Service PO from Delivery Order

Hi,
I have the following scenario.
On creation of a Delivery Order, I would like to trigger automatic creation of a Service PO. I am looking for ways to do it.
Could some one guide me on how to proceed. I am looking for the right exit where I can put my code (for  creation of Service PO through BDC).
Thanks & Regards,
Shobhit

Hi Shobit,
You can you FM BAPI_PO_CREATE1 for creating Service orders.
But, let us know how you are creating Delivery Order.
If you are creating through VA01 (Order Type : TAM), then you can code at USEREXIT_SAVE_DOCUMENT_PREPARE in Include MV45AF0B_BELEG_SICHERN.
Regards,
Raj
Message was edited by: Rajasekhar Dinavahi

Similar Messages

  • Credit release transfer from Delivery order to sale order

    Dear Master's,
    Our setting for credit release from delivery order but now change requirement from our organization, they like this check from sale order and i create setting it in test server but there is a problem with me, every thing is ok, system also block sale order for credit release but the value that is, net value. our requirement is different, we need gross value as we already working in previous with delivery order. anybody can solve my problem, i try to find it and feel there is no problem in setting but problem still in system.
    Regards
    Khan

    I already "A" which is credit amount adjust in Gross value after tax and all other discount values but i am confuse why system release value from before tax and trader offers
    Muhammad Arafkhan 
    Please use correct English. it is very hard to understand your requirement the above is one of the  small examples of your post. Am also not perfect.However, will try to use correct English to my level.
    Please never use any SMS language and try to avoid the maximum  grammatical errors.
    Coming into your requirement as per my understanding, previously you were using the credit control at Delivery level, now the same setting is changed to order level is that correct?
    Now kindly explain your requirement once again what is the issue after this change in OVA8? I did not understand completely.
    thanks,
    Srinu.

  • CRM- Find Service contract from Internal Order Number

    Hi Friends,
    I would like to know how to get service contract from internal oredr number.
    From service contract we can find internal order number by using CRM_ORDER_READ function module- table et_document_flow, but my requirement is how to find service contract from Internal order number.Any function module or BAPI available for this requierement ?
    Regards
    Vinayak Sapkal

    Hi,
      when the costs are transferred from CRM to R3, they are posted to an internal order. When a service order or incident is transferred to R3, we have to create an internal order for it, regardless of whether or not a contract has been assigned.
    This is all linked to the logic used in CO to find the appropriate internal order. It works as follows:
    The internal order is stored in the table IAOM_ASSIGNMENTS. This is accessed by a guid (the account assignment guid).
    To get this guid, there is a second table IAOM_EXT_OBJ_INF. This table links the GUIDs coming from CRM, dependent on the CO Customizing for CRM (Mass Controlling, Header level, item level controlling etc.)
    This is how we manage to link a service order to the internal order of a contract in the first place.
    When we call CO, CO first looks for an assignment for the object guid passed. If a service order has been linked to a contract, nothing will be found for the object guid. CO will then check for assignments to the reference guid and find the contract entry.
    If no contract has been assigned, CO will create an internal order based on the service order guid.
    From a CRM point of view, costs are assigned directly to an item, and so it makes no sense to have a reference guid for the costs or the possibility to change the guid via BADI.
    regards
    Waman

  • Deletetion of  service PR from maintenance order

    Hi Experts ,
    Is it possible to delete service PR from maintenance order. If it is created from order due to some problem I want to delete it ,so is it possible ?
    With best regards,
    AVI DDS.

    Hi
    Deletion of PR from Maintenance Order is not possible because the PR is created automatically
    This PR will get deleted automatically when you cancel//teco/complete the order
    Otherway around is you can always block the PRs
    Regards
    Kartik

  • Can we create service po from sales order

    HI
    can we create sales order from service po. if yes then how can we do so.

