Transfer Order Status Issue

Hi All.
For the delivery we are Creating the Transfer Order using the Transaction LT03 . Currently we are having issue with Transfer Order status.When we look the document flow for the transfer order, TO status reads as "Completed" instead of "open" whereas deleviry status is still in "being Processed" status.
Please give me the solition , why status goes to "Complete" status instead of "Open".
Thank you,
Cha
Edited by: Chabalan on Oct 5, 2011 10:57 AM
Edited by: Chabalan on Oct 5, 2011 11:00 AM

Hi Cha,
I thought it is a one-off issue.
You mean the TO is not yet confirmed using LT12 but status already shows complete?
Delivery is in correct status as the pick/pack and PGI steps are not completed..but for TO status, if it's confirmed then it should be complete.
Pls confirm what's your scenario?
Regards,
Raghu.

Similar Messages

  • Transfer order cancellation issue

    Hi Experts,
    User created transfer order 10 line items,9th and 10th line items not confirmed its in red colour error status all other line items are green ,now my user
    trying to cancel 9th and 10th line item through LT15 transaction that time showing error transfer order already confirmed or cancelled,please any body suggest me how to cancel 9th and 10 th line items,Tried through LT0G transaction reversal through delivery,unable to reversal also because my deliver is deleted,
    Regards
    Mohan

    Hi,
    When using LT15, enter the item numbers along with TO, then it should allow you to cancel.
    Let us know if you need any more help.
    Regards
    Vijay

  • Transfer order print issue

    Transfer order label of building A are printed automatically in building B instead of building A. how to check why it is happening, data avaialble is Process order number and transfer order number." what are the steps to select the right printer?

    for answer: Printing process order issue
    tcode : OMLV

  • 3rd Party Order Status Issue

    Hi Guys,
    In a 3rd party sales scenario, order status becomes complete even when it is partially invoiced. for example order qty is 4, PR created for 4 qty, PO created for 4 qty, MIRO is done for 2 qty, Customer Invoice is done for 2 qty. At this situation, the order status goes to complete. When I do a MIRO for the remaining 2 qty, the order status becomes being processed and when I create invoice for the remaining 2 qty, the status becomes complete.
    Question here is, is there a way to prevent the order from getting into complete status before it is fully invoiced?
    Let me know guys.

    Hi,
    You cannot achieve this using standard customizing, as for thord party the billing quanity is always proposed against MIRO and the logic is that after partial delivery/invoicing by supplier, the sales order becomes completed. If you expect partial deliveries )or you have planned them with the supplier), you need to split the sales order qty into separate items according to the actual delivery date by the supplier.
    Regards,
    Marcin

  • Purchase order status issue

    Hi Everyone
    I am having an issue with the status of Purchase order. When the Purchase order has single account assignment, everything is fine. But when I create a purchase order with multiple account assignment, the first line item is correct but when I ad second line, the still to deliver quantity gets added correctly but the amounts only reflect the recent item and not the previous one.
    For example:
    Item 10            Quantity 10           
    Item 20            Quantity 10         CC xxxx         GL account 666666
                                                       CC yyyy         GL account 666666
    Status:    Ordered        20              200
                    Still to deliver 20             100
    Please help me with this issue.
    Thanks,
    Shalu
    Edited by: Shalu G on Feb 9, 2010 12:07 AM

    Resolved myself

  • Internal Order status issue Error - Message Class X short dump

    Hi All Experts,
    I am creating internal order with CRTD status. However when I am trying to post transaction through MIRO , I am getting ABAP short dump mseeage class X. So I changed the CRTD to REL manually and able to solve the error.
    But could any expert help me what is the logic behind this CRTD , REL, LKD etc ?
    Since I am reading help.sap.com also as well but simple word help will be appreciable !
    One more can we,
    1 ) Create Internal Order with the REL status directly ?
    2 ) If YES where configuration needs to be done
    3 ) Will it hamper any business process ?
    Exprts guidance will be appreciable.
    Regards,
    Sharvari Joshi.

