Hi Experts,
We have created a sales order with Parent item and its 3 BOM items, with pricing doen at BOM items. Of the three BOM items, stock exists for only 1 item. When we are trying to create the delivery, it is bringing only the stock item in delivery overview and not the items without stock. We would like:
1. System to bring all the items while creating delivery. It may not permit picking and PGI till the stock is brought in system.
2. System to not allow creating delivery till stock exists for all the required items.
For the non-stock items, system is not allowing to carry out the availability check also. It can give a future date and confirm the quantity for future delivery!!
Please provide your expert opinions asap. Points would be awarded to all helpful answers.
Regards,
Peeyoosh.

Hi Peeyoosh,
had you a look at the customizing of your item categories for delivery? Did you use the standard item category TAN? Perhaps the customizing of "availabilty check for delivery item" and "Check quantity 0" in your category for delivery will bring you forward.
Regards Thomas

Similar Messages

  • Unable to create delivery for sustitute delivery in CRM complaint

    Hi,
    I have created a complaint with sales item in CRM system.Now I created return request which is distributed to ECC as sales order.Processed Returns delivery. Everything is updated in CRM complaint.
    Now i created Substitute delivery request in the same CRM complaint for the replacement. This item is updated in the same sales order in ECC. When I try to create a delivery for this sales order system is not allowed.
    Order cannot be delivered (see long text)
    Message no. VL461
    Diagnosis
    Possible reasons include:
    The copy conditions specified in Specify copy control for deliveries do not allow the order to be delivered.
    The order is blocked for delivery.
    The order document is incomplete.
    My doubt here is when i check the delivery document type, it's LR(returns delivery) for both the cases( for returns and substitute) since the transaction type is same. Now how could I differentiate since first case is returns delivery and second case is substitute delivery which is going out.
    Appreciate your help.
    thanks you
    Regards
    Nagi

    U can manually input LF delivery type in Vl01N screen and do the delivery.

  • Unable to create delivery for STO between different stroage locations

    Hi,
    i created PO for STO between differen storage locations belonging to the same plant.
                 At the time creating PO iam getting warning message " Of material RM-999999, only 0 KG are available on desired     
                 date". what could be the reason?
    when iam doing vl10b, PO is displaying but when iam selecting the PO line and clicking on the background button it is not generating any delivery document number and it is not showing any errors?
    can any one help on this.

    Hi Praveen,
    While executing VL10B, you are actually planning to create outbound delivery for STO PO.
    The STO PO will be due for delivery on that date and hence PO is displayed in the transaction.
    The error message specified by you means on the due date of delivery, there is no material quantity exists at supplying storage location. This could be because no quantity exists in storage location or there could be some reservations available for available quantity or some other quantity is booked under some other outbound delivery document on or before that date.
    Check for stock on posting date via t-code MB5B and proceed accordingly.
    Hope this resolves your problem.
    -Ravi

  • Create delivery for STO line item

    Hi All,
    My requirement is to allow creating delivery for Stock transfer Order(STO) line items which are
    not in blocked status even though some line items are in blocked status.
    Right now the logic checks if entire PO is in blocked Status using FM-- /SAPSLL/CD_STATUS_GET in method CHANGE_DELIVERY_ITEM of interface IF_EX_LE_SHP_DELIVERY_PROC
    But this FM does not contain PO item parameters. I need to incorporate item level checking logic.
    Are there any SAP notes available to fix this problem?

    Hi All,
    Any clues on this?

  • Group delivery for BOM's when one of the BOM component has no confirmed qua

    Hi,
    We have an issue. We have group delivery for BOMs. However it might be in some cases that one of the component has no confirmed quantity. Still we do not want delivery for any of the component to be created. What is the easiest way to achive this?
    thanks in advance.
    regards Camilla

    Hi Camilla,
    In VOV7 for the item category of main item Create Delivery Group must be assigned a value X (Form delivery group with one delivery date). If you have this configuration set-up done system will  assign one delivery group for the entire group of BOM materials and all will be delivered on the same date. Can you check this?

  • One Outbound delivery for all items in PO

    I created a Standard PO with 4 line items. I make the items with Sub contract material by specifying L in item category. Selecting from delivery scedule date and object listm, deleting all the material from  object list and giving 1 sub contract material for all line items. In Tcode ME2O, I am creating the o/b delivery for the vendor and SAP creates me delivery for each item, but my requirement is to create one deliver for line items. As I am an abaper, I didnt get the logic. Can anybody explain me.

    There is customizing in IMG > LE for delivery splits.
    Further delivery splits are defined as well with user exits.
    There are many OSS notes about delivery split (inlcuding check programs) especially for unwanted delivery splits with subcontracting.
    In most cases it is unfluenced by different requirement dates.

