Selecting prod.version before MRP run

hi all;
can any body know about-how  the production version selecting before MRP run?
for example: I have a material.it has 2 production version. when I run the MRP, MRP reads first production version(prd vers-1). but I want to select other production version(prd vers-2). how can I make this selection?
Regards,
Sema

Hi,
If you want to select the perticular alternative BOM define it in production version.
Theree is option by which the PV is manually assiged
Goto MD62
Execute the report
Goto Schedule line tab page
Fallow the menu path
Setting Production version
Enter the Production version required
Save
So system will select the perticular alternative BOm which maintain in that production version.
Regards,
R.Brahmankar

Similar Messages

  • Selecting production version in MRP run

    Hi dudes,
    our client is having reuirement is he will select the production version irrespective of lot size, but he select the production version at the time of manual creation of process order where it depends on resource(work center used in recipe of particular production version, BOM will be 1 alternative only.
    now while running MRP how to make system to allow manual selection of production version at the time of converting planned order to processs order.
    respond asap plz...
    Daniel.

    Hi ,
    During MRP, system will select the production version based on Validity date & Lot size.
    If a material contains two production versions with same validity date & Lot size qty , system will select the First valid PV by default (unless it is locked) & will copy to planned order.
    When u convert the planned order to production order,default PV will be copied automatically from planned order. Here u cannot select PV manually.
    Settings:
    Create valid production version with lot size and Valid routing , BOM at MRP view of Planning material.
    Assign the selection method = 2 or 3 at MRP view of Planning Material
    Regards,
    Anand.

  • Release strategy in sales order is required before MRP run

    Hi Experts,
    My requirement is Release strategy in sales order is required before MRP run. My client is doing the following process:
    1) Creation of Sale order (MTO).  Ex: User creates 10 sale orders per day.
    2) MD04- Stock Requirement List. All 10 Sale orders should be displayed. So no problem here.
    3) MD50-Make to order-Planning . Here when user gives the sale order number and sale order item and press enter, then only the released sale orders should be allowed and the rest sale orders it should throw a error message and it should not allow to process further.
    How this situation can be addressed in SAP.
    Kindly post some hints and comments.
    Regards,
    Kiran.

    Hi Kiran,
    Define and Assign status profile BS02 at sales order detail (line item) lets say with create and release status
    SD>Sales>Sales documents>Define and assign status profile
    Have create status as default while creating SO with item
    And do a user exit change for MD50 with ABAP consultant help and release it when user keys in SO and item.
    For other line item I believe it will give an error
    Pls try and update if it solves your requirment
    Regards,
    Siva

  • Selection of Production version during MRP run

    Hello experts
    At present I am having 2 production versions for a material code as PV01 and MV01.
    By putting validity date I am restricting correct version to be picked in MRP.
    Is there any other way, for example in material master where if I maintain the production version, then MRP should pick that only.
    Please suggest the best way.
    Regards
    Pradipta Sahoo

    Dear Pradipata,
    If you are having more than one production version for a material for the same Lot size and validity
    dates,and if you have given BOM selection method as 2 in MRP4 view,then always the system picks up
    the first production version defaultly.
    If you want the system to pick up the second production version in that case means,you have to lock
    the first production in MM02 or C223.
    Check and revert back.
    Regards
    Mangalraj.S

  • Alternative BOM problem in MRP run

    Hello Experts,
    We have two BOM for one material.Now I want to use BOM-1 for MRP run & BOM-2 for subcontracting.I have maintined following settings.
    1) Production version.
    2) BOM explosion selection method in MRP4 -2
    3) Assign PV in inforecord for subcontracting.
    4) Assign PV in MD61 in schedule line .
    But when I run MRP it still consider subcontracting BOM.Have I missed any setting?
    Kindly guide.Thanks you.

    Hi, Follow the below process,
    1.Enter the BOM selection method as 2 in the MRP4 view of the material master.
    2.In case if you have not assigned the production version in MD61 against the PIR's under schedule line
    tab key (in the top menu click on settings and prod version ,then you can assign the prod version which
    you need to pick during the MRP run),the system always picksup the first production version during
    MRP run even if all the prod versions contains the same validity dates and lot sizes.
    3.If you are not willing to assign the prod version in MD61 ,but the system should consider the second
    prod version for MRP run means,then set the locked status for the first prod.version.
    4.When run MRP via MD02 or MD50 in the simulation mode.(i.e w/o giving tick in simulation mode).
    Click on Save,You will get a pop screen,
    Now click on the continue icon, Then go to Plaining Results: Individual lines screen.where you will get Plan order on which when double click you will get pop screen below,where you have Planned order no,quantity,plant,storage location,and version.
    Now here you can select the required version,and it will become firmed. This BOM will be used in the order now. Try it.

