Third Party Processing

We have been using the Third Party Processing process, where a billable sales order is entered (item category TAS) a purchase req created, and converted into a PO, invoice verification is done, and then the billing is done . . . Sales order closed once all billing done.
Now we are being asked to use the Third Party Process but with free sales orders.  Also based on the type of sales order, the GL account and Cost Center may be different.
Today when we ship a free Demo, when the delivery is goods issued it hits a finished goods account and an expense account.
Today when we do a TAS order the PO shows a Cost of Sales Account, the Invoice Verification hits the AP account and the Cost of Sale account, and the Billing doc hits the AR account and the Expense account.
What I have done so far is create a new Item Category what is similar to the Free Item Category we have been using . . . it is not relevant for pricing or billing . . . yet also similar to TAS.
When I create the order, I do get a purchase req, which is type NB with Account Assignment Category of Z.  The GL account, which is a Cost of Sales account defaults . . . this must be in configuration, and it is grayed out.  The cost center from the Sales Order does come into the Req.
The Third Party Process was set up by consultants 11 years ago, and we have never had to do anything to change it, so it is a new area to us.  So can anyone provide steps to continue the set up of this.  I am thinking if the we could change the GL to an expense account we might be closer to it, but I am not sure.  Or should a new Account Assignment Catergory be created.
Any suggestions would be appreciated.
Edited by: Diane Thacker on Jul 17, 2009 4:53 PM

So it sounds like you are doing Free Third Party Order Processing, but I am not clear on what you have written.
Are you saying it sounds like what I have done with  item and scheduled line is correct?  Or do you need to understand further what I have done?
Also I think you are saying we can create a PO where we can assign a GL without a cost element . . . How is that possible?  Is there a setting in configuration that allows for this situation that you can enter the GL you want?
Also, if this is possible.  Once we create the PO, and then do the Invoice Verification . . . will the sales order automatically close or is there another step to close the order . . . since no billing to close it?
Thanks!

Similar Messages

  • Logical GR in Third Party Process

    Hi Friends
    There is logical GR involved in third party process. What if we do not want to trigger it?

    very useful thraed for your Qn-
    [stock not updating after doing MIGO (gr) for third party sales |stock not updating after doing MIGO (gr) for third party sales;
    BR
    Raj

  • Free of charge third party process.

    Dear Gurus,
    I want to create a sales order with a third party material with zero price, create a PO and invoice the PO with zero value.
    Could you please tell me how this can be achieved and what are the necessary settings in config to be changed?
    Thank You
    Kumar

    Hi Kumar,
    the third party process is as follows:
    1.Customer will order the material from the Company X.
    2.Company X will not have stock of the material.
    3.Company will raise a PO for the material to the Vendor & asks the Vendor to deliver the material to the customer.
    4.Vendor will directly deliver the material to the customer & will send the invoice to the Company X.
    5. Company X will then raise a invoice to the Customer wrt on the Sales order.
    Create a Sales order with item category TAS, Schedule line category CS(standard).Once the SO is saved, go to the change mode of the SO, go to Schedule lines tab, & note down the PR number.
    With reference to the PR, create the PO & then MIGO and MIRO.
    Then create the invoice wrt the SO.
    Let me know if you hav any problems.
    Regards,
    MP

  • Credit Check with Third Party Process

    Hi Gurz,
    I know about third party process but my problem is with credit check of the customers.
    If customer has not got enough credit limit to process the order in normal senario credit controller has to manually release the order as system blocks it. In third party process system will give you warning message when saving sales order about customer credit limit but allows you to save sales order. Once saving sales order it authomatically creates Purchase Requisition. From PR purchasing creates P.O. with out knowing about customer credit limit issue. and so on. In other words goods supplied to customer even though credit limit has exceeded. This user don't know untill raising the invoice to the customer which is too late.
    Can we stop creating Purchase requisition or block purchase requistion for credit check ? or there are better way of handling the process for credit check?
    Thanks in advance

