Sched. Collective Order

Experts,
if I have a collective order one parent order (A) and three child orders (B,C,D). At order start the order start dates and finish dates are alligned.
My question is, if I get a delay in child order B, should the parent order A automatically moved out if I reschedule the collective order due the later finish date of the child order ?
In our system the parent order won´t be rescheduled, are there settings to enable this ?
Thanks in advance
Jörg

I should think that a collective order is scheduled as an entire linked structure. If this does not happen in your system, you need to review customization settings for scheduling, and also routing definitions.

Similar Messages

  • COGI error generated while collective order confirmation

    hi ALL, this is the real  task for all PP GURUS.
    the issue is related with collective order confirmation.
    client is using customised program ZPP_CONF to confirm the collective order which is based on the sap spro program CORUPROC.this include automatic goods receipt,backflush & actual cost update .as user use zpp_conf for confirmation all this actions happened in backgruond.
    now after using ZPP_CONF . the confirmation is not happening .instead of that it is going in COGI where they are getting a error massage which is as follows
    "You have no authorization for this transaction with movement type 101u201D
    this error continues for 10-15 minutes after doing refresh it goes. & confirmation happens.
    this is not happening for all orders but for 8 out of 10.
    users have proper authorisations.
    they have enough stocks in st. locn.
    they are loosing lot of time becuse of this.
    HOW CAN I RECTIFY THIS ERROR GURUS?
    when i search i found this is written in the CORUPROC documentation
    Incl. incorrect goods movement: Not only preselected but also incorrect goods movements that are usually processed with transaction COGI are  selected and processed. 
    VENKADESH

    Hi,
    The Program CORUPROC only can adjust the Errors in Goods movements. It can not handle the Table Locks..
    The Program CORUAFWP, can taek care of table locks also, apart from the Errors in Goods Movements.
    Refer below thread for similar type of problem..
    COGI errors
    Hope this helps..
    Regards,
    Siva

  • Goods receipt in collective order

    Hi Experts,
                     In collective order situation, for the the child order, after confirmation the stock of SFG is not increasing automatically. Subsequently, after confirmation of parent order, in the material tab the SFG withdrawn quantity is showing up as zero. How to ensure that consumption of SFG occurs in the parent order ?
    regards

    SM,
    Please refer the below thread,
    Re: direct production
    In case of collective order scenario the goods movement of the child items are hypothetical, i.e. it is for document purpose.
    The stock doesn't get built up if you go for confirmation with auto GR.
    Rather as soon as you confirm the last operation or you go for the order confirmation the goods receipt on the child order & goods issue on the parent order happens simultaneously.
    Hope this helps you.
    SmanS