  • Production version selection in MRP run

    Hi all
    here my requirment is to select the Alternative BOM in MRP run.
    i have three alternative BOMs. and two routings. to make different combinations i was created Production version. so now my requirment was while run MRP how to choose production version manually. i was mantained MRP 4 screen for selection method as 3.
    my All BOM validity dates r same and same lot size.
    can any one suggest me how to choose production version manually in MRP run. otherwise system by default it choosing 1st alternative.
    Regards
    Deviprasad

    Hi All,
    Thanks for all your suggestions. here my requirment was not matching with these.
    my req was
    1. want to select prod version while run MRP.
    2. my demand was MTS.
    3. i already marked in MRP 4 Screen as selection method as 3.
    Constrains
    my BOM validity dates r same.
    lot sizes r same.
    i am giving hints for this.
    In Customization - BOM selection ID, Selection priority and BOM usage, Alternative selection of BOM in MRP.
    i was tried to mantain this. still system picks the default as first production version.
    can u try for this. how we can configure in SAP.
    example.
    i have one material as M-20. it has differnt grads of mixing as R1,R2,R3 alternative BOMs. all alternatives have same materials with differnt Compositions. i want to choose one alternative while run MRP. But system by default picking first alternative BOM.
    regards
    Deviprasad

  • MRP with selected production version

    Dear PP experts,
    I have two production version
    Prod. Version      From lot        To lot size        Base Qty.
       1001                      1                   100                100 Kg.
       1002                      101             9999999          400 Kg.
    The batch size mentioned in the material masters are Mimimum lot size 100 Kg. and Maximum lot size as 400 Kg.
    I have entered PIR in MD61 for the material for 350 Kg. Since I need planned orders selectively of 100 Kg. in MD61 I have maintained in schedule lines tab production version as 1001.
    After running MD41 system creates planned orders with the production version, but the batch size is not as per the production version.
    Pl. let me know what needs to be done.
    Regards,
    Prashant

    Hi Watson,
    I can see some conflicts in your Master Data settings.
    First of all you have set your Lot size ranges in Material Master Data from 100 to 400 Kg.
    And your Production Versions (1001) set lot size range is 1 to 100 Kg.Which may creates conflicts.
    Now your require qty is 350 kg.So as per your lot size restriction set in Material Master will force system to create one planning proposal of 350kg.I can guess you get one plan order of 350kg but due to selection made in (MD61) selected prod. version is 1001 instead of 1002.Which is again wrong
    Now to make the things correct you can have below options,
    1) change Lot size restriction to 1 to 100 in Material Master.So you wil get 3 Plan orders of 100 Kg and 1 of 50 kg.
    or
    2) Instead of changing Lot size in Material Master, use quota arrangement (MEQ1).For this you have to first activate Quota arrangement in MRP 2 view of Material Master.Then go to MEQ1 and create quota for the specified period.Here you can restrict lot size at production version level.
    Regards,
    Dhaval

  • Selection of BOM During MRP

    Dear All,
    I have three alternatives of BOM.The lot size and the validity period for all the boms is same.Now during MRP Run the system only selects the first alternative and plans the depending materials of that BOM.
    I want to set the system in such a way that i can able to select any alternative of bom and carry out the MRP Run.
    Please help me ..
    Regards
    Prashant

    Hi Prashant,
    With same valid From & To Date and Same Lot Size,
    In this case system will select first BOM alternative.
    If you want to choose a particular BOM then go for  production version ,assuming that u r not willing to change the lot size or valid from & to date,then u lock the production versions which you dont want to show to the system before running MRP except the one which u r willing to choose.
    We cant choose manually the prod.version during MRP.
    Assuming that in MRP4 view of FERT material u have given option 2 in BOM slection method.
    The other way is u manitain different lot size and acccordingly the production version will be selected by the system.
    I hope it will help you.
    Regards,
    R.Brahmankar

  • Make to order with Prod version with object depedency

    I m using 2 production version. In both case BOM & Routing having object dependency. Its make to order scenario. How can I select prod version in costing as well in configuration in sales order. Because by default its taking first version for both configuration & costing.How??
    And if I select second version in sales order, in prod order it should automatically take second version. How??
    Thanks
    varun

    Hello Varun,
    If you have two valid production versions for a part then by default system take the first available production version. You have give some selection criteria through quota arrangement.
    In ck11n you have the option for selecting the vesion in the quantity structure tab so i think there will be no problem for costing.
    For selection of production version in the production order you have work with planning strategy 82. Or incase of MTO (strategy 20) run MRP from MD50...your assigned production version in sales order will be planned.
    If helpful rewards your points
    Regards
    TAJUDDIN

  • Use of different production versions for MRP and costing

    Dear PP Gurus ,
    We have a scenario in which there are multiple production versions for a particular product .The MRP run as welll as costing run considers only the production version 0001.
    We would like the system to consider different production versions for MRP and costing ..that is 0001 for MRP and 0005 for costing .
    Is this possible ... if yes ...Kindly suggest the config and master settings for this to happen .
    Ram ~

