Unable to update revenue plan values in Easy Cost Planning

Hi,
Business maintains planned costs and revenues on WBS element using Easy Cost Planning tool. But for one of the WBS element system is not allowing to update/add planned revenue line items.User is able to update the planned costs for this WBS element.
The Legend in Easy Cost Planning screen is Non-Changeable Cost Estimate.
The status of WBS is REL,ACPT(Order Accepted),NSCH(Not Scheduled - Forecast Dates),RESA(Result Analysis Carried out).
We have checked all the business process and all the revenue planning is allowed.
Please guide us on how to resolve this issue.

This is resolved...Select the WBS and click on CLOSE icon to reset the cost estimate. This allows to plan revenues again.

Similar Messages

  • Calculated field in model of easy cost planning

    Hi,
    I would like to introduce the cost model easy planing a calculated field (characteristic), which was the multiplication of two fields (Characteristics).
    I have entered into the transaction CKCM "Easy Cost Planning: Model", I created 3 Characteristics (A,B,C)through the option
    "Assign Characteristics to the model."
    I entered the "Define the derivation rules (template)" and created a calculation with the two characteristics( C = A * B). The problem I have is that I did not enter the calculation in characteristic 3, which is what I want to pick up the value.
    Many Thanks.
    Regards.

    Hi Vivek,
    Thanks for answering.
    My question is, how I can assign a  calculation in a characteristic?
    Characteristic A
    Characteristic B
    Characteristic C = A * B
    I want the easy cost planning screen, enter a value in the characteristic A and B, it will automatically calculate the C and view the calculation in the screen in characteristic C. As I can do?
    Thank you very much.

  • Adding Z-field in tcode CJ9ECP - Easy Cost Planning,

    Dear ABAPers,
    I have a requirement where I need to display (Display only) MPN (Mat Part no) in Easy Cost Planning screen.
    I have extended CI_KISU and CI_CKIS`structure  with a new Z-field for MPN and the field is displayed on the screen without any value.
    However, which BADI to implement to fetch the MPN.
    Should I implement  BADI GUI_ITEMIZATION_CK or CP_ADD_FUNCTIONS_CK,
    If anyone have done similar taks, would you please share the code of the method, and other information , which method to use and how to go about it.
    Thanks
    Mahi

    Hi Vivek,
    Thanks for answering.
    My question is, how I can assign a  calculation in a characteristic?
    Characteristic A
    Characteristic B
    Characteristic C = A * B
    I want the easy cost planning screen, enter a value in the characteristic A and B, it will automatically calculate the C and view the calculation in the screen in characteristic C. As I can do?
    Thank you very much.

  • Easy Cost Planning & Project Builder

    Dear All,
    I would like to know whether the Material included in Easy Cost Planning be updated in Project Builder strucure. Is there any BAPI to upload material component?

    I do think, that there is no functionality in standard to include the materiai in ECP into PS structure.
    The material in ECP represent the costs point of view, and the material in PS structure represent typically not only the logistic view but also the costs point of view. If you manage to include the material into PS structure (e.g. manually), please avoid the double costs.
    Kind regards,
    Zhenbo

  • Overhead costing sheet in easy cost planning

    Hello,
    I have created a overhead costing sheet (having base as material cost elements where a %age is defined to be applied on the material cost) and attached it to the valuation variant of easy cost planning in PS module.
    Now for a given project when I am checking the easy cost planning, it is showing all individual lines of resources like material etc. along with its qty, price and value but I can not see the effect of the %age specified in overhead costing sheet.
    Kindly suggest what is to be done.
    Also pl. let me know whether I can see the cost component structure of easy cost planning.
    With Thanks and Regards
    Ratna

    Hello,
    Thanks for your reply.
    But when I run CJ46 for a particular WBS element, it says "The object is not relevant for processing".
    I have created the costingsheet as per the process mentioned below.
    For overhead costing sheet, base is created with raw material cost elements range and origin group range.
    Overhead rate is defined with dependency D020 - Overhead Type/Plant as 1.5% with proper validity period.
    Credity key is defined with secondary cost element with category 41 and cost center and fixed % with default "*".
    The above costing sheet is attached to the valuation variant of easy cost planning in PS module.
    There is a cost component structure 10 which is attached to costing variant PS06.
    Still CJ46 gives message as "The object is not relevant for processing" when I run it for particular WBS element.
    Kindly suggest whether I m missing any other step.
    With Thanks and Regards.
    Ratna

  • Easy Cost Planning

    Hi ,
    I am using Easy cost planning methodlogy for Cost planning.
    I need some guidance on following points.
    1. Can easy cost plan can be saved in versions ?
    2. In CJ30 planned cost I can view in annual view but it doesn't get Summed up at Header level WBS ?
    3.After releasing the WBS easy cost plan can be changed How to restrict that ?
    Pl suggest.
    Rgds

    Hi  Rasam,
    You can see the ECP of simulation using CJ20N, or CJ9ECP.
    The multiple ecp (MECP) is applied using SAP extenstion, after release 2.0. If you can check the system status of your system, you can find out, if the EA_APPL (at least 2.0 release) is applied your system or not. IF yes, you can find the corresponding customizing to active the MECP.
    If MECP is active, you can then determine in which version should be ECP maintained. You get an additional POP UP screen to let you select the CO version, as you lauch to the ECP in CJ20N or CJ9ECP.
    Kind regards,
    Zhenbo

  • EASY COST PLANNING at Network Activity Level

    Hi All
    I am using EHP4 system. I want to do easy cost planning at NWA level for this I already activate ECP for NWA in configuration setting and other necessary settings but still when I create ECP from CJ20N or CJ9ECP I can not able to do ECP on NWA activity level. Please give your inputs on same.
    Regards

    Hi Gokul
    All basic settings for ECP have been maintain. It allow me for ECP on WBS level but it not show me any activity or Network in ECP as I activate Planning for Network Activities with Easy Cost Plan in configuration.
    Regards

  • Easy Cost Planning & Project Stock

    Dear Experts,
    I am using Easy cost planning for WBS cost planning and Project definition control data tab page has Valuated Project stock selected.My costing model had an external procurement material for which I generated PR & PO thru Execution services.But the account assignment in my PR & PO was P with the corresponding WBS as account assignment and not Q.
    I have two question regarding this,
    1) Does it mean that while using ECP, Project stock concept will not work?
    2)How can we get the pop up of procurement type options(like Res + PR for WBS element) while generating PR through execution services?

