Schedule Ship Date/ATP in OM.

Hi Champs,
would like to know how system calculates automatic schedule ship date for an order.
also pls let me know if ATP and schedule ship date are same.
Thanks.
-Arif.

Hi Arif
Schedule ship date is populated by ATP when you book or schedule the order. If the item is ATP enabled, ATP calculates the schedule ship date and populates on the order.
When ATP runs, it considers lot of modules like , purchasing supply, open order for demand etc. ATP calculation is complex calculation and can be dependent on lot of parameters like if you have Global Order Promising installed or not.
I hope you get the answer.
Regards
Yogesh

Similar Messages

  • Is there any method to stop rescheduling of the PO Need By date from ATP if there is any holiday specified in shipping calender. The requirement is to update the schedule ship date on Sales Order but the lead time of  Purchase Order should not increase

    We are currently not able to manage schedule ship date proposed by ATP when our warehouse is closed. For example , we would like that ATP doesn't propose any schedule ship date for the first of May , which is a non working day in France. The constraint is that we don't want our purchase need by date to be impacted by the process.
    I tried to closed one day in FR1 calendar and, after testing with order management, it appears that ATP didn't propose the closed day, so that's fine, but, our purchase order lead time was increased of 1 day and this is not what we expected.
    Can you help us to find the right process.
    Thanks

    Hi Sandeep,
    when we try to Rescheduled out the PO and the request is errored out the with the error:-
    Start of log messages from FND_FILE
    reschedule fails
    old date in planner workbench: 19-MAY-11
    new date: 07-JUN-11
    header: 417474
    line: 605652
    po number: 2049031859
    shipment no: 1
    The need by date/promised date in the source instance is not the same as the need by date/promised date in the destination instance.
    In the source instance,
    The need by date is 19-MAY-11, and the promised date is 19-MAY-11
    End of log messages from FND_FILE
    ---------------------------------------------------------------------------

  • How to stop scheduled ship date and scheduled arrival date from defaulting to sysdate

    Hello,
    We have a business scenario where we are deriving scheduled ship date and scheduled arrival date outside and then imported in the instance with the order. However we find that the scheduled ship date and scheduled arrival date are defaulting to sysdate. The atp flag is set to N for these items. I have checked the defaulting rules, there is no such defaulting rule set for scheduled ship date or arrival date ( screenshot attached) Please share your thoughts on how can I stop scheduled ship date and arrival date date from defaulting to sysdate ?
    Thanks
    Rajesh

    Hi
    Please visit following link. It may be useful.
    How to prevent auto default of schedule ship date in sales order form
    HTH
    sd

  • Scheduled ship date not taking PO need by date

    1. Please consider following case -
    a. Sales order is created for org UK for item A for 10000 qty 24-Mar-2011 with order request date as 29-Mar-2011.
    a1. There is no on-hand in UK for item A.
    a2. The item lead time for item A, as defined in UK org in item attributes’ Lead times tab, is as following -
    a21. Pre-processing time - 4 days
    a22. Processing time - 20 days
    a23. Post-Processing time - 1 day
    a3. A standard purchase order for item A is created for 15000 quantity on 25-Mar-2011 with Need by date as 10-Apr-2011.
    a4. The ATP rule that is attached to the item, is having Purchase orders checked, under supply sources.
    Observation : Before purchase order creation, the scheduled ship date on SO was 28-Apr-2011 (item lead time of 25 days).
    Then the PO is created as in point a3 and ASCP plan was run. The sales order line for item A is unscheduled and Rescheduled, the scheduled ship date becomes 25-Apr-2011.
    Questions :
    1.     Why did the scheduled ship date change to 25-Apr-2011?
    2.     What all things it is taking into consideration?
    3.     As per our understanding, the scheduled ship date should have been changed to PO Need by date. But this didn’t happen. Is our understanding flawed?