  • How to trigger creation of collective orders

    Hi,
    How to trigger the creation of Collective orders.
    regards

    Hi,
    Collective Orders
    Use
    In a collective order, planned orders or production orders are linked to one another over several production levels. Each order in the collective order has its own order number. If subassemblies are produced directly for superior orders within a production process, without physically entering the warehouse, it is useful to have a representation via collective orders.
    The components for which separate production orders are created in the collective order are called directly produced components (see Creating Collective Orders)
    Prerequisites
    A collective order cannot be created for components that have one of the following indicators set:
    · Co-product
    · By-product
    · Alternative item with strategy 2
    · Alternative item with usage probability 0
    · Discontinued
    · Follow-up material
    · Intra material
    Features
    Collective orders offer the following advantages:
    · Integrated view of a production process
    Collective orders make it possible to represent different levels of the production process together in the system. The production process can be viewed as an integrated whole.
    · Separate order number for every order
    Every level in a collective order represents a separate production order/planned order. Every production order/planned order has its own order number. This enables you to process the entire collective order, a subtree in the collective order or an individual order.
    · No placements in storage or removals from storage between production levels
    Within a collective order stock movements only take place for the leading order (that is, the order that is at the highest production level) and not for directly produced components. This makes it easier to maintain the collective order in comparison with several individual orders. A further advantage is a more realistic representation of the costs of the production process, since subordinate orders can be directly assigned and settled to superior orders.
    · Business functions simultaneously for several orders
    Certain business transactions can be carried out simultaneously for several orders. Releasing an order that belongs to a collective order has the effect that all the hierarchically subordinate orders are released simultaneously.
    · Automatic change to dependent orders
    Changes to an order automatically affect dependent orders / components affecting orders. For example, if you change the order quantity in an order then
    ¡ the relevant quantity changes are automatically made to dependent orders
    ¡ the requirements quantity of the directly produced component is automatically changed.
    In the collective order, you also have the option of manufacturing directly produced material in a different plant to the planning plant.
    · Set status in leading order
    If you make changes in subordinate orders that have an affect on the status, then the system sets the corresponding status in the order header of the leading order in the collective order as follows:
    u2013 CFCO Confirmation in collective order
    u2013 GMCO Goods movements in collective order
    u2013 RLNE Release taken place in network
    In this way you are informed about changes in the whole collective order.
    · Reading master data
    You can copy the routing data and BOM data to the order again. You can find more information in Read master data.
    Example
    You want to produce a pump. The BOM for the pump contains a pressure regulating valve and a spiral casing. You want to enter these two components in separate production orders, but you do not want them to be posted to stock.
    You set the special procurement type to direct production in the material master record for the pressure regulating valve and the spiral casing, so that production occurs using a collective order.
    When you create a production order for the pump, a collective order is automatically created, which contains subordinate production orders for the pressure regulating valve and the spiral casing.
    Creation of Collective Orders
    Use
    Collective orders are only created if the special procurement type is set to direct production in the components for which the separate production orders are to be created (materials planning area in the material master).
    In the standard system, 52 is the special procurement type for direct production (that is, for components that are produced within a collective order).
    To create a collective order, you must use an order type with internal number assignment.
    Hope this helps.
    Regards,
    Tejas

  • Collective orders header order basic finish date is not changing

    Hai all,
    I am working on collective orders. The header order has Basic finish date as 17.05.2011 . Now i have changed this date to 10.05.2011 and re scheduled the order . But again system changing the Basic finish date to 17.05.2011. how to solve this.
    In the outline dates also i have given finish date 10.05.2011 it is remaining the same but order Basic finish date is not changing and schedulded dates are also not changing. can anybody help.

    Hi gurus,
    In a collective order suppose the lead order is having three child orders.  Kindl
    If one of the child order is partially confirmed is the entire collective order can be rescheduled.
    If one of the child order is Fully confirmed is the entire collective order can be rescheduled
    Can any body help me out

  • Scheduling in collective order

    I need some hint on a problem I'm facing here...
    We are using collective orders(Proc. E- SP. 52) and no scheduling parameters are defined in our workcenters...
    When I create a production order on the top level (finish good) for 10/ 31, the component that has an In-house production time =1 scheduling margin key = 000 is scheduled to finish 11/03
    I tried using "backwards" scheduling, "backward in time" scheduling...
    I would like the component to have start date 10/30 and finish date 10/31
    Any ideas?
    If I remove the in-house production time, the finish date of the component is the same as the finish good...

    Luc,
    Check with Route time for the component. It is likely the route time is higher than 1 day. Production order schedules on route time & hence likely the order has a finish date of 11/3.
    If your only looking at the planned order planning then it will take the material master inhouse production time. Also please check if you have 31 Oct as a non working day in your factory calendar. If yes then it is likely 1 & 2 Nov( SAt/Sunday) are non working too & hence the order plans to finish on 11/3( monday).
    That also explains if you remove inhouse time, system takes 0 days & has finish date as 10/03.
    Hope this gives you with some hint about what might be going on in your system.
    Thanks,
    Ram

