Two-step procedure(between 2 plants)

Hi
the doc. states
"The approaches to the entry of plant-to-plant stock transfers for the one-step and two-step procedures without a stock transport order correspond to those for storage-location-to-storage-location transfers."
can I infer , that in a the case of the two-step procedure
(between 2 plants), there are 2 material documents generated and 2 accounting docs., too. ?
Thanks

During Two Step transfer it will create two material doc as below
1.An item for the removal from storage at the issuing plant
2.An item for the placement into stock in transfer at the receiving plant.
If the plants belong to different valuation areas, an accounting document is created parallel to the material document for the removal from storage, because the stock is transferred from one plant into another.
Upon placement into storage at the receiving plant, the system again creates a material document.
For every item you enter, only one material document item is created, because the quantity is only transferred from stock in transfer into unrestricted-use stock at the receiving point
Since the transfer posting from stock in transfer to unrestricted-use stock occurs within the plant, an accounting document is not created in addition to the material document.

Similar Messages

  • Error when doing two step transfer between Plants with split valuation

    Hi expert,
    I´ve activated split valuation for Material X , it has three Valuation types ( NEW, REPAIR and DAMAGE ) . The problem arose when i tried to do a two step transfer between plants ( mov 303 ) and i got the following error msg :
    Use one-step procedure for transfer posting to mat. subj. to valuation
    Message no. M7048
    Diagnosis
    In the receiving plant, the material is subject to split valuation. For this material, a stock transfer cannot be carried out using the two-step procedure.
    Procedure
    Use the one-step procedure (movement type 301) or a stock transfer order for the stock transfer.
    The message is very clear itself , but... i just wonder if there`s actually any way to avoid this, I tried to change the error msg into a warning but couldn´t find it in customizing. Thanks for any comments on this !

    Hi,
    What do you mean with "inconcistent to my storage type definition?", is that mean i can process two step transfer without using PO/delivery process or one-step movement? coz according to business requirement, we must use two step transfer considering to the distance between plants is so far and we want to make it the simple way so that PO/Delivery process isn't better solution. I think, this is an standard procedure all company over the world can use but just the reason of split valuation the system can't execute the transaction.
    Is there any config i miss to? is there any user exit i can use for this requirement? please help me..
    thanks,
    AJ

  • Inspection type for STO with delivery and billing , two step procedure

    Dear All,
    We've  STO scenario between two company codes, plant '1000' of company code '1000' supplies goods to plant '2000' of company code '2000' using STO. We'd like to evaluate the supplying plant for vendor evalution with respect to receiving plant,
    Please suggest , which inspection type '01' or '08'  needs to  be activated in the material master in receiving plant '2000' in order to consider the supplying plant ' 1000' for vendor evalution. and kindly let know me that whether the functionalities of QM procurement (Checking receipt of certificate while posting MIGO) can be used in STO scenario similar to normal procurement scenarios,
    Here, we are going for STO scenario of two step procedure with outbound delivery & billing.
    Thanks & regards,
    rajesh

    The inspection type '08' is used for stock transfer order process.
    In SAP standard you can't evaluate the supplying plant but external vendor only.
    Also the functionalities of QM procurement can influece or control it when materials are procured from external suppliers.
    If you want to use the functionalities of vendor evaluation and QM procurement, I would suggest you implement normal procurement process, not stock transfer process.
    Regards
    Luke

  • Canu00B4t use two step transfer with split valuation ?

    Hi people , i´ve activated split valuation for MaterialX , it has two Valuation types ( Production and Purchase ) . The problem arose when i tried to do a two step transfer between plants ( mov 303 ) and i got the following error msg :
    Use one-step procedure for transfer posting to mat. subj. to valuation
    Message no. M7048
    Diagnosis
    In the receiving plant, the material is subject to split valuation. For this material, a stock transfer cannot be carried out using the two-step procedure.
    Procedure
    Use the one-step procedure (movement type 301) or a stock transfer order for the stock transfer.
    The message is very clear itself , but... i just wonder if there`s actually any way to avoid this, considering that having to create a transfer order for each movement will duplicate work and using a one step transfer won´t be practical. I tried to change the error msg into a warning but couldn´t find it in customizing. Thanks for any comments on this !