  • Special procurement type for BOM item

    Hi Experts
    I am creating BOM using BAPI : CAD_CREATE_BOM_WITH_SUB_ITEMS
    There is no field to update Special procurement type for BOM item in this BAPI.
    Could you please suggest some way to update this.
    Thanks in Advance

    hi Janardhan,
    phantom assembly is the assembly which is not kept in stock rather it consumes directly.
    Use of phantom assemblies are as below
    Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly.
    example - A car with music system.
    During backflush, only the goods movement for the phantom assembly components are posted. The phantom assembly is marked as backflushed but does not trigger any goods movement.
    Experts pl correct me if i'm wrong.
    Regards,
    Anil

  • Shipping point to create delivery for purchase order

    Hai,
          I have created PO in ME21N and I need to create delivery for this, so I have used VL10B Tcode, here it is asking for shipping point, which value we need to give for this. Actually I have given the plant which was given in ME21N, but I'm not getting PO number here to deliver, Is there any problem, or which value we nee to give as shipping pioint.
    thanks in advance,
    dhanush

    Hello,
    Check shippinng tab on your PO item level. If you can not find shipping tab that means shipping point is not determined.
    Shipping point determination :
    In SPRO>>Logistics execution>>Shipping>>Basic shipping functions>>Shipping point Determination->>assign shipping points>> For your Loading group,Shipping Condition and Supplying plant combination >>Assign shipping point here
    Also check shipping condtion in yor coustomer master and loading group in material master.
    Regards,
    Shailesh

  • Error in creating delivery for STO

    Hi SAP Gurus !!
    I have these errors while trying to create delivery for a Stock Transport Order between 2 plants using transaction "VL10F"
    APO: Check instructions YA / BE does not exist for loca tion product PFSIND_SM_TEST_FCO / 2383
    APO: Check mode YA and business event BE not defined                                         
    APO: Internal error: Item $ 1/000001                                                         
    Only 0,00 PC of material PFSIND_SM_TEST_FCO available                                        
    An item with no delivery quantity is not permitted. Item will be deleted.                    
    I have chcked that there is sufficient stock available at the storage location level in the supplying plant.
    Can you please help me out of this please......

    Dear,
            Please try to check whether some STO is still pending for do complete process. If there is any pending STO then stock is block for this material.
    Regards,
    Sandip Shaktavat

  • Unable to create delivery using ADSUBCON

    Hi Gurus,
    I am unable to create delivery using ADSUBCON transaction for the PO which has material with different Order Unit. My base unit of measure is EA where as the Order unit is Roll. If I delete the order unit system allows me to create delivery where the PO.
    Why the system does not allow me to create the delivery when the order unit is different than base unit of measure.
    Thanks in advance,
    Shashidhar
    Edited by: Shashidhar on Jan 29, 2011 5:19 AM

    HI,
    Its already been  maintained.
    Shashi

  • Create delivery for zero conformed qty

    Hi,
    In the sales order the order qty is 100 but due to no stock in plant the system is showing proposed availability date 10.06.2009.In availability control screen i did not accept the proposed date given by the system as i need to create the delivery doc for this 100 qty.In sales order the conformed qty is zero.Now the system is not allowing me to do delivery doc. Error messege is"   No schedule lines due for delivery up to the selected date" due to zero conformed qty in sch line.
    The requirement is instead of zero availability in sales order i can able to create delivery doc.After the material available we will do PGI in VL02N later.
    Is it possible in standard or any  userexit will be required.
    Regards
    Debasish

    Hi Friend,
    This can be possible by one setting at the item category level in the delivery document..
    Goto the transaction code OVLP and select your item category and in the display  you can see the CHECK QUANTITY 0
    In that field CHECK QUANTITY =0 mantain the value as BLANK which means you can create the delivery for the items without quantity.
    Please revert if you need any further help.
    regards,
    santosh

  • Why cannot create delivery for Sales Ord in SAP, even there is enough stock

    Hello
    I am trying to create delivery for sale order. I did for some lines. But it shows meassage "An item with no delivery quantity is not permitted. Item will be deleted." for the other lines, even there is enough stock.
    Appreciate your comments:)
    BR
    Happy

    Hi Happy,
    Please refer following link for better understanding the concept and functionality :--
    Re: Schedule line control in sales order
    http://www.sapfans.com/forums/viewtopic.php?f=5&t=127586
    Re: Delivery without Sales order? If yes,how can we track those materials?
    Regards
    Rajesh

  • Unable to create delivery through ME2O in subcontracting process

    Hi,
    I am trying to create delivery for the subcontracting order in ME2O, but it was giving the error. Stock also exist for component material.
    The error messange is:
    "An item with no delivery quantity is not permitted. Item will be deleted".
    Please let us know the reason.
    Thanks in advance!
    Thanks,
    Jana

    Hi
    Please check the Stock overview MMBE of the material, in the stcok overview check the stock qty click on
    details and check if any stock qty is reserved for any delivery.
    Usually the delivery is created but PGI is not done , in such cases systme reserves the stock for that delivery, in the sytem it shows that stock is availble but that may be reserved.
    Thanks & Regards
    Kishore