    Hi,
    Try to implement OSS note -738171 - Delivery block does not influence purchase requisition.
    Following is the details of the note;
    Summary
    Symptom
    The delivery block in a sales order does not prevent the generattion of the purchase requisition in a third-party or individual purchase order item. Regardless of the Customizing settings in the delivery block, the system confirms the TAB or TAS item and generates the purchase requisition.
    More Terms
    Order, purchase requisition, PReq, TAB, individual purchase order, individual purchase order item, TAS, third-party, third-party item, SD order, delivery block, VBAK-LIFSK, VBEP-LIFSP
    Cause and Prerequisites
    Solution
    Create a user-specific user requirement (for example, 902: BEDINGUNG_PRUEFEN_902 in Include LV07A902) as a copy of standard user requirement 102 and assign it to requirement 'Preq' by using Transaction OVB5.
    In the source code of the user-requirement, program a check for the delivery block which, if necessary, triggers an ERROR_EXCEPTION which prevents the generation of the purchase requisition.
    You can use the existing check for the credit block as a template.
    Regards,

  • Third Party Process and Inventory

    We are using the SAP function "Third-Party Processing". We are using the function in it's standard (SAP R/3 4.7).
    The auditor now has the following issue: Shipping the goods starts after paying the goods. Out of this, while shipping the goods, we are the owner of them. In this circumstance the ship is our warehouse.
    SAP does not allow an Inventory Management within Third-Party Processing:
    "Since a third-party order involves a movement from the vendor direct to the customer, Inventory Management is not in any way affected. If you wish to document the movement in the system, however, you can create a goods receipt for the third-party order."
    With the SAP functions in this scenario it is correct that the warehouse stock is not being impacted. This is a conflict with the opinion of the auditor.
    Let me explain in detail what is wrong out of the view of our auditor:
    For example we initiated the order of a customer in June and we have paid the goods in June. The shipment starts in June and the goods will arive in July. Due to the fact, that we are the owner of the goods on the ship, we have to increase the stock. This is the opinion of our auditor.
    Does any body know, how to solve the issue? How do you manage Third Party Processing & Inventory?

    Some auditors just dont understand the SAP process. Instead of talking to weak users, they should talk to SAP directly.
    What about shipments from standard sales orders that are shipped end of June and do arrive at the customer in July?
    When do you bill your customer? when the goods arrives there, or earlier? Depending on the Incoterms you may still be the owner until the truck is unloaded.
    If you change your process and post goods receipt to your warehouse, then you show inventory where no physical inventory is, you posted a goods receipt without a physical receipt. I am sure the next auditor will not allow such therotical process.
    Get together, IT consultants of FI and MM and SD, strong business people for the same modules and the auditor, and discuss and find an optimal solution.And let the auidor sign the decision paper!!! Very important, I recently had to convice German auditors because they had different opinion than the Australian and US auditors of the same auditing company (and the issue had nothing to do with local legal requirements).

  • Third party process with Valuated sales order stock

    Hi All,
    We have third party sales order process with valuated sales order stock. The problem is that in the theird party PR which is triggered directly from the sales order it determines a stock account which is assigned to the BSX key in OBYC.
    But since this is third party processing as per my understanding a consumption account assigned to key GBB-VAX (since account assignmnt category is X) should get determined, so that when the GR is done against the PO a consumption posting is done in the background.
    I am not able to understand if the system is determining the stock account due to the fact that it is valuated sales order stock and if so, what should happen after GR. Should we have a stock created for the material which is physically directly delivered to the customer?
    Regards,
    V S

    Hi,
    Check GBB-VKA which is defined in OME9 for your ''E'' Account Assignment Category that SAP will debit upon GR posting
    Also check "X" GBB-VAX and the G/L account assignment in OBYC
    The posting on GR should be debit KBS -Credit GR-IR
    Thanks
    Diwakar

  • Third Party Process - forcing PO creation after error

    Hello eveybody,
    I am implementing the Third Party Process and everything is going well but I have a question. If I enter say 10 items on a sales order and one material does not have an info record/source list then that item does not get entered on the purchase req. This then blocks the automatic creation of the PO.
    If I fix the problem material and re-enter it on the SO, then that item gets ordered but the other 9 are not processed. Is there nany way to force the PO creation for the other 9 items ??
    Many thanks in advance.
    Brian

    Hi Stanton,
              When you precess the third party order the purchase requesition will be created to the respective schedule lines so you can get the two different purcahse requesition for the 10 items then you can combine those two purchase requesitions in the purchase order what is the issue.
    or you can run another PO for that problem item.
    I hope it will not give any problem while creating PO
    Thanks,
    Murali.