    First of all , thanks everyone for the help.
    Csaba Szommer, Kunal ingale  , i read the OSS note and the pdf and indeed everything confirms it´s not possible to do the two step movement. So , i tried the stock transport order and something else appeared here. When creating this type of order , the system first ask for a Supplying Plant , then you can populate the material , quantity and the destination plant. But then it asks for the Valuation Type of the material involved, and it seems this field is Mandatory . Is it possible to make this field on the transport order as optional ? I couldn´t find this field at SPRO-MM-Purchasing-Purchase Order-Define Screen Layout at Document Level .
    I need this field to be optional for the following reason. In my company there´s a relation between two plants , Plant A ( from where products are dispatched to the customer ) and Plant B ( where the material is produced with valuation type "Production" and sometimes is buyed from vendors with valuation type "Purchase" ) . The idea is to run an MRP which will generate the material needs on Plant A considering the Sales Orders. This need will be then transformed (automatically by MRP ) in Stock Transport Orders with Supplying Plant "Plant B" and receiving "Plant A". The problem here is that , at the moment of the transport order creation it´s no possible to know which will be the valuation type of the material that will satisfy the need. I mean , Plant B ( production and buying plant ) will check the list of needs for Plant A and then will decide which material ( with which Valuation Type ) they will provide considering the actual stock levels at the time of the MRP run.
    In a few words, i see the only way to do a two step transfer of a split valuated material is using Stock Transport Orders , is there a way to make the field "Valuation Type" optional ?. The idea would be to choose the Valuation Type of the material at the moment of the Good Issue.  Thanks a lot , once again.
    Edited by: Christian  Len on Jul 7, 2008 3:16 PM

  • Stock transfer between plants for split valuated materials

    Hi,
    I'm doing a stock transfer between plants without STO.
    The FG's are split valuated,which are transferred from central warehouse to other warehouse at different states.
    I'm trying to use mvt type 303 and 305 to transfer the FG.
    But getting error "Use one-step procedure for transfer posting to mat. subj. to valuation".
    Please suggest how to achieve the requirement.
    Is it possible to make 303 mvt type document to be parked and posted.
    Regards,
    Venkatesh

    << Moderator message - Cut and paste response from Error when doing two step transfer between Plants with split valuation removed and points unassigned. Plagiarism is not allowed in SCN >>
    Refer below link with same issue discussed,
    [two step transfer with split valuation |Canu00B4t use two step transfer with split valuation ?]
    Edited by: Rob Burbank on Feb 3, 2012 11:30 AM

  • Material loss tracking in two step transfer posting with in plant

    Dear Friends ,
    Here the case is  material will going loss when shifting one storage location to another , here i am using two step procedure . so how can i track rhe loss here . our client want to post loss value to production account only and also they want to know total loss in report . How it can be maintainable?.....which is right method for this .
    RB

    Hi,
    You can scrap the material that underwent losses either at issiuing location (reverse GI for that much qty) or at the receiving location (do GR then scrapping).