    Hi Sandeep,
    when we try to Rescheduled out the PO and the request is errored out the with the error:-
    Start of log messages from FND_FILE
    reschedule fails
    old date in planner workbench: 19-MAY-11
    new date: 07-JUN-11
    header: 417474
    line: 605652
    po number: 2049031859
    shipment no: 1
    The need by date/promised date in the source instance is not the same as the need by date/promised date in the destination instance.
    In the source instance,
    The need by date is 19-MAY-11, and the promised date is 19-MAY-11
    End of log messages from FND_FILE
    ---------------------------------------------------------------------------

  • Schedule ship date

    hi all;
    when i book a sales order; the schedule ship date is same as request date:
    where is this setup done?
    i dont have any scheduling activities.
    i dont have any defaulting rule for that.
    i dont have any ATP setup done:
    pl help;
    regards;
    prasad

    Hi,
    SSD will default to request date at the time of Order entry.Change the SSD manually while entering the Sale order and book the Sale order.
    Arumugam S.

  • Scheduled ship date using PO /  On-hand Quantity

    Hi All,
    ATP calculates the scheduled ship date using the pegging from PO or from the available On-Hand-Quantity when the order lines are created.
    I couldn't find any difference in the order tables whichever way the scheduled ship date is created.
    Any idea how to find based on what this date is calcualted from OM?
    Thanks
    Geetha

    Seeing sales order in OM you can identify whether schedule date is coming from onhand or purchase orde or lead time. But this information is not stored anywhere.
    You should check this sales order on planning workbench and pegging area should tell you the required info.
    So whatever you are asking is available on planning instance (MSC data).
    if you are not using ATP based on planning output then I don't think you will be able to get required information.
    thanks
    Vikrant

  • Use of Shipping calender while populating schedule ship date

    Hi Experts,
    I have done following setup in system in order to use shipping calender,
    a) Define an item, enable ATP. Now we are having ATP based on ASCP plan output.
    b) Define calender where Friday is only working day. This is our shipping calender.
    c) Assign shipping calender to customer, with its ship to site in order management.
    d) Enter SO line for this item. Enter req date - 02 Jul 12 (Thus-day), assume that item is having very less lead time so it will be complete prior to 02 Jul. But due to request date and shipping calender, schedule ship date should be 06 Jul 12, but it is showing as 02 Jul 12.
    So want to know reason behind it.
    Thanks in advance / Dipak

    Hi Arif,
    I am looking for further more help in this case..
    Suppose, we are dealing with two OUs - US ( ie for USA organization) and EU ( ie Europe organizations). Now US OU is sales operating unit, SO will be entered in US OU, having customer and ship-to-location belongs to US OU. Here only SO line warehouse is belongs to EU OU. Its typical sales OU and manufacturing OU scenario.
    Now in order to use shipping calender, we have mentioned default 'shipping method' and 'internal location' on customer ship-to-location. This is pre -requisite. Now this customer ship-to-location is belongs to US OU and EU OU is not allowed to enter any value against it. But as EU OU is dealing with shipping, then want to 'ship' material on specific days. So in given scenario, is there any alternative way to achieve the same ? Is there any work around to use shipping calender ?
    Thanks,
    Dipak

  • How the Schedule ship date will get affected

    Hi Team,
    Q) How is the schedule ship date populated? Is this based on the Planning engine?
    Q) For some of the transactions realted to the OM will get stuck in RA_INTERFACE_LINES_ALL with the error "GL period is closed" without the invoice getting generated. ( I know by updating the GL_DATE TO SYSDATE (Open Period). the invoice can be generated.
    I want to know Based on which date the transaction get stuck in the INTERFACE (RA_INTERFACE_LINES_ALL).
    Thanks,
    Raghav.

    Q) How is the schedule ship date populated? Is this based on the Planning engine?
    The SSD is populated in a variety of ways.
    You can put it in manually.
    If not, you could run a program called Schedule Orders that will put the date in.
    If not, the order booking workflow could be putting that date in.
    If not, you could use ATP to arrive at the proper scheduled ship date.
    Please create a seperate thread for each question. It is easier to answer questoins that way.

  • Sales order schedule date is a (working) day before Scheduled ship date

    In MRP/MPS planning, the forecast consumption is occuring for all sales orders at a date (sales order schedule date) which is always a working day before the Scheduled Ship Date (SSD). What is the logic?
    Time fences are not used.
    E.g. Sales order is scheduled to ship (SSD) on 30th Nov, in forecast set > Forecast items > Consumptiion > Detail, the sales order schedule date is a day before SSD.

