Segregation of Production orders based on System status

Hi Experts,
I need your inputs to our requirement, We are sending Production orders to third party tool (TPT)for detailed scheduling, so Production Orders based on
Order status need to be classified and send in such way to TPT.
Requirement is
    Just REL or CRTD (No Confirmations carried out, no TECO, NO CLSD)             = OPEN
    PCNF or PDLV or GMPS (will be accompanied with REL only No CLSD, TECO) = WIP,
    CLSD or CNF, or DLV or TECO                                                                      = CLOSE
So we are fetching the list of order from database tables not using MD_Stockrequirement_List function module,
Is there any way to call BAPI and then use status profiles to  classify the list of production orders we are getting now based on our logic.
or need to pass this list of Production orders to JEST table and do some coding to get this classification. But using JEST table its difficult for coding to get the requirement satisfied, because for one Production order there will be many order status as REL PCNF PDLV GMPSPRCMACM etc.
Please provide inputs.
Thanks
Naga

Hello Naga
You should use BAPI BAPI_PRODORD_GET_LIST to get a list of production orders, instead of MD_Stockrequirement_List.
Alternatively, you can use BAPI_PRODORDCONF_GETDETAIL to get the details of a production order.
BR
Caetano

Similar Messages

  • How to fetch service order with partucular system status and user status

    Hello All,
    How to fetch service orders with specific system status and user status.
    thanks

    I want tables or views from where I can fetch service orders. I have to design ALV report based on this.
    I want to fetch released service orders with status INIT and RENT.
    Here, SYSTEM Status = Released and
             USER Status     = INIT
                                        RENT
    So is there any function module available for the same.....

  • PCC vs Production Order Based Costing

    Hi,
    Please reply back difference between PCC and Production Order Based Costing.
    Thanks in advance.
    Regards,
    Sameer

    Hi,
    PCC is product cost collector which is  used in mostly REM process.
    1. Here you have to creat the product cost collector mean sthe cost is based on period, when u create PCC you are creating the priliminary cost means the quanity strucure costing considering BOM , activity prize and the cost from costing sheet i.e admin cost, etc .
    2. In product cost collector the the cost of document posted in backflush is posted periodiclly. For that u have to run standard cost run i. CK11N and CK24. monthly.
    3. but in Production oredr or Process order thre is no PCC instaed of PCC the cost is settle with the settlement profile defined in OPL8 i.e order type dependent parameter SPRO.
    4. Each prd ord is REL,CNF and TECO when the status is TECO means the logistic point of view the order is complet now ready to costing .
    5 Then FI consultant settle this order
    6. here order based costing no period based costing
    hope u r prob solve..
    Siddhesh

  • Bapi or FM or tabel or any standard transaction code for Production order linking to get child production orders based on parent production order

    Dear Guru's,
    we have a requirement i.e. user can convert planned orders in to production orders (CO41) based on those production orders we can get Route card( Z Smart form)  presently we are using manual input for that Route card. recently we got requirement for this i.e. make to automatic generation of route card for this requirement we need to get the list of child's production orders based on parent production order
    so as per my requirement i need to get all child part numbers production orders based on parent production order number and quantity i tried in MD4C and CO46 but those transactions codes are picking multiple lines also so for this requirement please give your valuable suggestions
    Regards,
    Venkat 

    Dear Friends,
    Thanks for your reply,
    My business process is MTS purely strategy 10, for route card all components with production orders we can give input as like bellow these production orders are converted from planned orders,between few components are don't have production orders those are F-30 materials,because of this reason i need link for production order to child components orders
    01
    IND1
    IND1
    A1CE2003520103-005
    55685815
    02
    IND1
    IND1
    A1CE2003520103-010
    55685814
    03
    IND1
    IND1
    A1CE2003520103-015
    55685813
    04
    IND1
    IND1
    A1CE2003520103-020
    55685812
    05
    IND1
    IND1
    A1CE2003520103-025
    55685811
    06
    IND1
    IND1
    A1CE2003520103-030
    07
    IND1
    IND1
    A1CE2003520103-035
    55685810

  • FOR MTO & MTS scenario when the Production order shows the Sysy status DLV?

