Hi guys,
          I am a little kid in SAP. Before 30 days i don know what SAP is? am a newly joined trainee in basis in a concern.
now am given a oppurtunity to work on a project of "Test upgrade of Production server ECC 6.0 to EHP4".
i've to start my project. i've been preparing about the EHP4. but am not clear about the concept.will u guys give me the link for this upgrade guide??
i've seen that EHP4 has released as a new tool of installation unlike as other upgrade versions. And it allows to choose the netweaver component 7.0 for portal upgrade. Am not sure of this.please any guys, will u please elaborate about this concept??
And another thing is, my boss wants business suite 7.0 in that. i've no idea of business suite. when i asked my senior, he told that if u upgrade to EHP4, business suite components will be added to tht enhancement package. will u please exlain weather business suite is available in EHP4?
Thanks and Regards,
Santhosh.
Edited by: santhoshkumarvellore on Sep 4, 2010 4:40 PM

Hi,
  Please get the upgrade document from servicemarket place.
https://websmp204.sap-ag.de/instguides  or https://service.sap.com/instguides
You can do it from EHPI installer tool. this document also you can get it from above website.
From solution manager you can get the key and Stack file. download required support stack as per the stack file.
follow the steps in upgrade/Ehpi installer document.
Thanks and Regards,
Jibin,
Edited by: jibin singh on Sep 7, 2010 2:54 PM

Similar Messages

  • Error in Upgrading ECC 6.0 to EHP4

    Hi sap gurus,
                         Am upgrading ECC 6.0 to EHP4. now am in configuration phase. in the EHP_INCLUSION phase am getting a error:
    " Severe error(s) occured in phase PREP_EXTENSION/SUBMOD_EXTENSION_NEW/EHP_INCLUSION!
    Last error code set: Stack inclusion failed: patch level 53 for component EA-HR is too low, destination level is already at 55"
                  Then i downloaded the required patches of patch level service pack 56-61 and continued, but getting the same error..after that i checked the current status of the server. its having EA-HR component till service pack 55. but when i checked the stack XML file, its showing only EA-HR component SP02 to SP53. i think this error is due to the mismatch in stack XML file. i dono what should i do for this. should i need to alter the stack XML file manually? Please help me guys. my upgradation is hanging. please help me guys.
    Thanks and regards,
    Santhosh Kumar.

    it is fine to assume that the stack file is mismatched with the system as the file suggested the ehpi to patch until level 53 but the original system already up to 55. if you are set on editing the xml file and this is not for production, you could try to remove the HR part entirely, just use find and try to remove all of that content that related to HR, be careful with the tag. just delete <software-component> until </software-component> for the HR part, remember to backup original file. it will avoid the error. Since the xml suggested 53 and the system already at 55 and assuming all other components correctly defined in the stack, i think it is fine to continue, and if i'm not mistaken after calculation with stack file, ehpi will offer to add support package level manually, you can add HR level until 61 or just leave it at 55 and add manually with spam later. 
    if this is for production system, i think you should go with AC suggestion, just find whats wrong with solman and reinstall using the right xml file.
    Edited by: Henry Hsu on Oct 26, 2010 4:40 AM
    Edited by: Henry Hsu on Oct 26, 2010 4:54 AM

  • Re: Upgrading ECC 6.0 to EHP4 on Linux 32 bit.

    Hi gurus,
        Am new to SAP. Basis. i've started a project on "Test upgrade of PRD server ECC 6.0 to EHP4"  I finished installtion of SAP ECC 6.0 and took backup from PRD server and restored it in my test server. now i've to through my upgradation phase.
               Now i configured in solution manager and started maintenance optimizer. Now my problem is wen i configured in maintenance optimizer for the first time, i choose in 2. select files phase i chose the following options.
        2. select files  --> calculate files automatically-Recommended.
                               --> Enhancement package
    2.1 choose stack--->  i tick 'media' only.
    2.3 stack dependent files----> its selected some files showing totally 623 files ready to be download in download basket.
    but due to collapse in download manager i missed some files..so i started the maintenance optimiser again in a new transaction. but i can find its selected some files by default including 'media; option with other options also. in the next phases also it defaultly selected all the files required for upgradation. but this time i can see only 298 files ready for downloading.. i dono which one is correct one. shall i go the first transaction or he new transaction.. please help me guys..
    Thanks and regards,
    Santhosh Kumar.

