavinsoorma.com/2010/10/11g-grid-control-how-to-change-the-oms-repository-database-listener-port-or-hostname/
    ps Stop the OMS first.
    Eric