    Hi ALL,
    In the MTO & MTS  scenario when the Production order system status become DLV ?
    Regards
    Satish

    Hi Satish,
    For both the planning strategies (MTO/MTS)..
    The status of the production order becomes DLV ,
    when you do GR for the order with 101 movement type.
    (OR) 
    At the time of final confirmation if automatic goods receipt is activated.
    Regards,
    Anil

  • Search Production Orders based on Sales Order

    HI,
    Ours is MTO scenario.
    How to find Production Order number(s) based on Sales Order.
    We are getting in AFPO, but if the process starts from Enquiry or Quotation then there is difficulty.
    Because there can be multiple documents of enquiry or quotation.
    Kindly suggest.
    Thanks
    Ramakanth

    Ramakanth
    Did you try T code  COOIS - Order Information System?
    Here you can enter the sales order # ( Single values, range etc.) and get a list pf Production Orders?

  • How to delete production orders that have release status set in APO ?

    I have a few production orders which have a release status set in SCM 5.0 system. I need to delete them now. I cannot delete them from ECC since the ECC system no longer exists.
    I need to delete these orders in APO only ? Is there any way to do this ?
    Thanks in advance for your help!!
    Ranjini.

    Please try deleting with either of the reports  /SAPAPO/OM_DELETE_INCON_ORDERS or/SAPAPO/DELETE_PP_ORDER

  • Dyanmic work center selection in production order based on material

    Hi ALL,
    We’ve a business requirement to support the following functionality.
    There are four similar type of milling machines say MILL1 MILL2, MILL3, MILL4, we create a single work center called MILLMC by specifying total capacity of four milling machines in the capacity header screen of work center with 4 individual capacities. And we mention work center MILLMC in the operation of routings for respective materials.
    However, during production order creation, there needs to be provision for detailed planning of work centers as per the following requirements
    In production order, some operations can be performed on any one of the machines MILL1 MILL2, MILL3, MILL4, so provision needs to be there to enter exact machine on which it is performed in the production order operation after the details are copied from respective routing during production order creation.
    In production order, some operations can be performed on only MILL3, so system should select only MILL3 in the respective operation of the production order
    In production order, some operations can be performed on either MILL1 or MILL2 or MILL4 and not on MILL3, so system should not select MILL3 in the respective operation of the production order.
    Please provide your valuable feedback to support the above requirements.
    Regards,
    Satya.

    Hi Satyanarayan,
      Please do refer to the below document. I think the same concept can be used for work centers as it is used for resources in PI industry.
    Resource Classification in Master Recipe for Planning
    Regards
    Kalyan

  • Capacity planning and schedulng production order based on availabe capacity

    Hi Gurus,
    I am trying to use capacity planning, when the production order is created it takes the order start date as the requirement date. Then when i do he capaity check it says capaity not available. After finite scheduling again it proposes to shift operations by certain days.
    I need the capity to be check in MRP and the palled orders to have start dates based on aviable capity, currenty all the palled orders are starting on the requirement date irresptive of avaiabe capaity. I tried using finite scheduling option in MD02 still it does not take in to account exsting production orders for giving dates of the planned orders.
    Regards
    Abhi

    Dear Abhishek,
    1) This is Std SAP of MRP, only material Av check will be carried out in MRP & create procurement
    Proposals
    2) Capacities will not Checked  ( consider ) in MRP in Std R/3
    3) Your Need can be only met through APO
    Regards
    Madhu