    Hi,
    Better make new transaction and choose again otherwise if you will miss some file then you will get error in upgrade.
    Thanks
    Sunny

  • IS-Retails on ECC 6.0 with ehp4

    HI,
    I am looking to install IS-Retails on ECC 6.0 with ehp4
    Can any one guide me exact location to find the component and also installation procedure.Thanks
    Best Regards
    Narendar

    Hello,
    Goto Service Market place and goto download page. Then click on Search for Installations and Upgrades under Installations and Upgrades.
    In the search tab fill with EA-RET.
    http://help.sap.com/saphelp_erp2005/helpdata/en/43/6880cbb88f297ee10000000a422035/frameset.htm
    In the above link check under Logistics-general for more details for IS-Retail.
    Regards,
    Yoganand.V

  • Error AFAB after upgrade ECC 6

    Dear All,
    My company just upgrade ECC 6, but when I test it with AFAB,
    test run
    System gives message:
    T E S T R U N was terminated Refer to the error log
    No documents were created in this run
    Error Log:
    Number range 30 has not been created for document type AF.
    Message no. AA738
    Diagnosis
    No valid number range interval has been created for document type AF.
    Procedure
    Specify an interval for number range 30 in the year 999 for company code .
    Please help me.
    Thanks
    Ocep

    Hi,
    Kindly check  in transaction FBN1 for Company code and number range 30 whether external number flag tick is marked or not. If it is marked , remove the same.
    In ECC 6 above mentioned tick for external number flag is not required.
    and later maintain number ranges for current period.
    Hope this help you.
    Regards,

  • ECC 6.0 with EHP4 fresh Installation

    Hello Gurus,
    A fresh ECC 6.0 with EHP4 needs to be installed on Wnidows + Oracle Platform, please let me know which of the following path should be followed?
    1. SAP NW 7.0 installation (without EHP1)  --> EHP 1 installation --> EHP4 Installation
    2. SAP NW 7.0 with EHP1 installation --> EHP4 installtion
    3. SAP NW 7.0 installation --> EHP4 installation
    The other way to ask this questions is what are the dependencies between NW7.0 (ECC 6), EHP1 and EHP4?
    Please let me know which of the above options is feasible and recommended. Please let me know a better option if its not present in the above options.
    Regards,
    Saurabh.

    Hi,
    refer the following SAP note 1143022.
    Regards
    Manohar

  • How to upgrade ECC 6.0 SR2 to EHP4..

    Dear all,
    Currently we are on ECC 6.0 SR2 ABAP stack only
    We are planing to upgrade to EHP4 .
    Is Java stack mandatory for EHP4 ? If yes what in documents  i need to go through....
    If JAVA stack is not required, How hosuld i update to EHP4.
    Regards
    rahul

    If Java is required or not depends on your scenario. If you only use the ABAP part now and you don't plan any other scenarios then Java is not required.
    The guide can be found at
    http://service.sap.com/instguides
    --> SAP Business Suite Applications
    -->  SAP ERP
    --> SAP ERP 6.0
    --> SAP enhancement packages for SAP ERP 6.0
    --> SAP enhancement package 4 for SAP ERP 6.0
    Read here
    Must Know document
    How to install SAP Enhancement Package 4 guide
    There is a separate forum here for EHP installations:
    /community [original link is broken]
    Markus

  • After upgrade ECC to EHP4 errors appears (STMS tp check)

    Hi!
    Configuration
    Two dialog instance. Central instance works on cluster node. DI works on standalone server. Message server and enq server is separate instanse(ASCS) installed on windows cluster
    Check TP
    'Could not start transport control program tp RFC error: timeout during allocate / CPIC-CALL:'ThSAPCMRCV''
    This error happens only on DI installed on standalone server. If checks tp is started on central instance than error does not appear.
    dev_rfc.trc
    ERROR file opened at 20120224 135020 Russian Standard Time, SAP-REL 701,0,150 RFC-VER 3 1260209 MT-SL
    T:9800 Error in program 'C:\usr\sap\QUA\D00\exe\tp': ======> CPIC-CALL: 'CMACCP : rc=20
    LOCATION CPIC (TCP/IP) on local host with Unicode
    ERROR partner 'clusterpqua.internal.russ-ergo.com:3300' not reached
    TIME Fri Feb 24 13:50:20 201
    RELEASE 701
    COMPONENT NI (network interface)
    VERSION 38
    RC -10
    MODULE nixxi.cpp
    LINE 2845
    DETAIL NiPConnect2
    SYSTEM CALL connect
    ERRNO 10061
    ERRNO TEXT WSAECONNREFUSED: Connection refused
    COUNTER 1

    Hi,
    ERROR partner 'clusterpqua.internal.russ-ergo.com:3300' not reached
    ERRNO 10061
    ERRNO TEXT WSAECONNREFUSED: Connection refused
    Check few points:
    1. Is DI installation is domain installation ?
    2. Is DI standalone server is a member of domain ?
    3. Are you able to ping and connect (telent)  to system "clusterpqua.internal.russ-ergo.com" on port 3300 ?
    4. Are you able to access share "
    clusterpqua\sapmnt\trans" from DI Server ?
    Hope, it will help to resolve the issue...
    Regards.
    Rajesh Narkhede