  • Error While creating Delivery For  AAK

    Hi experts ,
    I am creating Delivery for AAK in sap but i m getting error as
    ERROR:::--
    A delivery of type Installation/Upgrade already
    exists for component KAARTECH (version 400_700)
    We have already created the delivery but we couldn use the old one. so i m creating new delivery but it throws an error like .
    Kindly help me proceed after this..
    I just want to create a new delivery and proceed in this AAK.in old delivery i am facing few errors so i m creating new delivery , but its unable to create .
    Regards,
    Ajay.
    Edited by: ajayshyam on Jan 27, 2011 8:54 AM

    Hi,
    Do you have any steps to follow AAK.
    We have lots of TOC's delivered to different client.
    Now i have to install AAK and start delivering the files through AAK.
    I dont know how to start. I registered a TOC. Next what ?
    Can you share some information on how to start working with AAK.
    Regards
    Kuna

  • 2960X 15.02(EX5) %AAA-3-ACCT_LOW_MEM_UID_FAIL:AAA unable to create UID for incoming calls due to insufficient processor memory.

    Deployed four 2960X switches in a stack.  All okay for about one month then tried to web browse for the first time via firefox which partially displayed the page.  I assumed this was a browser error.  So tried Chrome then IE which both failed.  Chrome was a bad display and IE fails to connect.
    After this, I could not telnet or ssh.  Plugged into the console and immediately started receiving:
    %AAA-3-ACCT_LOW_MEM_UID_FAIL: AAA unable to create UID for incoming calls due to insufficient processor memory
    %% Low on memory; try again later
    I am unable to log in.  I have a TAC case logged but the first step to try is a reboot which will be difficult until I can get a maintenance window.  When I do get a maintenance window, I would also like to deploy a fix such as a different version of code or a work-around cofig command.  I don't mind disabling HTTP.
    Any suggestions?

    I am currently working with TAC
    The switches failed about 18 hours later and had to be rebooted to get back up.  Now that I have console/telnet access, I can see the memory being depleted mostly by the Auth Manager process at about the same rate as free memory is dropping.
    SW13#sho proc mem sort | i Auth Manager
     191   0  177721332   95004616   34757416          0          0 Auth Manager
    SW13#sho proc mem sort | i Auth Manager
     191   0  177754888   95025696   34759780          0          0 Auth Manager
    SW13#sho proc mem sort | i Auth Manager
     191   0  177774316   95037928   34761056          0          0 Auth Manager
    SW13#sho proc mem sort | i Auth Manager
     191   0  177799720   95053940   34762888          0          0 Auth Manager
    SW13#sho proc mem sort | i Auth Manager
     191   0  177824976   95069732   34764696          0          0 Auth Manager
    SW13#
    SW13#
    SW13#sho proc mem sort | i Processor
    Processor Pool Total:  442796836 Used:  103448576 Free:  339348260
    SW13#sho proc mem sort | i Processor
    Processor Pool Total:  442796836 Used:  103454416 Free:  339342420
    SW13#sho proc mem sort | i Processor
    Processor Pool Total:  442796836 Used:  103455860 Free:  339340976
    SW13#sho proc mem sort | i Processor
    Processor Pool Total:  442796836 Used:  103459236 Free:  339337600
    SW13#sho proc mem sort | i Processor
    Processor Pool Total:  442796836 Used:  103461040 Free:  339335796

Maybe you are looking for

  • Enhancement of 2LIS_02_ITM

    Hi, I have a problem extracting the field EKPO-LABNR with the 2LIS_02_ITM: I build an append to MCEKPO, did the same with MC02M_0ITM, and added code to fill the field via cmod. When I change the field in the purchasing document, I can see the documen

  • Not able to post GR from SRM portal

    Hi, We are trying to post GR from SRM portal but getting below errors. 1) document type AA is not defined 2) check account assignment category. Purchase order is classic type and having account assignment type as asset. Is there any config which will

  • Rotating Off-Days in PM Work Center Available Capacity

    Good Day! Background: Each Maintenance person is represented by a PM Work Center. Maintenance person have a rotating off-days which cycle repeats after 21 days. Requirement: We want to reflect rotating off-days to PM Work Center Available Capacity. O

  • The Most Universal Codecs

    I'm working on a project where 50 filmmakers around the world are sending me clips that I'll edit together in FCPX. They're shooting with everything: camcorders, DSLRs, etc. I had asked people to send me footage in ProRes, but PC users are writing to

  • Library constantly screws up my song info

    OK this has really been bugging me. I sorted my girlfriend's ENTIRE library (artist, track #, etc) and it randomly glitched up. So I finally got around again to fixing it all, but now its messing up again. It'll resort back to its old composer, delet