Two Delivery dates in Sale Order against one item

Dear All
I need two delivery dates in sale order. one is default at the time of creation sale order. second i need actual delivery date which will be confirmed by production planning department after analysis the order whether material can be ready on that delivery date or it need to change. Actual delivery date may vary from original delivery date and both need to preserve in system. kindly provide solution. best regards.
Manjit

You need to select the Availability & Transfer of Req. check box in Schedule Line Configuration.It will transfer the req. to PP.So while creating the sale order , schedule Lines will be confirmed as per the Available Stock.
System will give you the Default Delivery Date as the Date added after Lead Time in days in the Configuration.Else system will give the Current Date.
Best regards,
Ankur

Similar Messages

  • Changing proposed delivery date in sales order for one specific sales org

    Hi All,
    I want to change proposed delivery date in sales order automatically for one specific sales org only without changing lead time in VOV8.
    For that can I use MV45AFZZ. But it is asking access key to make changes. Is there any other user exit for the same. And how does exactly change it.
    Thanks in advanced.
    Points will be awarded.
    Regards,

    EXIT_SAPFV45E_001 has nothing to do with this - it is meant to update the purchase order from a sales order. It might not even be triggered if the sales order has no link to a purchase order.
    USEREXIT_SAVE_DOCUMENT is not really good for this either, because the delivery date has to be changed before that. If memory serves, it also influences the schedule lines and probably the ATP check and such. I would strongly advise against it. One of the other routines in MV45AFZZ should do just fine, USEREXIT_MOVE_FIELD_TO_VBAK for example.

  • How to syatem determine delivery date in sales order

    hi sap gurus
    how to syatem determine delivery date in sales order
    Thanks and regards
    ram

    Hi Friend,
    There are many things which determines the delivery dates.
    01. PICK TIME+ PACK TIME +LOADING TIME
    02. LEAD TIME in days (VOV8)
    03. Shipping point
    04. Scheduling line
    05. Kind of availblity check
    06. If the above things are maintained as blank then the current date will be the delivery date
    However whether it must be proposed by the system or not is determined by one check box there find in VOV8 in requesteed delivery date determination tab.

  • Required delivery date in sales order shoud not be less than the inhouse pd

    Customer Requested Dates (CRD) entered in orders are often shorter than Product form wise lead time. 
    Logic to be configured in SAP : SAP should capture the CRD as per the lead time of Products or Date entered by sales persons (whichever is later).
    Required delivery date in sales order shoud not be less than the inhouse production lead time.
    Please help.
    Regards

    IMG - Sales and Distribution - Basic Functions - Availability Check and Transfer of Requirements - Availability Check - Availability Check with ATP Logic or Against Planning - Carry Out Control For Availability Check
    Here select the combination of your Availability Check & Checking Rule.
    Under Replenishment Lead TIme, you need to put a Tick Mark in the Check Box of "Check without RLT"
    This will make sure that system considers either the Requested Delivery Date or actual Material Availability Date, which ever is earlier.
    Hope this helps.
    Thanks,
    Jignesh Mehta
    Edited by: Jignesh Mehta on Nov 9, 2011 12:18 PM
    Edited by: Jignesh Mehta on Nov 9, 2011 12:23 PM

  • Delivery Date in Sale Order

    Dear All
    Delivery date in sales order should automatically changed or by defalt it should be after 2 days of creating the sales order.
    I have tried with lead time period and the ways given in the forum, but the schedule line/delivery date is by default coming as the day of sale order creation.
    Please guide me how to do it.
    Regards
    SB

    Hi,
    Goto Tcode: VOV8
    select sales document types
    goto request delivery date tab
    remove tick mark or uncheck propose delivery date
    and maintain lead time 2 days.
    thanks.