    Hi,
    All Masters,
    Eli - Thank you for your answers.
    Lawrence - Thank you for simple word that is what I was looking for.
    Can anybody tell me how can we create IO directly in LKD status ? Or it is manual acitivity by clicking on Set / Rest button and then check LKD and save. I tried in KOT2_OPA but not no any option found. If any experts can guide for the following configuration would be great.
    1 ) Is it possible to create IO with LKD status directly ?
    2 ) Where that configuration needs to be done ?
    3 ) What is significance of JEST Table relating to Internal Order ?
    Exprerts help would be great !
    Regards,
    Sharvari Joshi.
    Edited by: Sharvari Joshi on Dec 3, 2010 11:52 AM

  • Sales order status issue.

    Hi,
    if we make delivery reference to a order the status of the order is showing complete.. but my requirement is this until billing is gettign completed order should remaik open or in being process status. Where can i make this settings..
    Please help.
    Supratip

    Hi Supratip,
    Use Completion rule B in item category.
    Regards,
    Prashant

  • Transfer Order printing issue

    Hi, log. executioners )
    I've faced such an issue while printing TO via standard WM print functionality.
    TO was created for moving batches which has no SLED maintained in it's master and printed using form LVSTSOLO. SLED was missing in a document.
    I specified required data in a batch master, and tried to reprint TO. But SLED in paper slip is still missing in the print document.
    As far as I have understood, the print tables (the data for printing SAP Script forms is taken from) are filled while TO posting only, but not while print program run. So changes in linked objects have no influence on that data.
    Am I right? And is there any possibility (some kind of a background job or smth) to update print tables after changes were made?

    Hi Guys
    Unfortunately I do not think that you will get an answer now. Either your question is not simple or we do not know the answer.
    So in the interest of keeping the Forum tidy and easier to surf through could you please close your thread and either try one of the other forums or try another post. I do not think that most people will bother to look this far back anymore.
    Sorry I cannot help as I would if I could.
    Regards
    Frenchy.

  • Cancel Transfer Order

    Hi,
    I am looking a way to cancel the two step confirmation TO.
    I have completed one step, ie. pick confirmation is done, but now I want to cancel the TO, while cancelling TO through LT15, system is saying that it is already confirmed or cancelled.
    Is there any way to cancel the pick confirmation and process further.
    Very urgent
    Thanks in advance
    Deejay

    Hi, All
    Sorry to involve in this issue.  Because similar problem am facing at my client place.
    My transfer order status is completed and it is required to cancel the delivery (no PGI done).
    As per the expert below suggestion :-
    `Since step 1 is already confirmed, you canot reverse it. You will have to move the material back with LT01 movement 999.`
    Created transfer order using LT01 and movemente 999, but no luck and i am not ablve to delete the delivery items.  If am trying to remove batch qty in the delivery for deleting, SAP says that `Picked quantity is larger than the quantity to be delivered`
    Hi Deejay
    If you able to resolve this issue please let me know and help me to reslove it.
    Regards
    Srini

  • Issue at the time of creation of transfer order for inbound delivery

    Hello,
    I am facing one issue at the time of creation of transfer order for inbound delivery.
    If I create inbound delivery for purchase order with account assignment as 'M' (Ind. cust. w/o KD-CO), inbound delivery is not updated. Also document flow for inbounde delivery s not updated. I can create N number of transfer orders for on inbound delivery. Need help to resolve issue.
    If I create inbound delivery for purchase order with account assignment other than 'M' (Ind. cust. w/o KD-CO), inbound delivery and document flow is updated.
    Thanks and Regards,
    Nikhil

    Hi
    In OMS2 t-code
    for your material type and  plant ,you have to mark value based and qunaity based updation mark
    Regards
    kailas Ugale

  • Automatic goods issue for outbound delivery, during the transfer order confirmation

    Hello,
    Could you please advise how to realize automatic goods issue for outbound delivery, during the transfer order confirmation in the WMS.
    Now after creation of outbound delivery, i can't post the goods issue. Before i have to make the transfer order and confrim it and only after this i can post the goods issue in the VL02 t-code.
    Could you please advise - what i have to customize that to make automatic GI for outb. delivery (i mean with creation material document) during the TO confrimation.
    Thanks in advance.

