Client is uploading one file having employees expenses through Customised Tcode which is generating one Batch session.and executing the same through SM35
Now the problem is Its Picking up correct Vat Code which should calculate 10% but it is calculating 5%
Its picking up the Vat code basd on condition - Country code and Vat amount which is there in Flat file.
Whle debugging even though Abapers are changing the Vat code , lets say for 20% , then also it is calculating same 5%
In FTXP the Vat rate is 10%
Do i need to check any configuration step ?
It has anything to do with Customer / Vendor Condition type ?
Do we maintain any Tax rate anywhere else in SD or  MM apart from FI
Can any one suggest me where the story might be wrong?
Its critical issue
Positive response would be appreciated.
BR
aadii.

Hi Dennis Knutson
Thanks for your suggestion.
Tushar Jambhekar
[email protected]
Jambhekar Automation Solutions
LabVIEW Consultancy, LabVIEW Training
Rent a LabVIEW Developer, My Blog

Similar Messages

  • CFM /TR - how system calculate amount based on rate FX 60A

    Hi all,
    i need to know how system calculates amount based on rate entered upon creating a contract (t-code TX01).
    steps input:-
    1. header - comp code, product type, trans type
    2. partner
    3. purchase curr & amount (eg. IDR 8,345,545,500)
    4. sale currency only (amount system will auto calculate) USD
    5. rate field = 11.553
    6. spot rate will auto pick up from rate
    7. value date
    8. contract date
    upon TBB1 no error. posting log as follows:-
    FX1000+ : 40 8,345,545,500 IDR bank GL acc
                    50 8,345,545,500 IDR clearing acc
    FX2000- : 40 722370.42 USD clearing acc
                   50 722370.42 USD bank GL acc
    but upon TPM18 error occurred as follows:
    DBT_C009 - GL not maintain in acc symbol 5.3.4
    DBT_E039 - no posting spec assigned to update type
    DBT_B018 : 40 0 USD, 431,977,511 IDR gain/loss
                       50 0 USD, 431,977,511 IDR clearing acc
    so, after maintained DBT_C009 as follows still error for DBT_E039:
    40  0 USD, 38 IDR clearing acc
    50  0 USD, 38 IDR P&L gl acc
    what i don't understand is how system calculate and get DBT_C009 & DBTE039.
    what is the function of TPM18?
    thanks.

    Hello Prarnod,
    I have done the first node only for actuals that come from the integration to the internal order.
    I have tried setting up 2 and 3 even though the 3rd one does not make any sense to me
    Thanks,
    Paul

  • How system calculate exchange rate for two currency vise versa automaticaly

    Dear All, i have maintain exchange rate type M with USD to PKR with different time interval. When i run Project System report the system show transaction figures in Controlling Area currency is PKR. However, when i switch to USD currency with translation key (Mean rate as of today) . System do not allow to show the result.
    I know if i maintain exchange rate type M with PKR to USD then system display the result. But my concern is that system should automatically calculate exchange rate from PKR to USD for exchange rate M if as i have already maintained exchange rate m with USD to PKR.
    How system can do it?
    regards
    Saqib Usman

    Hi SAQIB USMAN ,
    Please set  the indicator for INV in OB07 for the exchange rate type M.
    This indicator might not be set in your case.
    Then system calculates using inverse ratio.
    Please read it for your reference and easy understanding
    Indicator: Calculation allowed with inverted exchange rate ?
        Indicator that in the case of a missing exchange rate entry in the system
        for the required translation from one currency into another, the inverted
        exchange rate relationship may also be used.
    Example
        If an entry is missing for the translation of USD into DEM in the system,
        then the translation takes place by means of the entry for the
        tranlsation of DEM into USD, providing the indicator is set.

  • How system calculate Exchange Rate for material?

    I have some doubt how system calculate exchange rate for material when doing GR.
    For example, standard price of material is 0.01 USD per ea. PO is created in foreign currency (THB) with qty: 40,000 ea (THB 2,852.00)
    Actually when I do GR ea then accounting doc is:
    Dr. Inventory 400 USD (12,800 THB)
       Cr. GR/IR    88.64- USD (2,852.00- THB)
       Cr. Variant 311.36- USD (9,948.00- THB)
    for 2nd and 3rd line item, exchange rate M (THB -> USD) is 0.03108 which is correct.
    Could anyone advise where system get exchange rate for 1st line item?

    Hi
    First of all, as mentioned by you, the exchange rate for Item 2 and 3 is not 0.03108.. It is as below, based on the figures given by you...
    Dr. Inventory 400 USD (12,800 THB)........ Exch rate is 0.03125
    Cr. GR/IR 88.64- USD (2,852.00- THB)....... Exch rate is 0.03108
    Cr. Variant 311.36- USD (9,948.00- THB).... Exch rate is 0.0313
    I guess the item 3 is just a derivation from Items 1 and 2.. The Price diff results as a difference between std cost and purchase price...
    I believe, the exchange rate would have been 0.03125 at the time of GR... You need to check this in your system... For sure, it uses  exch rate type M in the standard... Check if 0.03125 (USD -> THB) or 32 THB -> USD exists in your system at all
    Item 2 is based on your PO negotiated rate...
    Regards
    Ajay M

  • How does the system calculate the Taxes?