    Hi,
    we can create po from sales order in cross docking functionality.
    The steps are
    Sales order > Purcahse requistion > Purchase order > Inbound delivery with reference to purchase order and PGR > Outbound delivery with refernce to sales order and PGI > Invoice and billing.
    Br,
    Tushar Patankar

  • Auto generated service PR from maint, order

    Dear Experts,
    As you know while processing external services using control key PM03, a service PR will be generated for the service selected from the agreement or contract & from there we will create PO.
    Here in my case while creating PO from auto generated PR it is not carrying the condition type ( Discount entered the contract).Instead of that it gives the option to enter the condition type in the drop down list.Then we can select the condition type as discount & process the order.
    where as for the same service from the same agreement,if we create the PO from the manually created PR (not the auto generated from maintenance order) it carries the condition type of agreement (discount) to PO & the discounted price will be displayed automatically.
    Why it is not happening to auto generated PR? is there any particular settings are available? is there any notes available?
    Please help me out to come out of this problem.
    Thanks & best regards,
    Praveen

    Dear,
    I am extremely sorry for this issue. there was some problem with the program & rectified the same.
    Thanks & Best regards,
    Praveen

  • Service PR from PM order

    Hi gurus,
    Is threre any way to stop PR generation from PM order, when i select any service with control key PM03 , because i am not interseted in planned cost, but need to book service required in PM Order at the time of planning.
    Any standard config or any customisation.
    thanx in advance

    you can do teh folowing change in SPRO , then yu will not get the PR from maintenance order;
    Go to
    Maintenance and service processing-->Maintenance and service orders>Functions and settings for order type->Define change document,collecctive PR indicator,operation no interval.
    Inside this there Select PR never.
    But as Pete said what you means by planning . Your query is not cleard. what you want to do.anyway by this PR will not be created.

  • Passing 'Service Level' from Forwarding order to Freight order

    Hi All,
    If I create a Forwarding order with Service Level "XYZ" and create a freight order from it,
    the service level 'XYZ' is not passed on to the Freight order Service Level field.
    Instead of 'XYZ' it is empty.
    When investigated found out that, freight order will take Service Level defined in the corresponding Freight order type.
    In my case, the Service level in Freight order type is left Empty.
    Is there any workaround to bring the Service level from FWO to FO?
    Thanks & Regards,
    Michael.

    Hi Michael,
    It depends how you are creating a FO from forwarding order. Do you have FUs as linkage or you are creating FO directly by using FUBR?
    Thanks & Regards,
    Tarun Kumar

  • Populate G/L account into service entry from Purchase order

    Hi Guys,
    I created a service PO, where the G/L account was populated based on the material group i changed the G/L account to a new one  and saved the PO.
    Now i am trying to create a unplanned service based on the PO using ML81N. When i provide the short text quantity, Uom and gross price and click account assingment button the G/L account is deafulted from the material group assignment . It does not populate changed  G\L account from the PO line item.
    Is there any configuartion or enhancement that we can apply to get this done.
    Thanks,
    Amit

    Hi,
       In SproMMPurchasingMaterial masterentry aid for item w/o material master...maintain the valuation class for the Material group.
    In OBYC maintaing the G/L account for this Valuation class in GBB--VBR.
    Enter this materila group in the service order.System will automatically determine the G/L.
    Even if you enter acct assignment U...while posting the service entrt sheet this GL will be fetched.
    Rajesh

  • Services PR from PM order released with dif value from Out. Agreement

    Hello,
    We are creating PR for services (item category D) coming directly from released maintenance orders. We select an outline agreement in the PM order and the service. Change the gross price in PM order. When is released a PR is created, but the price picked is the one in the contract and not the one changed in the PM order.
    Does any one have this issue?
    I already check OMET and OIOE and parameters EVO + EFB but they are related with the price coming from PR to the PO, not from the contract to the PR.
    http://www.sapfans.com/forums/viewtopic.php?f=6&t=339306
    I already did some research but no confirmation of what is the standard behavior and if this is customized or is an enhancement.
    Best regards.
    Tania
    Edited by: Tanunu on May 11, 2010 9:54 AM

    Dear Tania,
    have you also the PO created? If yes, after a service purchase requisition item have been ordered the              
    purchase requistion is closed. If you try to change the price in the PM order now, it would have no effect.                                                                             
    In the standard system it is not posible to change the service lines in this situation        
    and the information message SE721 is issued.                                 
    But the message SE 721 can be customized to a warning message. Please test it.
    Please check also if you have the exit  EXIT_SAPLCOZF_001 implemented in your system. It could also change the behaviour.
    íIf you use service masters, it is worthy to check also the price update flag (ESLL-SPINF).
    Regards,
    Edit

  • Service PR from production order operation!