  • Different Order Types within a Collective Order

    Dear PP Gurus,
    I have a requirement for having different order types with in a collective order. For example, in a BOM of 3 levels, the order type for each assembly should be different say ZPP1, ZPP2 and ZPP3.
    For this, I have maintained separate production scheduling profiles in each of these assemblies with the respective order types. Also, I have maintained MRP groups separately for each of these materials. Further, in Plant Parameters, no default order type is assigned.
    However, when I create the order, the system creates all orders with order type ZPP1 which is for the header material.
    As per SAP help, this is possible but I am not able to create collective order with different order types.
    Please suggest any SAP Note or configuration changes which I have missed out.
    Thanks!
    With Regards,
    Nitin

    Dear Sabine,
    Thanks for your reply.
    However, as per SAP help, this is possible. Please refer to the link http://help.sap.com/saphelp_470/helpdata/en/ee/b6532cae8011d19e97080009b0db33/content.htm
    In this link, under Pre-reuisites section, in Point 2 it is mentioned
    "This indicator is transferred into the order header (master data) of the orders. If there are differing order types within the collective order, the setting of the indicator of the order type of the leading order takes precedence. This indicator is transferred to all lower-level orders and overrides their original indicators."
    The above line implies that different order types are possible with in a collective order.
    Please suggest some way out.
    Thanks!
    With Regards,
    Nitin

  • DOCUMENTED  GOODS MOVEMENT  FOR COLLECTIVE ORDER

    Hi Guru's
    In  the  4.6C version 
    If i got to Production order from transaction code CO03 , Read the collective order , highlight the toplevel item and ''GOTO'' in the menu bar and select Documented goods movement , the display shows the Top level order AND the Sub-Assemblies.
    ( sub-assemblies goods movement with main assembly  can be seen in the single screen)
    In the ECC 6.0 Version
    If i got to Production order from transaction code CO03 , Read the collective order , highlight the toplevel item and ''GOTO'' in the menu bar and select Documented goods movement , the display shows the Top level order only.
    To see the Goods Movement in the Sub-Assemblies  you have to go to each production order individually.
    can this be changed in ECC 6.0  exactly to that seen in 4.6c version .
    pls give me your valuable inputs at the earliest .
    Thanks for your help.
    Regards
    satish k

    Hi satish,
    In collective order struture ,Automatic goods movement will be happened between toplevel & lower level.
    Please check with "coll order goods mvt" settings for order type at OPJH For ECC 6.0 version.
    Please also check with cost analysis for Goods movement.
    Regards
    Pradeep

  • COOIS Capacity report for Collective Order

    Hello Expert,
    Need your help & assistance. I have an issue related to collective order, COOIS report display for list Capacity.
    For one collective order, when I check this COOIS>Capacity report it display only header order detail, not for dependent order.
    But for another collective order for same order type & Plant, it display for both header & dependent order.
    Please find the  attached word doc with screenshot for the steps I am following. Please point out the reason, that I can check so that for first order also it displays both header & dependent orders in the COOIS > Capacity list.

    Case:01: Wherin COOIS>Capacity list display only show for header order not dependent order
    Case 02:Wherin COOIS>Capacity list display show both for header order & dependent order
    Order type & Plant is same in both cases.
    For detail please check .xml attached
    Regards
    Piyush

  • Goods movement in collective order

    Hi all,
    We have ticked the indicator for 'Goods movement for collective order' in OPJH, still we are not getting required results. The goods receipt against the child order does not occur.
    Please help.
    SmanS

    Hi Dear Can u please explain..how you solved this..
    Regards
    Raghu

  • Collective Order deletion flag

    Hi All,
    I have a Collective production order which got deleted accidently. now all the orders under collective order have a delection flag activated and status as DLFL.
    Please tell me a way to revoke the deletion flag. I have tried the deletion functions under CO02 but they all are in grey field and can not be changed.
    The system shows a information that " the change is not allowed"
    Please help.
    Rgds,
    Rohit

    Hi ,
    The Change is not allowed is just a warning message , to revoke the DLFL press the enter button after this warning message and goto menu bar --> functions --> deletion flag --> undo
    If its a process order then menubar--> process order --> functions --> deletion flag --> delete
    and save

  • MRP for collective order

    Dear experts:
           I met a problem of Collective order.
           My scenario is :   Fert (A) -- Halb (a) -- ROH ( b) .  Set special procurment 52 in mrp2 of material a.
           suppose material "a" has stock 30pcs,  now when i creat a Plan order for "A" 100pcs,
           and then run MRP,system generate a plan order "a" 100pcs directly,
           not consider the stock of a (30pcs). 
            my question is how to setting, then i can get the result :  Plan order "a"  is 70pcs.
            And also how to setting when scenario is creating Production order.
            Thanks in advance.

