Scheduline lines in Scheduling agreement
Hello Gurus,
I have a setting in material master in MRP1 view MRP group as generate planned orders only.
But when i run MD02 for a specific material and select MRP control parameters as Delivery schedule as 3(schedule lines).
Will it create Schedule lines in Scheduling agreement when in sourcelist the MRP field is 2.
Please let me for any more information required.
Helpfull answers will be rewarded
regards
suresh
hi,
proceed as follows
1.for child components in material master views
MPR1 -
mrp type as PD
lot size as EX
MPR2 --- procurement type as F
special procurement type as 20
MPR3 --- strtergy group as 10
2. in source list for the item maintain schedule aggrement no , item no, MRP as 2 ( record relevant MRP schedule)
3.now run the MRP for parent item
4.check the schedule lines
regards
laxman
Similar Messages
-
Creating Schedule lines in Scheduling agreement using LSMW
Hi,
I want to upload multiple schedule lines in scheduling agreement using LSMW. I have done the recording and maintained multiple lines in input file. However during execution LSMW creates only one line and keeps on ovewritting the same line. Please let me know how can I create multiple schedule lines.
RegardsFirst you should search for existing standard LSMW migration objects that possibly cover your scenario. These normally take care of complex header / multiple items / multiple subitems relations.
With a recording you can only load flat structures. Sometimes a "create new lines" / "enter first line" / "save transaction" logic can be constructed to load multiple items to a header (or even subitems to an item?) with a recording, but this can be pretty awkward.
Thomas -
Schedule lines for schedule agreement
Hi,
I need get all schedule lines for schedule agreement (all schedule lines = all visible in tab analysis u2013 all lines for all forecast dlv. sched).
I check table VBEP and VBEH and I canu2019t find all items.
Could you help?
Thanks in advance,
EHi Manju,
For this you need to set creation indoactor for planning run in SPRO.
The path is spro-MM-CBP-Carry out overall maintenance of plant parameters-Click on maintain-give your plant-click on external procurement under planning run-here you can give your option for the schedule line creation.
Traction code is omi8. Hope this will help you.
Cheers
Ravi -
Redetermined the past due schedul lines in Scheduling agreement
Hi All,
We have an issue with past due schedule lines in scheduling agreement, the details are below.
Delivery date: 3rd Jan 2011 - Order qty is 100 no confirmtion. The system has proposed new date that is 19.01.2010 (System date) with full confirmation. The Scheduling agreement is not relevant for ATP check also. When we check with other plant scheduling agreement, it is not determining any new date, it is confirming on same date.
Different Document types used in two cases, but the config is same in both cases. Not sure why the system is determining to current date with full confirmation. Is there any config relevant to this.
Regards,
Lakshmikanthhi
schedule lines in scheduling agreements = correct & confirmed dates.
that means if you enter the date manually here system confirms that date as schedule line date.
compare those two plants and let me know if any difference is there in between.
check MMR RLT's MRP views
check Lead time in days - document types
check & confirm.
balajia -
Change Schedule line in Scheduling agreement by function.
I want to know that is enalbe to change schedule line in Scheduling agreement by function( 'BAPI' or Standard function).
I known that is possible by BDC.
But I have to change many records. So I want to know faster method.
Please let me know what function enbale that.
Thank you for your interest.Hi..
The Scheduling agreement is one which is created runing MRP not VA31.
I know that is two transaction data in SAP.
One is Sales Data other one is Purchasing Data.
This is second one.
Thank you your response. -
MRP To Generate SCHEDULE LINES for Scheduling Agreement
Hi
I have followed the below steps but still the Schedule lines is not generated for scheduling agreement.
1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)
2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)
3. Create Scheduling agreement using ME31L
4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2 (Necessary ?) ME01
During Run MRP for the material.the below details entered///
Processing key NETCH Net Change in Total Horizon
Create purchase req. 1 Purchase requisitions in opening period
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 1 Determination of Basic Dates for Planned
Run MDBT or MD02 but still doesn't create the schedule lines......Anything else missing.
MRP1:
MRP Procedure: PD
MRP Group: 0000 (External Procurement only)
Lot Size: EX (Lot For Lot)
MRP2:
Procurement Type: F
Sched Margin Key: 000
MRP3:
Avilablity chec: 02 (Individual requirement)
MRP: 4
NilRaj,
Source List a Mandatory for Scheduling Agreement, if you want to create automatic Scheduling line.
Plz use (2) in MRP RELEVENT tab in ME01 (Source List).
rest of the thing is ok, make sure a material master(MRP 2 VIEW) in that view you have to give a planed delivery days. it is must.
HOPE IT WILL WORK
Regards:
Poision -
How to get GR posting date for schedule line of scheduling agreement?
I had hard time to tie the GR date to schedule lines. I need this information to generate vendor performance report. However, the GR date is tied to scheduling agreement item level only. One item line can have multiple schedule lines. Is there a way to link the GR date to actual schedule line? Thanks in advance!
Hi,
There will be icon called PO history in the over view screen of SA.Select the item and press it.May be this will be some what useful to you.
Regards, -
Schedule lines on scheduling agreement by MRP
Hello,
we use MRP to generate delivery schedules on a purchasing scheduling agreement. The vendor of the material has a limited capacity but when the need of our customer is very big MRP generates schedule lines on one date (too many for the vendor too handle).
Is it possible to limit the amount of a schedule line per period (for example we allow to generate 100 tons per week, if the need is 500 tons it should be splitted into 5 schedule lines over 5 weeks).
Thank you for your help!!!!Hello,
the weekly lot size generates lots per week but this answers only a part of my problem.
example: vendor can produce 50 tons per week
need is 200 tons
with a weekly lot size and a maximum lot size of 50 the system proposes 4 schedule lines of 50 tons on the same week and this is not what I want. I want 1 schedule line of 50 ton on the week and the rest on the weeks in the future. -
To generate Schedule lines for scheduling Agreement when MRP is run.