  • How system determine delivery date in sales order

    Hi, sap gurus
    I am new to sdn forum please help me regarding my question
    1) how the system will determine delivery date in sales order
    2) what are factors effects to conform sales order stock
    3) what is different between static check and damanic check in credit mgt
    Thanks and regards
    nishad

    hi,
    Reg question:1 - System determines the Requested Delivery Date based on the Scheduline assigned to the item category of the item in sales order.the schedule line in the order transfers the requirements trhu MRP (can be individual or collective) . If its ruch order , you configure the order type "Deliver Immediately".
    In Detail:
    The TOR depends on the Requirement Type (MMR), Requirement Class(MMR), Checking group(MMR) and the Sc line category (Line Item). For the TOR to happen u need Plant at line item, scheduline category markd for TOR, Requirement Class marked for TOR and Checking group in MMR (Availability check)
    What all stocks need to be checked during Availability check is controlled by using the checking rule.. for example for AV -02 Ind Requirements a checking rule will be assigned and this checking rule- and then what all stocks need to be considered to determine the delivery can be maintained here.
    Rgds
    Sai

  • Change Delivery date in Sales Order

    Hi all
    I want to change Request Delivery Date in Sales Order. But when I changed Request Delivery Date system appear" The default date is not copied into existing schedule lines"
    And Delivery Date didn't change.Could you tell me how to change Delivery Date ?
    I setup Request Delivery Date - September 21th but Availability Date is September 19th. Could you tell me how to setup loading time, picking time, packing time ?
    Thank and Best regards,
    Thang

    Hi,
    When you change the Request Delivery Date, it automatically changes the schedule line date of all the materials, but by default does not change the schedule line date of the ordered material.
    So just check the ordered material schedule line date and change it manually in the order.
    Similarly maintain the same date in all the resp fieldsi in the delivery, wherever you see the date.
    Regards,
    Siddharth.

  • Delivery date and sales order creation date

    Dear all
    Can you please explain the relation between delivery date and sales order date. In my case i can create delivery with delivery date as before the sales order date... how it is possible that i can create delivery before the sales order date.??
    Please explain.........
    Warm Regards
    Inder Pal

    Hi,
    Sales order date: Date on which the customer officially places an order to your company.
    All the commitment and product allocation counting starts with reference to this date.
    e.g. customer says that the goods are required from 20 days of placing order, then from this date the calculation starts.
    Delivery date: Date on which after the system goes through material availability date, replenishment time, calculates the date on which physically the goods can be delivered to the customer.
    e.g. customer orders 100 qty of material X in 15 days, you will hve to check this delivery date through availability check which can be done in sales order and also delivery.
    payment date is based on this delivery date.
    regards,
    Siddharth.

  • User Exit for Requested Delivery Date in Sales Order

    Hi
    Which user exit can be used to change Requested Delivery Date in Sales Order.
    Scenario:  Sales Document Type: OR has Lead Time: 7 days.  System always proposes delivery date after 7 days.  We need to change this Lead Time based on plant.
    Thanks in advance for your support.
    Regards
    Uma

    Hello,
      try with USEREXIT_MOVE_FIELD_TO_VBEP or USEREXIT_SAVE_DOCUMENT_PREPARE, of program MV45AFZZ.
    Hope to be useful.
    Best regards,
    Andrea

  • Automatic delivery dates in sales order.

    Hi all,
    The problem is that, The sales order is taking current date as delivery date , although ther are all config exist for availabiltity chek and Delivery & Transportation scheduling. The goods reciept processing time is 5 days in master record(MRP 2 View).
    so if order is created on 18.04.08 , the delivery dated also been shown as 18.04.08. why?
    Thanks in advance.
    Edited by: Gaurav S on Apr 18, 2008 11:20 AM

    Hi,
    System takes the requested delivery date from the sales doc type settings-
    goto VOV8- choose your sales doc type-details,
    in req.del date/pricing date/po date- maintain the lead time in days field- as desired.
    the above settings you made in material master is to confirm the delivery date in sales order, but not for the requested del date.
    hope it clears.
    *rewards