  • Outbound Delivery Document Flow (One-Step procedure) Goods Receipt

    I am trying to extract the Goods Receipt status of Outbound Deliveries which are posted using One-Step procedure.  I can do this one delivery at a time using VL03N.
    Some sites (plants) are configured with One-Step procedure and others are configured as Two-Step procedure.
    Document flow of an Outbound Delivery is extracted from table VBFA.
    For the two-step delivery process (Movement type 641) the Goods Receipt is recorded in table VBFA (Subs.doc.categ. / VBTYP_N = 'i').  Therefore, I can easily extract the goods receipts for these deliveries. 
    However, for the one-step procedure (Movement type 647) the Goods Receipt does not appear to be recorded in table VBFA.  Does anyone know which table the Goods Receipt is stored for one-step procedure?
    Using transaction VL03N we can view the document flow.  It appears that for One-Step procedure the Goods Receipt is held at item level.  By highlighting a delivery line in VL03N and viewing the document flow we can see the goods receipt for One-Step deliveries (therefore, the data must be held somewhere).
    I understand that by using One-step procedure the goods receipt is posted automatically, so we can assume that there should never be outstanding Goods Receipts for One-Step sites.  However, I have been tasked with the job of reconciling all deliveries for the past 12 months.  I need to prove that a goods receipt has been posted for every single delivery.
    Any advice is much appreciated.

    Thankyou for the advice.   I will proceed with your recommendation.
    However, the query is inefficient since the link between LIKP and MKPF does not use the primary key (Article Doc. / MBLNR).  We have almost 7 million records in MKPF table. 
    Is there any intermediate tables I can include between LIKP and MKPF so that only primary keys are used for the joins?

  • Two step and Single step Reservations

    hi
    am bit confused with the following.
    can anyone tell me why cant we use the Reservations for the two step procedures for stock transfer and why for single step procedures?
    regards

    Hi,
    It is a very good question and one that is not that easy to answer (and it <u>should</u> be easy).
    I have tried to figure out why this should be the case and I cannot think of anything concrete.
    perhaps it relates to the use of in-transit and in-transfer stock, perhaps the system cannot cope with reservations that affect these transit stock areas? I don't know why it cannot cope with these but perhaps it relates to the ability to trace reservations from within transactions such as MMBE etc. perhaps it is too difficult to show a list of reservations that are increasing in transit stock?
    Sorry i can't help a lot with this, but the above is the only thing I can imagine would be the reason?
    Steve B

  • Two steps to make the panel a TRUE COLOR one

    It seems that the MSI True Color Technology is fulfilled through a two-step procedure, hardware control and software modification.
    Really impressive. 
     

    This is your third posting on this topic.
    If you need further help then you need to create a [Short, Self Contained, Compilable and Executable, Example Program (SSCCE)|http://homepage1.nifty.com/algafield/sscce.html], that demonstrates the incorrect behaviour.
    We don't have access to your database so the code can't be executed.

  • Stock transfer between plants two steps 303-305

    Dear All,
                    We are using version SAP 4.7 we are using stock transfer scenarion between plants two steps. 303-305 source plant they will remove the stock  with 303 movement in the receiving plant they will receive the goods against the 303 document number.
    at the time with 305 movement type one document generated in that document table MKPF 303 reference number should be updated but in the 305 document the reference document 303 not updated in table MKPF.
    why?...any updations required. because i want to develop an user exit at the time of Goods receipt with 305 movement in the receiving plant now it is allowing posting date as <= 303 document posting date it should be allow only >=303 document posting date at the time of 305 document generation in the receiving plant.
    in MKPF table the reference document is not updating ....any ideas....
    im using the standard Enhancement :MBCF0002
    EXIT_SAPMM07M_001.
    Regards
    Anand..

    Hi..
        then how can control.
    receiving plant 305 document posting date is should be greater than or equal to source plant 303 document posting date how can achieve this?.
    via user exit in the reciving plant 305 document the reference document not updated. how to achieve this?...
    any ideas..
    Regards
    P.Anandhakumar

  • Stock Transfer between plants two steps.

    DearAll,
                 We are using the scenario stock transfer between plants two steps.in the source plant we are issueing the goods  with on 303 movement in MIGO with Remove from storage option. in the receiving plant we are receiving the goods with refernce to 303 material document in MIGO with place in storage option.
              we are using the version SAP 4.7.
    my problem is at the time of goods receipt SAP is allowing to the posting date less than the source plant 303 document date. it should allow the posting date as Greater than equal to source plant document date at the time of GR.
    Any standard pracktise is there.
    for example  source plant 303 document date is 08.06.2009 wrongly i have entered the receiving plant 305 document posting date as 06.06.2009 it is allowing to post it is not throw any information. it should not allow to know.
    i want to control this. any standard controls is there. kindly help.
    Regards
    P.Anandhakumar
    Edited by: Anandhakumar Palanisamy on Jun 9, 2009 10:46 AM

    Except user exit , Is it possible any standard functionality.?
    why SAP not controlled this?.
    this is SAP bug or not?. kindly clarify..
    Regards
    P.Anandhakumar....