    Hi Iiya
    Check the below setting, might be helpful

  • Issue with Transfer order after inbound delivery

    HI SAP Experts ,
      we have an issue where User inputed the Inbound delivery and then assigned with Handling Unit and then he has Created the Transfer order and which he has confirmed
    later he has Unassigned Handling Unit , know how can he  Proceed further
    Case   1) I believe he has deleted the Inbound delivry also , How then the Transfer order Movements can be    reverted
    Case 2) inbound delivery exist in system , in unassigned state wrt Handling unit and Transfer order (Confirmed )also exist , if user Tries for vl09 for Reversing Delivery , system throws error , Reversing not possible -What should be done here
       Awarded Full  Points for correct answer
    Thanks and Regards
    Adarsh

    Hi
    You use LT01 with the reverse movement (1 or 10 higher than the  production receipt - standard SAP uses 103 fro GR and 104 for the reversal).
    You then want to unprocess the transfer requirement if existent (look up the TR number in the TO header)
    And cancel  VL09 and then TA LT0G

  • WM - Confirm Transfer Order - and automated Goods Issue posting

    Hi
    We operate Warehouse Management, on the Sales Process that has been implemented, we have standard sales order, delivery with a transfer order created in WM, when the TO for the delivery is confirmed in WM (tcode LT12) this usually automatically creates the goods issue in MM.
    However sometimes the Goods Issue in MM is not created automatically, I can see no immediate reason why, and if the Delivery is brought up in VL02N, and 'Post Goods Issue' option chosen it goes through fine without any probs.
    Any ideas welcome on what I should be checking to track the problem?

    There is no background job that is producing the Post Goods Issue in this instance after the TO is manually confirmed in LT12.   My issue is that usually the PGI happens automatically from the TO being confirmed (not by a background scheduled job), but in some instances it does not. 
    It is the latter problems I am trying to trace, as when the PGI is not automatic from the TO confirmation, we are able to goto VL02N (Change Delivery) and issue a PGI without an error.  The problem is that this is an extra step, I wish to trace why it is not automatic from the TO confirmation like in 98% of cases in our setup. 
    There is defintely no background job scheduling PGI, I am aware of the RVV50L21 program which can be used to schedule background jobs for PGI, as we use this on another Sales Org (where WM is not used), but it is not scheduled for the Plants/Shipping Points regarding my TO/auto PGI issue.

  • Status of transfer orders

    i have a delivery document
    if i see the document flow of that delivery document
    i found there are 4 WMS Transfer orders
    in that 4 transfer orders
    2 are with status completed and 2 are with status open
    in my report i need only transfer orders with status 'OPEN'
    which table i need to refer for this
    if not tables how can i get those open orders

    Hi,
    You can get the status of all your transfer orders from the table LTAP. In that there is a field called confirmation which will tell u whether the TO is confirmed or not.
    Also you can see all your open TOs using the transaction LT23.
    Reward, if helpful..
    Thanks..

  • Status of the transfer orders

    i have a delivery document
    if i see the document flow of that delivery document
    i found there are 4 WMS Transfer orders
    in that 4 transfer orders
    2 are with status completed and 2 are with status open
    i am an ABAPER
    in my report i need only transfer orders with open status
    which table i need to refer for this
    if not tables how can i get those open orders

    Hi,
    You can get the status of all your transfer orders from the table LTAP. In that there is a field called confirmation which will tell u whether the TO is confirmed or not.
    Also you can see all your open TOs using the transaction LT23.