  • Third Party Process ASN

    We have configured a third party process for specific sales orders.  We receive an inbound ASN with shipment information and then we create the outbound invoice, directly from the sales order, after we post the inbound invoice.  Is it possible, and how, to create an outbound ASN, from our system to the end consumer, based on the information in the inbound ASN?  We would prefer not to create an outbound delivery document in our system and would like to generate the outbound ASN off the outbound invoice or the original sales order.
    Thanks for the help.
    Chris

    We have configured a third party process for specific sales orders.  We receive an inbound ASN with shipment information and then we create the outbound invoice, directly from the sales order, after we post the inbound invoice.  Is it possible, and how, to create an outbound ASN, from our system to the end consumer, based on the information in the inbound ASN?  We would prefer not to create an outbound delivery document in our system and would like to generate the outbound ASN off the outbound invoice or the original sales order.
    Thanks for the help.
    Chris

  • Third party process as inventory value

    Dear Experts,
    Kindly need help for third party process.
    We have third party process which triggered from Sales Order. This Sales Order will automatically created PR. PR will be convert into PO.
    The issue is we would like to have goods in Sales Order (or Purchase Order in next process) as inventory value when receiving goods.
    Can third party process be treated as inventory value when receiving it?
    Thank you in advance.
    Best Regards,

    In third party process your customer gets the goods directly from your vendor.
    You only make a statistical GR ("phantom" GR) in the system, the goods are physically received by your customer and your customer's inventory will increase after your customer's GR and not yours. Knowing this your question doesn't make any sense I think.
    If your third party process is not a real third party process and you receive the goods physically and after that you sell it your customer you can use individual PO scenario.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/dd/5601d4545a11d1a7020000e829fd11/frameset.htm
    Regards,
    Csaba

  • Third party process - error

    Dear all,
    In the third party process, have we to create outbound delivery?
    I have created PO from PR of  a third party sales order. And now, i don't understand to delivery to customer.
    Pls tell me solution.
    If we have to create outbound delivery from that sales order, i get errors:
    Item category TAS is not defined and Item category TAS is not defined, so item 000010 will be disregarded. I also checked in VOV4, VOV6, VOV7.
    Thank you,

    Hi
    In third party scenario the material is delivered to your customer thro out side vendor
    You are billing your customer
    Vendor is billing you for the material he has delivered to your customer
    Here we dont make any delivery
    Process Flow for 3rd Party Sales
    Customize the third party sales in summary:
    1. Create Vendor XK01
    2. Create Material u2013 Material Type as "Trading Goods". Item category group as "BANS".
    3. Assign Item Category TAS to Order type that you are going to use.
    4. A sale order is created and when saved a PR is generated at the background 
    5. With reference to SO a PO is created (ME21N). The company raises PO to the vendor.
    6. Vendor delivers the goods and raises bill to company. MM receives the invoice MIRO 
    7. Goods receipt MIGO 
    8. Goods issue
    9. The item cat TAS or Schedule line cat CS is not relevant for delivery which is evident from the configuration and,   therefore, there is no delivery process attached in the whole process of Third party sales.
    10. Billing
    SD -  3rd party sales order Create Sales Order
    VA01
          Order Type
          Sales org, distribution channel, div
          Enter
          Sold to
          PO #
          Material
          Quantity
          Enter
          Save
    SD -  3rd party sales order View the PR that is created with a third party sales order
    VA01
          Order Number
          Go to Item Overview
          Item ->Schedule Item
    SD -  3rd party sales order View the PR that is created
    ME52N
          Key in the PR number
          Save
    SD -  3rd party sales order Assign the PR to the vendor and create PO
    ME57
          Key in the PR number
          Toggle the "Assigned Purchase Requisition"
          Execute
          Check the box next to the material
          Assign Automatically button
          Click on "Assignments" button
          Click on "Process assignment"
          The "Process Assignment Create PO" box , enter
          Drag the PR and drop in the shopping basket
          Save
    SD -  3rd party sales order Receive Goods
    MIGO_GR
          PO Number
          DN Number
          Batch tab , click on classification
          Serial Numbers tab
          Date of Production
          Flag Item OK
          Check, just in case
          Post
          Save
    SD -  3rd party sales order Create Invoice
    MIRO
          Invoice Date
          Look for the PO , state the vendor and the Material
          Check the box
          Click on "Copy"
          Purchase Order Number (bottom half of the screen)
          Amount
          State the baseline date
          Simulate & Post
          Invoice Number
          *Invoice blocked due to date variance
    SD -  3rd party sales order Create a delivery order
    VL01N
          In the order screen , go to the menu Sales Document , select "Deliver"
          Go to "picking" tab
          State the qty and save
    SD -  3rd party sales order Create a billing document
    VF01
          Ensure that the delivery document is correct in the
          Enter
          Go to edit -> Log
          Save
    Hope the process is very clear to you now
    Regards
    Raja
    Edited by: ramanathan raja on Sep 18, 2008 3:06 PM