    Hi,
    This is a complex issue; best solution is by using APO/GATP.
    If not, then in ERP only, the second best is:
    1) Work with assembly processing in SO, meaning that a production/planned order is automatically created in the customer order during order creation.
    2) Then, after the order is created it is scheduled, and the delivery date proposal is based on that.
    3) Now you can check in the order that there are no capacity overloads, and all capacity required to produce on the proposed date is available. If yes, you're done. If not, it gets a bit complex, since you actualy need to switch to capacity planning, do capacity leveling and dispatch (PP), and the you get a new feasible schedule proposal based on that.
    APO/GATP could do all that automatically!
    Regards,
    Mario

  • Drop Ship SO Schedule Ship Date to Purchasing NeedBy Date

    Has anyone found a solution to resolve the fact that the Sch Ship Date defined on a sales order becomes the Need By Date on a Purchase Release document sent to a Supplier to fulfill a Drop Ship Order Line? This is confusing to the Supplier as the term NeedBy implies this is when the customer will need the product on site. If the supplier has the product there by the Need By Date transmitted from OM, then the product will arrive too early.
    Thoughts?...

    Let's assume the Customer Service person does not know whether the item is a drop ship item or not. The problem we have is that the Customer Service person normally uses the Scheduled Ship Date as the date Shipping must send out the product on product sourced internally. We are trying to keep things consistent for the end user.
    We hope to use the Scheduled Ship Date as the date the product must be shipped regardless of whether the product is sourced internally or externally. Again, this is to keep order entry consistent for the end user and they do not have to think differently when entering the sales order.
    Thanks for any feedback.

  • Is there a way on CONVERSION to create a sales order with a scheduled ship date in the past?

    Is there a way on CONVERSION to create a sales order with a scheduled ship date in the past?
    Customer wants to maintain the original scheduled ship date on converted ordered, but the scheduled dates is defaulting to sysdate for past due shipments on converted orders.

    Hi Friend,
    As of now there is no functionality to display SSD,RD,PD backdated, max it can be sys date, not lower then that.
    Regards
    Shyam
    Please see following Metalink Note ID for all in One solutions
    Oracle E-Business : All In One Metalink Note ID's
    If you are happy with the Document, please mark as Helpful by doing so this will provide assistance for other people looking for answers to their queries.

  • IC_TRAN_PND의 TRANSACTION DATE가 ORDER의 SCHEDULED SHIP DATE와 불일치시 처리방법

    제품: MFG_GMI
    작성날짜 : 2005-11-29
    IC_TRAN_PND의 TRANSACTION DATE가 ORDER의 SCHEDULED SHIP DATE와 불일치시 처리방법
    ====================================================================
    PURPOSE
    IC_TRAN_PND의 Transaction Date이 잘못되어, Order의 Scheduled Ship Date와 match되지 않는 경우의 해결방법을 기술하고자 함.
    Problem Description
    OMSO order lines에 대한 pending default transaction에서 transaction date가 Order Line의 scheduled ship date와 일치하지 않는다.
    이것은 MRP를 통해, 잘못된 날짜의 Plan 정보를 발생시킨다.
    Instance: 11.5.8 patchet J
    Workaround
    Order Header level에서 Request_date를 Order line level의 schedule ship date로 변경시킨다. 이는 IC_TRAN_PND의 trans_date에 반영된다.
    Solution Description
    This issue has been fixed in the files:
    GMIURSVB.pls version 115.133.115100.9
    GMIURSVS.pls version 115.35.115100.1
    To implement the solution, please execute the following steps:
    1. Please download and review the readme and pre-requisites
    for Patch 4560700
    2. Please apply Patch 4560700 in a test environment.
    3. Please confirm the following file versions:
    GMIURSVB.pls version 115.133.115100.9
    GMIURSVS.pls version 115.35.115100.1
    You can use the commands like the following:
    strings -a $GMI_TOP/filename |grep '$Header'
    4. Please retest the issue.
    Reference Documents
    Bug 4560700

  • Updating schedule ship date and arrival date in SO

    Hello all,
    I want to update the sales orderline based on supplier PO changes.
    Can anyone let me know if I can use process order API to update the schedule ship date and arrival date.I have created a seperate procedure inorder to achieve the same which will inturn call oe_order_pub.Process_Line.Now am getting the following error:
    SQL_PLSQL_ERROR: N, ROUTINE, MO_GLOBAL.VALIDATE_ORGID_PUB_API, N, ERRNO, -20001, N, REASON, ORA-20001
    Any pointers to this is highly appreciated.
    Regards,
    Sumi.