    Dear all friends,
    How does the SAP system calculate the Taxes?
    pls. explain with the example will be highly appreciable.
    thanx in advance to all
    best regards,
    Rajesh

    Hello
    The SAP system calculates tax based on the tax calculation procedure assigned to your country in OBBG.
    The tax calculation procedure is similar to the pricing procedure in materials management.
    As you have different pricing elements like gross price,discounts,freight charges, etc in pricing procedure, you will have different tax elements like Excise duty,Special excise duty,Cess,Edu cess,VAT,CST, etc in tax calculation procedure.
    At the time of PO creation, the tax base amount is communicated to the tax calculation procedure from the pricing procedure.
    And the tax values are calculated based on that and how you have configured your tax calculation procedure.
    In CIN, we have two tax calculation procedures
    TAXINJ which can be formula based or condition based and TAXINN which is condition based.
    In TAXINN, the tax percentages are picked from the condition records maintained.
    But in TAXINJ, it can be either from the condition records or the tax % given in the tax codes in FTXP. It depends on how you configure your system.
    Hope this helps
    Regards
    Gregory Mathews

  • How does the system calculate nondeductible taxes?

    Dear Gurus,
    How does the system calculate nondeductible taxes?
    Thanks..

    The sytem calculates the Taxes based on the Tax rates maintained in a tx code, the Caluctaion is based on the taxing procedure assigned to the Country.
    Non deductible tax is identified based on the Account key assigned to the Condition type in the Taxing procedure.
    The Non deductible tax Account keys are
    NAV - Non-deduct.input tax ( This will distribute the tax into a new line item)
    NVV - Non-d.input tax dist ( this will Distribute to relevant expense/revenue items )

  • Overwrite the system calculated VAT - Condition Value with Inbound VAT Amou

    Hello experts:
    We have a following requirement in my customer for Inbound VAT Processing.
    We want to overwrite the system calculated VAT - Condition Value with Inbound VAT Amount
    Details :
    Aggregated sales Idoc ( WPUUMS01) is used here for posting the daily sale.
    Inbound pricing procedure is ZPOS00 ( copy of POS000)
    VAT is maintained with condition Type ZMWS. Using Tax Codes
    When idoc get posted system calculates the ZMWS and working fine.
    However we would like to overwrite this condition value with inbound condition value (from segment 5 of WPUUMS)
    Example :
    For Article A : inbound aggregated sales Amount= 100 INR and ZMWS is 10%( VAT code B1)
    Then system will calculate 90 INR revenue and 10 INR as VAT
    However due to rounding in POS system we may get from POS the VAT Amount =9.99 for example.
    Tisak wants to overwrite the condition value 10 INR with 9.99 INR.
    I will appreciate if anybody can suggest some approach or share experience if came across the same scenario (Tax condition type).
    Thanks and regards,

    Hi,
    Either you can use rounding in POS such that it round up for 9.99 to 10.
    And then in SAP pricing procedure you can use alternate calculation type as 16 or 17 (17 should be used with decimal point assigned to currency for rounding like 2 decimal for INR).
    doing this will also round the figure from 9.99 to 10 is SAP.
    Hope this solves your query.
    Regards,
    Ashutosh

  • Acquiring a signal from two separate DAQs at different rates at the same time

    Hi I am trying to setup a system where I need to build two separate arrays one from two separate sets of data. The data needs to be brought in at the same time, but at a different rate. One set is from the PCI-4472 and will come in at ~10Hz, while the other is from a SCXI-1102 that is connected one channel on a PCI-6070E at ~3-5Hz. I was wondering how to have the two be read at the same time, but at the different speed. I am using LabView 6.1. Thanks in advance.

    Hi Muheesh:
    Since your DAQ's are working at an exact multiple of one another, what you could do is fill alternate channels with some "DUMMY" data...like zeros. Then you could index the array and match it up with the faster card. It might seem like a waste of memory, but it will give you two sets of aligned data, which seems to be what you need. If you're operating them at some weird multiple, it's a bit trickier. Whatever you do, you're going to have to insert some bits somewhere. Look for a least common factor (LCF) of your sample rates, and see if you can divide by that before logging the data.
    Eric
    Eric P. Nichols
    P.O. Box 56235
    North Pole, AK 99705

  • How can I record several channels of data at different rates with the same card?

    I am building an application in which I need to record several channels of DC voltage data to disk at different rates, for example, Channel 1 at 40 Hz, Channels 3-5 at 10 Hz, Channels 6-8 at 1 Hz, etc.
    All these channels are time-referenced, so I need to make sure data for channels recorded at slower rates line up with their correct time stamp.
    Currently, I am building all data into a 2D array one row per loop iteration.