  • How to get the pricing hierarchy based on the delivery date for sales order

    Hi,
    How to get the pricing hierarchy based on the delivery date for sales order other than system date.
    My requirement is to get the Pricing hierarchy based on the delivery date other than system date.
    Waiting for kind response.
    Best Regards,
    BDP

    HI Sai,
    please refer teh document already how to write FM based extration on generic extractors.
    and here  the logic to find the latest records values:-
    -> get the data in an internal table
    ->Sort the internal table data based from date descending
    -> Using READ statement , we can read the first record of the table which is nothign but your latest record.
    Regards.
    Sakthi

  • Cant change delivery date on Sales Order posted in prior period

    Hello All,
    Scenario: A sales order which was processed in prior period but since then delivery date had changed due to request from our customer. When we try to go back and change the delivery date, we find it greyed out. To get around this, we have to open the period again, change date and then close the period. Problem is that not all dates get changed, so our late delivery report look bad, shows that 90% of our deliveries are late, when in fact they are on time, the new time which we could not record on the Sales Order. We have similar problem with our purchase Orders.
    Is there anything in Administration we can do to enable us to easily chnage delivery dates on Sales order and purchase orders?

    Hi,
    Welcome you to post on the forum. What is your B1 version and PL?
    Thanks,
    Gordon

  • Delivery date in Purchase Order in the item overview

    Hi all,
    In which table is Delivery date in Purchase Order in the item overview stored.
    the screen field name is eeind.
    Thanks

    In table EKET in field EINDT the delivery date is stored, based on the Schedule lines in the PO Item

  • Schedule line delivery date of sales ordere in production order-MTO

    We have a Make to order scenario where item in sales order can have mutliple scheule lines on different delviery dates.
    Ex : sales order 100020  and item no 0010
    has schedules with schedule line dates as
    10.04.2010----1pcs
    20.04.2010---1pcs
    03.05.2010----1pcs
    When the planned orders are converted to production orders, the 1 del date (EDATU) in the all the three production orders is the same ie the earliest delivery date (10.04.2010), even though the delviery dates are different for three as shown above.
    Is there a way we can show the indivdual delivery dates on all the three production orders.
    production order 1----- 1 del date as 10.04.2010
    production order 2 -
    1 del date as 20.04.2010
    production order 3 ---1 del date as 03.05.2010
    Thanks in advance.
    When a planned order is converted toproduction order

    We have a Make to order scenario where item in sales order can have mutliple scheule lines on different delivery dates.
    Ex : sales order 100020  and item no 0010
    has schedules with schedule line dates as
    10.04.2010----1pcs
    20.04.2010---1pcs
    03.05.2010----1pcs
    When the planned orders are converted to production orders, the 1 del date (EDATU) in the all the three production orders is the same ie the earliest delivery date (10.04.2010), even though the delviery dates are different for three as shown above.
    Is there a way we can show the indivdual delivery dates on all the three production orders.
    production order 1----- 1 del date as 10.04.2010
    production order 2 -
    1 del date as 20.04.2010
    production order 3 ---1 del date as 03.05.2010
    Thanks in advance.

  • Delivery date in sales order

    Hello Gurus
    I have a sales order with 5 items, the requirement is suppose all the the 8 items have different delivery dates eg: item 1 - 06.01.2009, item 2 - 15.02.2009, item 3 - 03.03.2009, item 4 - 25.01.2009,
    item 5 - 03.02.2009.  The need is i want the  the last date for all the items to be based on ie for 3 rd  item 03.03.2009,  to  be the delivery date for  all the items, like this delivery date should change.
    Need for this when the entire sales order will be closed, user wants to know and he wants to delivery only on that date all the items, automatically how to do that.
    Thanks in advance
    Rajesh

    Hi
    Goto VA02 - open the sales order- in the overview screen, click the tab Shipping and in the column D (Delivery Group) next to the column Material, give value 1 for all the line items and save the order. Now if you open the order again and check the schedule lines, all the delivery dates will be rescheduled and you can see the same date for all the line items, latest date by which all the items are available.
    Thanks,
    Ravi