    Hi all,
    Can anyone let me know if I can use process order API to update the schedule ship date and arrival date.Because sometimes am getting the above mentioned error but now am unable to see any error message but the status is error.
    Regards,
    Sumi.

  • Order Line Schedule Ship Date

    Hi ,
    How is the schedule ship date in order line calculated?
    Currently its taking from Request date when i try to schedule it from tools .
    I tried to modify this through defaulting rules but it doesnt take effect.
    The requirement is :
    Schedule ship date=Request date +Transit Time
    How do i take the transit time from the ship method ?
    Thanks

    Why Cant the Schedule ship date be less than Request date in Order line when Request Type is Arrival?
    I followed the document 262124.1 which was mentioned in the document 251449.1.
    The setup is only partially working for me .
    For example the document mentions:
    Scenario :
    Ist Case(Works Fine)
    If Order Date Type - Ship, then we add the Transit Time to the Scheduled Ship Date to get the  Scheduled Arrival Date
    Request Date =23-Sep-2010
    Transit Time =3 days
    Request type in Customer ship to= Ship
    After booking:
    Schedule ship date=23-Sep-2010
    Schedule Arrival Date=26-Sep-2010
    2nd Case (Doesnt Work)
    If Order Date Type - Arrival, then we subtract Transit Time from the Scheduled Arrival Date to get the Scheduled Ship Date for the order line.
    Request Date =23-Sep-2010
    Transit Time =3 days
    Request type in Customer ship to= Arrival
    After booking:
    It should be
    Schedule ship date=20-Sep-2010
    Schedule Arrival Date=23-Sep-2010
    But i Get
    Schedule ship date=23-Sep-2010
    Schedule Arrival Date=26-Sep-2010
    Please advise .

  • How to pass scheduled ship date from istore

    we need to set request date as sysdate and instead of request date,we need to pass scheduled ship date from iStore.
    Is there is any solution for these requirement.

    Hello Rahuljith,
    The request date can be entered by the user in the iStore UI and the schedule ship date can be populated by -
      Using the OM Defaulting rules, set the profile option "ASO: OM Defaulting" to yes and setup the OM Defaulting rule for the Schedule Ship Date.
      Or setup Quoting User Hooks (Doc ID:373923.1) to populate the schedule_ship_date in OE_ORDER_LINES_ALL at place order ( ie use Submit_Quote_POST).
    Regards,
    Debbie

Maybe you are looking for

  • Application Not listed In Force Quit Applications Window

    I running an application that is not displaying in the Force Quit Applications window. When Adobe Lightroom 3 is running it is not listed. I have quit the application and relaunched it and it still is not appearing in the list of Applications that ar

  • Javax.resource.ResourceException

    Hi, I'm trying to import the class javax.resource.ResourceException in my program but when I compile the code I get the error "class javax.resource.ResourceException not found in import". What is the name of the jar file that contains this class and

  • Export time lapse for Premiere

    (I'm a switcher from Final Cut Pro to AE/PrPRo, normally I would assemble timelapses in QT 7 pro as Prores then import and edit/"pan" in FCP.) I have shot a bunch of timelapses as jpegs.  I gather that I want to assemble the image sequence in After E

  • Delete an OM infotype

    How to  delete an OM infotype clearly? For example, I created an OM Infotye 9190, But when i delete it using T-code PPCI, the HRI9190 structure stills to be there. Thanks for all your help. victor ying

  • Problem in viewing form in Internet explorer

    Hi I am new to Forms, can some one please help me in this issue. After building the form i started the OC4J Instance and then i ran the form. Now i got the default Internet explorer opened and it is not displaying the form. I got some HTML tags like