    Hello;
    At this time, the NI DAQ boards have only one scan clock, so, you can only define one valid scan rate for all of your channels.
    The better approach for you is to sample all channels at the highest rate you will need, and then discard the samples you don't need to save.
    Hope this helps.
    Filipe

  • How system calculate the required qty. after MRP RUN

    Hi,
    I want to know if we are using MRP Type as PD and also we are calculating automatic saftey stock and re order point qty. after MRP RUN according to which rule formula system calculate the safty stock, reorder point qty. and the required qty. as a PR.
    and if we are not using calculate safety stock automatically and if we set safety stock qty. manually in this case how system will calculate the required qty.
    regards,
    zafar

    please check the below links.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/b441a9a1b011d3a82d0000e82a3c24/content.htm\
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d256344af11d182b40000e829fbfe/content.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm
    please check the above links may get some idea.
    Regards,

  • CST% should calculated two different rate for C Form /  Without C Form

    Hi,
    How we can assign to one CST% condition against two different rates for C Form / Without C Form for same Plant/Vendor/Material.
    My scenario is, we have purchased the Material for one plant from Vendor, but Vendor has given the material against C Form or Without C Form not fixed.
    We have used to Plant/Material/Vendor Key combination for updating CST (JVCS) 2% condition through FV11. And created two PO for C Form 2% & second 5% Without C Form but it is showing 2% in both PO as per maintained in condition.
    When we have received the material against without C Form 5%, changed in CST (JVCS) condition 5% and do the MIGO and same think do for against C Form.
    How to resolve this type problem without changing?
    But it is possible in SD their maintaining Price Group; same is it possible in MM.
    Devendra

    Hi,
    1 .How we can assign to one CST% condition against two different rates for C Form / Without C Form for same Plant/Vendor/Material.
    As suggested by the Pankaj you need to create 2 tax code i.e. one with C form & other as Without C form having appropriate Percentage maintained in the condition record ( FV11 )
    My scenario is, we have purchased the Material for one plant from Vendor, but Vendor has given the material against C Form or Without C Form not fixed.
    We have used to Plant/Material/Vendor Key combination for updating CST (JVCS) 2% condition through FV11. And created two PO for C Form 2% & second 5% Without C Form but it is showing 2% in both PO as per maintained in condition.
    As you may have maintained single tax code with the 2% condition record so same % flows in both PO , Use 2 sperate tax code it will resolve the issue.
    Regards
    Mascot.

  • System message - Base document exchange rate cannot be used

    Hi!
    I need an Information ... when I use the function "Copy From" i get the Draft Document Wizard where i set "Use Exchange Rate from Base Document." But when I select "Finish" I get the following system message: "Basic Document Exchange rates can not be used, the rows will be updated using the exchange rate target document.
    Why??

    Hi
    at the sales front
    the exchange rate should be always as per the Posting date this is standard, how ever if you wish you can manually overwrite the defined exchange rate
    at the purchase side you define the system wether you want the exchange rate to be from based document or as per the posting date in choose  Administration -  System Initialization - Document Settings -> Exchange rate base date (A/P documents)
    hope i made my point
    sandeep

  • In Sales enquiary stage how system calculate EK02 condition value as cacula

    Hi
    In Sales enquiary stage how system calculate EK02 condition value as caculated cost
    Is there any cofig to get the value of EK02 condition for calculated cost at Enquairy stage only for forcasting
    Regards
    Santosh

    Hi,
    In our company we get the calculated cost into our sales document with the following configuration:
    IMG: Plant maintenance and customer service / Maintenance and service processing / Basic settings / Quotation creation and billing / ODP4 - Assign conditions to sales document types
    With this configuration, we assign the calculated cost condition (EK02) to the corresponding sales document. The system sends the calculated costs from the order to the corresponding sales order created.
    Regards,
    Óscar
    http://blogdesap.blogspot.com

  • Mail error "Verify that you have addressed this message correctly. Check your SMTP server settings in Mail preferences and verify any advanced settings with your system administrator.Select a different outgoing mail server from the list"

    The Mail application has suddenly started giving error:
    "Verify that you have addressed this message correctly. Check your SMTP server settings in Mail preferences and verify any advanced settings with your system administrator.Select a different outgoing mail server from the list"
    It was working fine till yesterday, suddenly it stopped. I have 3 email accounts configured here, 2 are on exchange servers and one yahoo. Connection verification works and shows all servers as green.
    Any inputs?

    I had 3 accounts, 2 ms exchange accounts and 1 yahoo. After removal of yahoo, everything is back to normal.
    Regards
    Rohit

  • How does the system calculate taxes?

    Dear All,
    How does the system calculate taxes?
    Can anybody explain in detail how the values will flow from PB00 / PBXX to BASB ?
    Is this flow will remains same in both deductible & non deductible taxes ..??
    Pls explain
    With Regds

    Hi
    Just remove the base type 362 in the taxing procedure & check if your tax is calculating or not.
    The Tax determination still works.
    FORM FRM_KOND_BASIS_362.
    *Application country specific
    *This alternate base value is to be attached to BASB. This routine
    *fetches KZWI6 captured in the pricing procedure.