  • Third Party Process Issue

    Hello Friends,
    Need Your Inputs for below issue"
    in third party process: SO is created with 2 line items, -->PR-->PO--> Vendor delivers only 1 item and MIRO is done for it,
    But
    During Creation of Customer invoice Both Line items are considered in the Invoice(F2)
    1st line item with the Value of X Rs,  and 2nd Line item with zero value ( as there is no delivery done to customer and hence no invoice via MIRO)
    Requirement is:
    The 2nd Line item should not be considered at all during Customer invoice creation.
    Item cate used is TAS with billing relevance F (i,e standard config)
    Kinldy help
    regards

    hello srinu..
    SO is created with 2 line items, PR is auto created. 1 PO is created (with 2 line items)
    MIRO is done w.r.t PO line item 10 only,
    then when i create customer invoice from SO i get 2 line items, for 1st line item there is value populated. 2nd line item has zero value,
    The requirement is that if there is no Processing of SO for line item 2 ,, then it should not be populated in the customer invoice.
    Regards

  • Third Party Process in Materail Management (No SD)

    Hi,
    Our Business would like to outsource the Stationary materials to supply the required materials directly to requester.
    I believe the best possible solution for this requirement is to implement third party process in Material management as we do not have SD Module.
    In this scenario, which material type we need to use (Item category group, Field ref, Sref material type and field ref) and the config part.
    Secondly, does it have any effect on MRP, Stock levels? Also please explain the process involved in Goods returns
    Appreciate, if you could share your experiences.
    Regards
    Kumar

    Creating a Third-Party Item Manually
    To enter a third-party item in a purchase order without an SD order or purchase requisition, proceed as follows:
    Enter a third-party item manually in the same way as the purchase requisition.
    After entering the account assignment, you receive a screen in which you can enter the address of the sold-to party.
    Enter either the customer number or a delivery address.
    Check whether goods receipts can be made for the third-party item. Goods receipts are possible if the goods receipt indicator is set in the item.
    Save the purchase order.
    Setting the Goods Receipt Indicator
    The account assignment category X in the Customizing system of Purchasing determines whether a goods receipt can be posted for a third-party item. Here you define whether a goods receipt is possible, not allowed or compulsory.
    If a goods receipt is possible, the GR indicator in the purchase order item is changeable. When you enter the purchase order, you decide if a goods receipt is to be posted or not.
    Mat Type can be use ROH or Trading
    For Return you can do return to your plant or ask vendor to pivk and replace the goods or issue the creadite to customer and take from vendor

  • Third party process in MM

    Hi friends,
    i need all your help in configuring third party process in MM.please guide me by giving step by step process with t-codes.
    your advise is considdered more valuable.
    Regards,
    william

    Hi,
    Process Flow for Third party process with SD-MM Integration
    Customiztion requires is
    1) Defining the Purchasing org,Purchasing group,
    2) Assign the Purchase org to company code
    3) Assign Purchase org to plant,
    Material type used should be Trading goods -- HAWA
    1. Create Vendor XK01
    2. Create Material with  Material Type as "Trading Goods" & Item category group as "BANS".
    3. Assign Item Category TAS to Sales Order type
    4. Sale order is created and in the background a PR is generated
    Note down the PR number along with Sale order no
    5. With reference to PR a PO is created (ME21N).
    PO will be sent to the Vendor with delivery address as your Customer.
    6. Vendor delivers the goods to the Customer and raises Invoice to the Plant. 
    7. Goods receipt MIGO & stock update in the Plant ( Not physically)
    8. MIRO for Vendor to clear the Payment
    9. Create the outbound delivery for sales order
    10. Post Goods issue for delivery
    11. Billing for the customer
    rgds
    gsc