  • Process to split production order based on the raw material batches

    Hi All, below is a business situation which needs some some SAP process to help overcoming this issue.
    We are working on process industry, where the core fabric (SFG) are produced from different machines and which are used as raw material in the subsequent process (Coating).  Business wants SAP to generate individual planned orders for Coating when it uses this materials
    e.g
    Current situation.
    SFG1  is the component of SFG2
    SFG2 is  the component of FG.
    When the demand for FG is 100, you get 2 planned orders  SFG1- 100 yd and  SFG2- 100 yds
    During production, the Planned order for SFG1 is split for 2 production order  each producing 50 yds each.
    Now I have SFG1 - 50 yds ( Batch A001), and SFG1- 50 yds ( Batch A002).
    Now Business wants  SAP to automatically propose 2 order for SFG2, However based on MRP it will  only show 1 planned order of 100 yds required for SFG2 since the demand of FG is 100.
    We want to split the planned orders of the higher level to look at lower level stock.
    Any ideas or thought process.
    Regards
    Sarvan

    Sarvan,
    You can have MRP propose two lots of SFG2 based upon lot sizing.  For instance, if you always will want SFG2 to have orders of 50 each, then one way to achieve this would be to set the 'maximum lot size' to 50.  MRP1 Tab of the material master.
    There are other lotsizing methodologies that may be better suited to your business requirements as well.
    Lot-Size Calculation - Consumption-Based Planning (MM-CBP) - SAP Library
    Best Regards,
    DB49

  • Production Order and external system non-SAP

    Dear Friends,
    I need to send a Production Order to a external system no SAP, and upload the information back to SAP,
    SAP does something standard to accomplish this task?
    To send Production Order, I created an IDOC with report RCCLORD, this IDOC contains all information of a production order (AUFNR, WERKS,..) and all operations and materials. But I don't know how to process the information returned.
    Also I have read some information about the interface PP-PDC, but I don't know how to use it.
    Please, Can anyone tell me the best way to accomplish this task?
    this is the scenario:
    SAP R/3 -
    > Production Order -
    > External System
    External System -
    > Return information about Production Order -
    > SAP R/3
    Thanks!

    Hi,
    PP-PDC is for confirmations only, see further details
    http://help.sap.com/erp2005_ehp_05/helpdata/en/31/fcbd3411d411d3b6b60000e8359890/frameset.htm
    maybe usage of POI is an option for you. See details here
    http://help.sap.com/erp2005_ehp_05/helpdata/EN/1a/0e347b539911d1898b0000e8322d00/frameset.htm
    BR Sabine

  • Printing production order in a created status

    Can I print a production order when it is in a created status. If yes then how do I control the configuration

    John,
    I standard SAP, this is not allowed. If you need than you need to make changes to CRTD status in BS22 transaction where you need to allow "PRINT" business transaction. Caution, this would be applicable to all applications not only PP. I dont really recommend this.
    Regards,
    Prasobh

  • Only Production order Based on SO

    HI Experts...
    how to do the settings for planned/production order only based on sale order..
    the the raw material requirement based on forecast..
    If there is no sale order no planned or production order..
    but based on forecast the requirement will generate only for raw material planning.
    I mean Raw material planning based on forecast..
    and Production or finished goods planning based on sale order.

    Sri Ram,
    You have several options open to you. 
    First you need to decide where you will forecast.  You mentioned RM planned by forecast.  Will you Forecast each RM?  Or will you forecast your subassemblies? Or will you forecast Finished goods?  Or....?
    Also, you need to think about where (if anywhere) you will keep inventories.  RM?  SubAssys?  (Obviously, not FGs, since you don't want any orders except to support a Sales order).
    So, here are the planning strategies that may be useful to you.  I will exclude any characteristics based strategies for now
    Forecasting FGs
    Strategy 50 http://help.sap.com/saphelp_erp60_sp/helpdata/en/e0/71bb199c9f11d191920000e8a5f6e6/frameset.htm
    Strategy 52 http://help.sap.com/saphelp_erp60_sp/helpdata/en/a2/4e79a0927d11d1800f00c04fadcb73/frameset.htm
    Strategy 63 http://help.sap.com/saphelp_erp60_sp/helpdata/en/a2/4e79a3927d11d1800f00c04fadcb73/frameset.htm
    Or you can use straight MTO at FGs
    Strategy 20 http://help.sap.com/saphelp_erp60_sp/helpdata/en/e0/71bb1f9c9f11d191920000e8a5f6e6/frameset.htm
    Combined with forecasting at a lower level in the BOM
    Strategy 70 http://help.sap.com/saphelp_erp60_sp/helpdata/en/1a/c2ba8c935011d1801000c04fadcb73/frameset.htm
    There are other ways as well.
    Rgds,
    DB49