  • What is Cycle or steps to create Stock transfer between plants.

    What is Cycle or steps to create Stock transfer between plants.
    Reply with T Codes & Justify

    Hello RM
    We can transfer stocks within a company code between 2 plants using 3 methods:
    1) Using single step simple stock transfer (Mvt Type 301).
    2) Using two step stock transfer (Mvt Types 303 and then 305).
    3) Using a stock transport order(STO) again it is based on 2 things:
    a) r u using STO with delivery or
    b) without delivery.
    Though the first two steps are very simple to process but using STO has its own advantages: 1) Quantity in transit can be monitored 2) delivery costs can be entered in the STO.
    First 2 steps (single step and 2 step plant to plant transfer) can be done using MIGO tcode , selecting stock transfer and entering the relevant mvt types.
    would like to tell you about STO as it is an important process.
    STO without delivery, the following functions are provided to support the Internal Stock Transfer without Delivery :
    #Create Stock Transport Order
    #Post goods issue for stock transport order
    #Post goods receipt for stock transport order
    Config Step required before processing above steps:
    Setting Up Stock Transport Order: Purchasing Document Type, the purpose of this activity is to specify which document type is to be used for a certain combination of supplying (issuing) plant and receiving plant.
    Path go to SPRO--MM-Purchasing---PO-Set up STO-----assign doc type, one step procedure, underdelivery tolerances.
    There you have to enter your supplying and receving plant with the Purchasing doc type( UB).
    Now the process:
    1) Receiving plant will create a STO towards issuing plant.
    2) Issuing plant will transfer material from their unrestricted use stock to stokc in transit using mvt type 351.
    3) Receiving plant receives the goods using MIGO mvt type 101.
    Regards
    Yogesh

  • Stored procedure between two scenarios.

    Hi All,
    I need to call Oracle Stored procedure between two scenarios.
    My first scenario is file to JDBC. Ather that i need to call a Stored Procedure and once it is executed i need to trigger another scenario which is JDBC to File.
    I can call SP in OS comands but can anybody tell to how to initiate the JDBC to File scenario after SP?
    Thanks,

    After you receve the message in BPM and call the JDBC adapter, have a send step (syn). This should use a synchronous interface. The message type should be SQL XML for calling SPs (Check help.sap.com for JDBC receiver adaptoer SQL XML format). Once this step is done, you have to receive the response into the container variable of the asyn interface for file. Then have an asyn send step to write to file.
    Receive (Async)->Send (Async JDBC)->Send (Sync JDBC call SP, Since sync, you would get the response)->Send (Async File)
    VJ

  • Step by step procedure to establish connect between SAP APO and SAP PI

    hello All,
    Can any one provide me link or step by step procedure to establish or exchange messages between SAP APO and SAP PI.
    Thanks
    Rajeev

    Hi,
    >>>Can any one provide me link or step by step procedure to establish or exchange messages between SAP APO and SAP PI
    sure 
    a) if you want to use idocs
    http://www.sappress.com/product_basic.cfm?account=&product=H3059
    b) if you want to use ABAP proxies
    check out blogs on sdn on ABAP proxies
    only those two are used
    Regards,
    Michal Krawczyk

  • POSDM Diff Between : One Step and Two Step Processing Tasks

    Hi All,
    Can you pl give some points on difference between "One Step and Two Step Processing Tasks in POSDM ??
    Thanks!!

    Please consult the SAP Note 980272 on the service marketplace. It gives a detailed description of the difference.