    Hi All,
    I just want to check whether it is possible to trigger service purchase requisitions (with item category D) for an external vendor from a production order operation?
    If it is, please let me know the procedure to do so...
    Regards.
    V S

    >
    V S wrote:
    > but how do i get the item category in PR as D for service?
    Hi,
    Item category D is not possible but u can use that pr as Service PR ... We were using this process only.
    Now we are creating manualy.
    Arun

  • Service number from purchase order number ?

    Hi People,
    can anyone tel me how to take service / activitry  number from the corresponding purchase order
    number.... ( table flow in detail ) where these service number are stored with respect to PO ?
    thanks,
    Siva

    Hi
    Take the value of the field PACKNO from EKPO table and pass it on to the same field PACKNO in ESLL. Here you can pick up all the details:
    For Example:
    select packno from ekpo into it_packno where ebeln = "purchase order number.
    select * from esll where packno = it_packno-packno.
    If you want sub package number, it is in the field SUB_PACKNO(activity number) in ESLL table.
    Vishwa.

  • How to avoid automatic data change in service notification from work order

    Hi,
    when I change work order address data the address data from the service notification connected to the order is changed too, how can I avoid this change? Is there anything on customizing to control whichs fields are updated automatically.
    Thanks,
    Juan.

    Hi,
    You can trying using Books of Business.
    Create a book and add that particular user to that book and at the time of task creation, through a workflow you can assign it to the corresponding book.
    This might resolve the access issue you are facing.
    hope it helps,
    Mayank

  • Unable to create Service Contract from Sales Order

    Hi Guru's,
    I put a sales order with one product and service line. SO has been closed and then I ran 'Service Contract Order Capture Integration' program.
    When I query my SO using Reprocess Order, I got error status with message as "Request ID : 8360452; Referenced Product not present in the Installed Base;".
    So I searched in metalink found - 'Referenced Product not present in the Installed Base [ID 549160.1]'.
    As mentioned in the document I checked the freeze flag in Oracle Installed Base Admin --> Setup --> Install Parameters.
    The same already been checked. I also checked the service item definition and found IB track not checked under service tab. When I tried to check the flag, an error states that 'Non subscription contract Item cannot be Install Base trackable'.
    Now how to overcome this issue. Any help will be highly appreciate.
    Instance Details:-
    RDBMS : 10.2.0.4.0
    Oracle Applications : 11.5.10.2
    Thanks,
    Bala

    Hello Bala,
    The 'Installed Base Trackable Flag' is a Master Item Controlled attribute in Inventory, which means that when the Attribute is set at the Master Item Level it is cascaded to all Child Organizations.
    If there is inventory in any of the Child Organizations, the flag cannot be changed at the Master level.
    You must issue all of the Inventory out of each Child Organization, change the flag at the Master level.
    Thanks
    -Arif.

  • Generate External Service PR from Process order

    Hi,
    i want to generate a PR for external service on an operation fro the process order and then make a service entry sheet against it, is this possible in SAP? I set the control key accordingly, a PR is generated but it is not for external service, it is working well for subcontracting. It is possible to generate PR for external service manually but i want to automate the process.
    Thanks

    Hi Muhammad Naveed,
    In PP cycle we do not use the concept of taking external services. External services is hiring a vendor to come to your plant and do the servicing for your equipment. This is followed in plant maintenance module.
    In PP cycle, we only send the material outside to vendor for doing a certain operation using PR - PO (subcontracting scenario).
    Hope you are clear.
    Regards,
    Naren

Maybe you are looking for