  • Collective production order link based on parent production order in MTS with strategy 10

    Dear Team,
    Now we are using MTS Production order system with strategy 10,As per my Business requirement we need to take all the child components production
    orders based on the Parent component production order .In this case for planned order conversion we are using CO40 transaction code(i.e. Collective conversion) as well as all planned orders  generated through MRP. As per my business process we are using Route cards which are Z smart forms with all Production orders from parent to child component with quantity is taken as a PDF printout,As per our customer requirement we will store those Route cards up to next 15 years. When user has to check Production order linking at any point of time, this functionality is not available for MTS. I tried MD4C but it is not a best solution for my business requirement.So please provide any another standard solution available for this requirement.
    Thanks in advance,
    Regards,
    Krishna.

    There is another suggestion that you can determine the costing indicator in the requirement class. you can get the requirement type from procurement page in the sales order header, then go the customizing menu to find out which requirement class has been assigned to the requirement type. Then you can get the "costing" and "mark" indicator.
    The customizing menu is the node of controlling - cost object controlling -> CO PC for sales order.
    Correct me if i am wrong, thanks.
    Best Regards!
    Flex Yang

  • Month end closing - production order status

    Hello,
    I am requesting the information, can I  carry  the month end closing and account for only production orders having the TECO system status rather than considering production orders with the DLV status.
    Where in SPRO these parameters are being adjusted .
    Thanks and Regards
    Artur

    Hi,
    For settlement, the Order Status Should be TECO and/or DLV.
    If it is not TECO also, with DLV status syetm will consider the Order for Settlement.
    With BS22 (Maintain System Statuses) you can handle the Situation..
    Travel to I0045 - TECO- Double Click on that.
    Please refer this link also
    [Link|Re: scrap]
    Hope this clarifies..
    Regards,
    R.Brahmankar
    Reward if useful.

Maybe you are looking for

  • Iphone 5 other person can't hear my voice - possible fix.

    Hi all I have a 2 month old iphone 5 replacement from Apple. Randomly around 1 in 10 calls the receiver says they can't hear my voice. Normally I will stop the call and it takes around 3-4 more calls straight away to rectify the issue. Highly annoyin

  • IPod 5G takes 70 seconds to mount, or not at all.

    I've been plagued by my iPod taking seemingly an eternity to mount. It either takes around 70 seconds to be found by Finder and in iTunes, or it just doesn't get found at all. My G2 Nano 8G works OK (only a couple of seconds to get recognised) on the

  • Why are photos in pagemaker & PDF printing in solid blue?

    I publish a newsletter that I layout in Pagemaker 7.0. When I printed it out to proof, all the photos, color and B&W printed out in one solid bright blue block. Also some pieces of text were missing in the print out. Same thing happened when I printe

  • HT4597 What is the best replacement for Mobileme Gallery?

    It has been a great way to share photos with my family overseas, and the new service is a poor replacement. Suggestions?

  • Will the iphone 5 be unlocked?

    Hi everyone, I'm just wondering if the soon-to-come-out Iphone 5 will be unlocked or will it be locked to each other the carriers (such as AT&T,Verizon, and sprint)? Because I have a t-mobile phone number, so i was just wondering if I it individually