    Hi,
    I am replying again because in my last answer there was some typing mistake.
    Hi,
    I tried your scenario is my system.
    whenever i am changing P to Q in Config in SPRO,It is giving an error that "The selected account assignment category is not supported" that means it is not meant for Q but i double click for object type PR WBS Element and changed Acct Assgmt Cat to Q then system allowed me to save.
    The i create a PR and WBSE is coming in the Account Assignement ,then i converted PR to PO and then i recived goods as project stock.when i issued the material in ECP it is not issuing from Project stock because 221 Q is not present in Config for SPRO so it is issuing from Normal stock so special stock from ECP is not supported.
    But you can manually issue the material to the WBSE in MIGO/MB1A by 221 Q.
    Hope it is clear.
    Muzamil

  • Easy cost Planning & Network Costing

    Dear All
    In one Project can we use both Easy cost Planning & Network Costing. Easy cost planning is generally used when you have structure with WBS only. Network cost planning is a combination of group of activities, all these having their relevant cost elements/ work center combination. can we manage both this in one project. If it possible please explain in detail.
    Regards
    Nivrutti

    What is your business requirement ? It depends on that. Yes your understanding is quite correct. We use easy cost planning in the initial phase of project. Easy cost planning can be done in various versions including  0 plan / actaul version.  If you does easy cost planning in 0 along with network costin you will double up lannning cost.
    Network costing can only be done in plan / actual version 0 only.
    Best approach is to use easy cost plnnaing as rough cut level apart from 0 version. And use network costing. However it may very a/c to business requirement.
    With Regards
    Nitin P.

  • Easy cost planning with integrated planning

    Hi All,
    I am testing easy cost planning and I see that to use easy cost planning, I have to unmark the flag for "Integrated PLanning", this leeds to no creation of line items in planification. Does anyone know if there is a way to use easy cost planning with integrated planning?
    Thanks a lot in advance.

    it may be with reference to the Versions.

  • Easy Cost Planning at Network Level

    Hi All,
    I was able to implement ECP at WBS level, but not able to implement at network level. I am using SAP ECC 6.0 EHP 4.
    I have activated the business function ops_ps_ci_1 and also activated the 'Activate Planning for Network Activities with Easy Cost Planning' in the configuration settings in SPRO-IMG. I had gone through most of the threads on this topic like :
    Network Activity Easy Cost planning
    ECP at activity level not triggered
    I am not able to find the option for 'Create Alternate CO Version' and 'Activate Multiple CO Version' under the Easy Cost Planning and Execution Services in SPRO-IMG.Please advise me in implementing Easy Cost Planning at Network Level and correct me if I was wrong in completing the configuration steps.

    Thanku All,
    I have done all the steps as you mentioned
    1. Activated the business function OPS_PS_CI_1.
    3
    2.
    3.
    Activated Multiple Plan Version using the tcode RCNPRECP
    Still not able to view the options under SPRO-IMG Easy Cost Planning
    * Create Alternate CO Version
    * Activate Multiple CO Version
    Also not able to implement ECP at network level.

  • Easy cost planning - cost element

    Hi,
    while creating an easy cost planning using a cost template, the system proposes a cost element (linked to the activity type). Can we propose by default another cost element ? (using a user exit ?) We tried to do it in the derivation rules for the cost template, but didn 't had any luck..
    thanks in advance !!

    just trying to keep the topic alive

  • Easy Cost Planning-prob Costing model

    Hello ,
    I am creating costing model
    i want at time of Easy cost planning  court fee(Characteristics)   to be selected from drop down list
    i have made characteristic court fee ,in currency format
    (CKCM) while defining derivation rule(template), if i am mentioning quantity as court fee
    Facing error that Syntax error in quantity
    Pls help
    Thanks

    After Double click on Qty , you have to define the formula there,
    correct your Formula which may be wrong leading to Syntax Error.
    Regards,
    Nitin

  • Easy Cost Planning Short Dump

    Dear All,
    Activated Execution services at activity level in Easy cost planning.
    Created Project with Activities and planned cost using Easy cost Planning.
    While Posting actual using Easy cost Planning system is going to short Dump.
    Please find the attached Screen Shot for your reference.
    Regards,
    Avinash Kusam

    Check this note and see if it helps you,
    20434 - SAPSQL_ARRAY_INSERT_DUPREC at ONR00

  • Easy Cost Planning - Passing info down the hierarchy

    Is it possible in Easy Cost Planning to pass characteristics down the hierarchy for use lower down.
    For example, enter the dimensions at the top level and have them passed down for use in calculations lower down the hierarchy?
    Thanks
    Graham

    Here is a WIKI that has detailed steps to create.
    http://wiki.scn.sap.com/wiki/x/5IHpFQ
    http://wiki.scn.sap.com/wiki/display/PLM/ABAP+calls+to+create+Easy+Cost+Planning+in+Project+Systems

Maybe you are looking for