Hi,
Please help advise on my following requirement:
When I run the MRP for 'Single Item - Multi level' (MD02) for a material, I want MRP to generate delivery schedule lines for that material in Scheduling agreement.
Please advise as to how i can go about with this.
Regards,
ManjuHi Manju,
For this you need to set creation indoactor for planning run in SPRO.
The path is spro-MM-CBP-Carry out overall maintenance of plant parameters-Click on maintain-give your plant-click on external procurement under planning run-here you can give your option for the schedule line creation.
Traction code is omi8. Hope this will help you.
Cheers
Ravi -
Text on schedule line of Scheduling Agreement
Dear All,
I want to maintain some text on each schedule line of JIT Delivery Schedule of Scheduling Agreement.
Also this text should flow in Delivery as well as in Billing Document.
How to maintain this text ?
Regards
SAGARSagar,
you can maintain text determination at item level so that it flows into delivery and billing documents
reward points if it helps -
BAPI for schedule lines (purchase scheduling agreement)
HI
Is there a BAPI available to create schedule lines in purchase scheduling agreements?
Is there any other way of creating schedule lines in purchase SAs via program?
Thanks in advance
SriramDear Sriram,
Please check BAPI_SAG_CREATE with SE37.
Regards,
w1n -
Schedule lines in Scheduling agreement
Dear Experts,
We are using Scheduling agreement for our subcontracting process.Meaning we issue the material which is getting converted as another material and do the GRN.
When I make a schedule line thro TXN ME38 with specific date and quantity system does'nt restrict me to enter the child material ie Input Material.
this will lead to the Wrong GRN ie without consuming the parent part system allows me to do the transaction
Can I have the suggestion to control this ?
Thanks in advanceDear ,
Thanks for the reply
In PO we have the check to assign the child part.Where as in Scheduling agreement / Schedule lines we don't have control right at the moment.Should we need to customise ? if So kindly tell us or do we need to use the user exit ? Please explain. -
Schedule lines of Schedule Agreement
Hi Friends
Can any one please provide me detailed defination of Schedule Lines of the Schedule Agreement.
Helpful Answers will be rewarded.
Thanks in advance.Hi,
check tcode ME33
TABLES EKKO HEADER TABLE
EKPO ITEM TABLE
Regards,
V.Balaji
Reward if Usefull... -
Schedule line in Scheduling Agreement non modifiable
Hi Friends,
I'm creating Scheduling Agreement with VA31. The issue is that Schedule line category is coming as non-modifiable. Is it standard that in Scheduling Agreement, you can not overwrite default schedule line category? In customizing for Assign Schedule line categories, Manual schedule line categories are defined, but still I can not overwrite Schedule line category in VA31. Pl suggest what can be the reason. I don't have any ABAPer at my rescue.
Thank you.Sgr,
For Sch.Line Agreement for component suppliers,we cant change sch.line category as of normal sch.line agreement.
Based on MRP for Delivery Schedule Types (Field available in Header Data under SALES view) and item category,sch.line category will be determined.
MRP Indicator
FORECAST
JIT
A
L1
CN
B
L1
L1
C
BN
L2
D
L1
L2
E
CN
CN
However,To decide which type of delivery schedule is currently relevant for requirements and delivery, the system uses the JIT delivery schedule horizon and the material requirements planning indicator in the scheduling agreement header
Try to change the MRP Indicator available in Header data to match your requirement.
For more info,try this URL
Scheduling Agreements for Component Suppliers (SD-SLS-OA) - SAP Library
Regards
Logan -
Regarding Schedule line category,scheduling agreement.
Hi,
can u pls explain me about the difference between Scheduleline category and scheduling agreement.
Thanks & Regards
Ramesh chandra<b>Schedule Lines</b>:
Together with the sales document types and item categories, the schedule line categories contained in the standard SAP R/3 System cover the most common business transactions.
The SAP System can only copy items of a sales document to a delivery if they have schedule lines. The control of the schedule lines depends on the schedule line category.
The following menu options describe how you define schedule line categories or adapt them to the requirements of your organization. You must process the following points to do this:
You must define schedule line categories or adapt them to your requirements.
You must allocate the schedule line categories to the item categories depending on the MRP type.
If necessary, you must define schedule line types for scheduling agreements.
<b>Scheduling Agreements with Delivery Schedules</b>
In this step, you set scheduling agreements with delivery schedules used by the component supplier industry. This includes:
Control incoming EDI messages
Define schedule line types
Set planning delivery schedule functions
Regards,
Rajesh Banka
Reward points if helpful.
Maybe you are looking for
-
When I download a file the download window opens but not files are viewable. I cannot execute a file from this window. I can open the download file using Explorer and then execute the file from there. Why are the files not viewable.
-
Screen Resolution Problem in Session Method
Hi I want to use session method in BDC. How to resolve screen resolution problem in Session Method? Please give me the code or steps regarding this. Thanks & Regards venkateswararao
-
I'm a newbie in javacard. Here is my problem. I'm trying to encrypt a byte array of size 8. The cipher obtained is of length 16, But I was expecting this to be 8. Here is my code Cipher cipherinstance = Cipher.getInstance(Cipher.ALG_DES_CBC_ISO9797_M
-
Can I use my ATT iPhone 4S with a French carrier?
I am moving to France for a year and would really like to be able to use my iPhone 4S while I am there. Currently, my understanding is that I can simply take my iPhone to Orange when I get to France and have an Orange simcard put in my iPhone and the
-
hi all experts, Can anyone explain me one business scenario with Service oriented architecture. and some business cases. Thanks Sam