    Dear Ramakrishna,
    For doing the costing for a specific production version use CK11N,under quantity structure tab key you
    can assign the prod.version which is to be used for costing purpose.
    While taking MRP if you want to consider the particular Prod.version,assign the demand to the
    correct prod.version under schedule line tab in MD61.
    Otherwise the system always picksup the first prod.version for MRP.
    One more alternative is you have to lock the other prod.versions if you want the system to consider a
    particular prod.version.
    Check and revert back.
    Regards
    Mangalraj.S

  • Schedule lines not generated after MRP run

    Dear All,
    I am trying to create Schedule lines through MRP run , but instead system creates MRP element PRqRel  and its PurRqs when i check in MD04 ,  the following are the prerequisite i done before MRP run , but still Schedule lines are not generating.
    1.activated checkbox source list in material master.,Procurement type is F, MRP type PD , lot size MB , marked JIT  Scheduling indicator as 1 in Pur view of material master , no MRP group is used in our process.
    2.Maintained Inforecord.
    3.Maintained source list for the material and marked MRP relevant as 2. Validity also checked.
    4. Quota arrangement for this vendor only.
    5. Created New scheduling agreement.
    6. Material is not sent for subcontracting.
    7. Ran  MD02 with following parameters ,
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Delivery schedules 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 3 Adapt planning data (normal mode)
    Please let me know if i am missing something
    Thanks in Advance
    Benny

    Hi,
    Please check the below links...
    Schedule Lines not getting created in MRP
    Schedule Lines not generated for MRP Type PD
    Kuber

  • MD01- MRP run in test mode.......

    Hi Expets,
    My client wants to see the Material and quantity going to be generated by MRP run, so how can I run the MD01 in test mode, in order to view which materials are planned and with what quantity PR is going to be generated before MRP run, Same like in the single level planning MD03 with "Display results before they are saved ".
    Regards,
    Sri.....

    Hi Afshad Irani ,
    My question was is there any way to see the test results in PRD only like in MD03 T-Code.Every time we can not copy the PRD to Quality.
    Regards,
    Sri.......

  • BADI For Changing Planned order Qty during MRP Run

    Hi,
      My requirement is i want to change Planned order qty based on some conditions during MRP run(MD02). Is there any BADI to fullfill my requirement.
    Thanks,
    Kishore

    Not sure I understand the situation correctly...You want to delete the planned orders before MRP runs again. WHy do you want to do that ? Are these firmed Planned orders ?

  • MRP run with lot size as per prod. version and capacity levelling

    Dear PP experts,
    Hi, We are working with strategy 10. For SFG and FG produced inhouse we have created BOM and recipe with production version.
    For example:
    I have a production version with batch size as 100 Kg.
    I load PIR for 500 Kg in MD61.
    I have maintained lot size as EX in the material master but I have not defined mini. and max. lot size.
    Is it possible during the MRP to consider the production version batch size if the mini. and max. lot size is not maintained in the system and create 5 Planned Order of 100 Kg each.
    I know, how it can be done by using lot size in material master or by maintaining schedule lines in MD61 or by maintaining quota. But if nothing is maintained is it possible for the system to create 5 Planned orders as per the production version batch size.
    Pl. check if this is possible and revert back.
    Regards,
    Prashant

    Hi
    No, system will not consider the size that maintained in the production version  for the creation of planned order while the mrp run .
    This lost size is used to validate the bom/ routing combiation for the particular  pv of the material

  • MTS - MRP Run and Poduction version

    DEAR PP GURUS & EXPERTS,
    There is a case of MAKE TO STOCK and we have multiple production versions (OR BOM) for a single material.
    Now, MRP Point of view: Suppose we want to produce (let 6000 PCS) of that finished goods. Out of which:
    1000 Based on BOM1,     2000 Based on BOM2      3000 Based on BOM3
    Can we differentiate 6000 PCS During MRP RUN or During MRP Run can we devide the Finished Qty in percentage.
    Thanks in Advance.
    DSC
    Edited by: Devendra Singh Chauhan on Dec 23, 2010 2:02 PM

    DEAR PP GURUS / EXPERTS
    Suppose, I have finished Goods 20017440 for which I want to produce 5000 PCS. For that I have mentioned  Quota arrangement  Usage 3 in MRP-2 View, In MRP-4 View Under BOM Explosion / dependent requirement I have mentioned
    Selection Method -3 and also mentioned Production versions (1001, 1002 & 1003).
    After that in MEQ1(Quota arrangement) I have mentioned Validity and three lines for this item by defining:
    QAI     P     S     PPI     Ver     Quota     in%     Quota BAse Qtt
    1     E     E     1152     1001     2     20     1000
    2     E     E     1152     1002     5     50     2500
    3     E     E     1152     1003     3     30     1500
    After that Run MRP in MD02-NETCH-2-1-3-3-2 and chek the result in MD04.
    But Result is appearing only for 1 Production version not for second and third.
    Actually my requirement is: I want to Produce 1000 PCS as per production version 1001, 2500 PCS as per production Ver. 1002 and 1500 PCS as per Prod. ver. 1003. So, total Qty. is 5000 PCS. For these I want to run MRP and generate planned Order.
    Please Suggest Where I am wrong.
    Thanks in Advance.
    DSC