    Dear R.Brahmankar:
          Fert A :        M0      Individual/coll.  "blank"
            Halb a:       M0  ,  special procurement:  52  , idual/coll.  "blank",     stock 30pcs
               ROH b:   PD.
      Now , I creat a Plan order for "A" :100pcs, and Run MD41,  
      result is:    material  "a",   plan order :  100 pcs.
      but what I expectation result is :   material  "a",   plan order :  70 pcs.  for I already have 30pcs stock  of material "a".
      how should i do. Thanks

  • Cancellation of collective order.

    Hi PP gurus,
    While cancelling collective orders, all the input materials for main and sub orders were returned back (with 262 movt.)
    and output on the main WO also cancelled (with 102 movt.)
    But the output material of the sub orders were not cancelled .for sub order material 102 movt type is not shoeing in document.
    In that case variance it will be huge as no input material will be consumed to get the output for the sub orders.
    Thanks

    Hi venugopal,
    Thanks for u r response.
    but it is not allowing to delete from sub order level.
    for that sub order item Special procurement Key 52 is there.
    how to do the process.
    the problem is  movement type 102 is not updating for sub order material.
    Thanks

  • Direct production in collective order network, automatic 261...

    hi all,
    i have a problem in a schenario with collective order network.
    i have order B part of collective order network of order A. and material of order B has special procurement key 52 maintained in it. and colletive order of goods movement is selected in order type setting of order B.
    now the problem is when i confirm the order B, its header material automatically gets issued to order A (as per the settings that is fine.. ).
    but when i canel \ reverse the order A, i can not see 262 for material of order B which was issued automatically....??? why so?
    and if i try to revrse order B,  it stucs in COGI with the error of deficit of sales order quantity (or unrestricted quantity)....
    can somebody tell me how to sollve this? how to get 262 of the header material of order B?
    best regards,
    Maulin
    Edited by: Maulin Munshi on Jun 17, 2009 8:27 AM

    If you're doing the confirmation of parent order (leading order) at header level (meaning you use CO15) then you can only confirm that particular order and not any child order. If you want the child orders to be confirmed also after completely confirming you'd have to change the control key of last operation of routing in leading material as milestone and use CO11 or CO11N and just confirm the last operation, it will automatically confirm all the operations in the leading order and all the sub orders (child orders). I don't think your OPKI setting will solve the issue.
    Production orders that belong to collective orders are generally confirmed like normal production orders. However, you should note the following:
        When you carry out a confirmation at header or suboperation level, you can only confirm the order concerned.
        When you confirm at operation level, you can confirm operations for all orders as long as you work with milestone operations or progress confirmations.
        When there is a confirmation in the collective order, the system sets the status CFCO (release occurred in network) at the header level of the leading order in the collective order.
    If you want to read more than what I mentioned, you go to this link

  • Collective orders settlement

    Dear Experts,
    Please advice how collective orders are settled.
    I have tested and fouind that both child and header orders are to be settled individually but is there any possibility that if Header order is settled all the child orders are automatically settled.
    Please explain the configuration steps to be folloewd to make auto settlement of child orders if parent order is settled.
    Regards,
    Krishna mohan

    Dear Krishna mohan
    their are 2 options to settle  collective orders, see question 4 in FAQ note 1574381.
    Normaly if you set indicator "Coll.order with Goods Movement" in customizing for order type the system should automatically generate the settlement rules for child orders settle to header order. Did you try this way?
    BR Sabine