  • Ship to party and vendor relation in third party process

    Hello Experts,
    I need your precious suggestions on my business requirement.
    When we create the third party sales order system creates the Purchase Requisition and further PO is created through purchasing department.
    Suppose in my third party sales order I have two items X & Y, and both need to deliver at two different ship to party XXX & YYY respectively. in order system determine plant 1000 for both materials based on plant determination (CMIR >> CMR >> MMR) and system generates PR.
    I know while converting the PR to PO system check Source list (ME01) to determine the vendor. my requirement is I want to determine Vendor based on ship to party in sales order. suppose ship to party locations for XXX and YYY are Bangalore and Pune respectively and in both place we have different vendor. Both vendor manufacture product X & Y. so I want system should pick the vendor according to ship to party.
    Is there any relation between ship to party and vendor which will work in third party processing ?
    Kindly explain how I can achieve this requirement.
    Thanks,

    I doubt this can't be achieved by SAP standard functionality. You may need to use user exit. Check Third party to purchase req user exit or purchase req user exit to fulfill the requirement.
    Regards,

  • Delivery date should be confirmed in third party process

    Dear Experts,
           I have one doubt in third party process i.e., while creating sales order how can we confirm the delivery date because here vendor deliver the goods to customer but if customer is asking for delivery on a particular date then how can we assure him the delivery date is there any tracking in standard or how to solve this requirement.

    Dear Venkatesh
    In the third party Process, the Vendor will deliver the goods. That is correct. so as per my experience the delivery dates will get copied to Sales order ----- PR ----then PO. Then the vendor will also deliver the goods on the date which is mentioned copied into PO only.
    Also refer to the below link to gain complete knowledge to clear your doubt.
    http://help.sap.com/saphelp_scm700_ehp02/helpdata/EN/c1/42c95360267614e10000000a174cb4/frameset.htm
    Thank you
    Srikanth

  • PO based billing in third party process

    How can the Sales Billing be based on the PO net price in a third party process?
    The copying requirements are set up with price source A = Purchase Order
    And the pricing type is = C (copy manual and redet. others)
    The billing quantity is = E (GR based)
    ...but still the billing net value seem to be taken from the sales order and not from the PO?
    We want to bill the customer whenever we have done partial goods receipts for the PO item.

    hi,
    in standard you have only limited possibilities (it's working only for VPRS).
    Let's say your condition is PR00 in the PO. If you wan't this in your billing document, you have to have it in your pricing procedure in the same line, with the same name and same text:
    PO
    n. 1. PR00 standard price
    invoice
    n. 1. PR00 standard price
    Balazs

Maybe you are looking for

  • Replaced Hard Drive--How Do I Get My iTunes Account Back?

    Hi all, My hard drive melted down. Because it had corruption on it, I couldn't simply transfer the system to the new drive and have had to reinstall software from discs and drag my data over from my external backup. I have done that with iTunes too,

  • M575 LaserJet Color MFP eprint PROBELM

    Hello Everybody, I have the printer M575 Color MFP LaserJET and I have a problem with enable the ePrint on HP Web Services tab. I click the green Enable button but it show me an error: Unable to connect to the site HPConnected.com. The product is not

  • How can I get more storage on my iPhone 5?

    I have an iPhone 5 with the smallest amount of storage. I'm not sure exactly how much I have, but I keep filling it up and am often finding myself unable to download apps, music or take videos. I don't t want to delete anything from my phone, but I w

  • Newbie in Solaris

    hye all .. i'm new with this new solaris server . is there any specific language i need to master in order for me to operate the server . my company is using solaris 9 platform . if there is any god book for me to read please do suggest .. thanks all

  • How can I automatically associate infotype 4005 to a internal applicant?

    Hi everyone, I'm new in HCM and I need a hint. In the recruitment process, my client needs to compare the employee's salary to the position's pay grade. To do so, the internal applicant has to be associated to the infotype 4005. I'm using infogroup t