  • /ASU/UPGRADE after the ECC6.0 EHP4 upgrade Finalization step

    Hello all,
    Needed some information on the ASU step in Postprocessing phase of the upgrade. We are upgrading form 4.7 to ECC 6 EHP4 and we are in the Postprocessing phase. The current step is to perform the /ASU/UPGRADE, and I wanted to know if I need to stop te upgrade to perform this step or I can proceed with the rest of the Post processing and Finalization phase and still do the /ASU/UPGRADE step. Please advice ASAP.
    Thanks
    Deepak

    Hello,
    we are in upgrade to ECC 6.0 EHP4 too and now at phase ASU/UPGRADE.
    Note 1000009 advices to make adjusments in client 000, but we are working in client 100. And the procuced task list is client-dependent. So things like budget period or wage types are usually in working client.
    Which is the correct client to use?
    Regards,
    Julia

  • Question about upgrading ECC 6.0 to EHP 4 and NW 7.0 to EHP 1

    Hi All,
       I have read articles about installing Enhancement Packs. How ever I am a little confused.
    We are currently on ECC 6.0 and NW2004s. For Portal also we are on Nw2004s (EP 7.0 SP 16)
    We want to install EHP4 for our ECC system. Do we have to install EHP1 for our NW side? Does this mean we need to upgrade our portal also to EHP 1?
    Also, do we need to update our ESS and MSS business packages also?
    I have an OSS note open about a VC issue. They have recommended us to upgrade to SP 18. if we install EHP 1 on Portal, do we still need to upgrade to SP 18 or all previous SPs are included in EHP1?
    I really appreciate your help on this. If you can refer me to some docs which give more detail on EHP 1 for NW, I will greatly appreciate it.
    Thanks in Advance
    Preet

    Hai,
    Check the below link.....
    SAP Enhancement Package 1 for SAP NetWeaver 7.0
    /docs/DOC-7741#section4 [original link is broken]
    Regards,
    Yoganand.V
    Edited by: Yoganand Vedagiri on Feb 7, 2009 1:06 PM

  • Impact in portal for Upgrade ECC 5.0 SP04 to ECC 6.0

    We are upgrading the ECC system from SAP_APPL 500 SP04(ECC 5.0) to SAP_APPL 600 EHP4 SP10(ECC 6.0) . I need to know what will be the impact on Portal 6.4 VErsion which is having ESS/MSS and BI integrated .

    Hi GjEPCons ,
    The Ess/mss application are standard some  application webdynpro java and web dynpro abap so nothing happen upgrade one version to another version in backend  and bi reports also but we can check the system object if case any thing happen ,
    Ecc 5.0 and Ecc 6.0 nothing more change some features have add in Ecc 6.0 so we dont bother  tome to upgrading .
    Upgrade from ECC 5.0 to ECC 6.0
    Hope this information help s to you
    Thanks&Regards,
    G.srinu

  • Failed to upgrade from ERP 6.0 EHP4 to EHP5

    Dear SAP Gurus,
    we are running ERP 6.00 with EHP4 (HCM-component) based on Windows 2003
    SP2 X64 and SQL Server 2005 SP4 (64-bit).
    We are using SAP Kernel Unicode 7.01 PL 133 (64-bit).
    We intend to upgrade from EHP4 to EHP5.
    Upon running SAPehpi, we encountered issue which stopped us from
    proceeding with the upgrade.
    Case 1: Direct upgrade to 605
    The upgrade failed on PREP_INPUT/VERSCHK_INI with error message: The
    following combination is not supported (SAP_APPL 600, SAP_BASIS 701,
    SAP_ABA 701).
    Case 2: Upgrade SAP_APPL component from 600 to 604 (due to the above
    error message)
    The upgrade failed on PREP_INPUT/VERSCHK_INI with error message:
    Release '701' of component SAP_BASIS is too new.
    Case 3: upgrade via SAINT is not supported by SAP. When uploading the
    Stack XML file, we got error saying that the stack is not supported.
    Attached is the complete list of the current SP Level of Installed
    components.
    Please advise on how we can perform the upgrade to EHP5.
    Many thanks in advance.
    regards,
    Denny

    The thing is Solution Manager was able to produce the XML file during the previous upgrade to 604 (the one without SAP_APPL 604).
    So how can it not be supported by SAP?
    If it is not supported by SAP, how can I proceed from here?
    Component Software C SP-Level Support Package Short description of the component
    SAP_ABA 701 0007 SAPKA70107 Cross-Application Component
    SAP_BASIS 701 0007 SAPKB70107 SAP Basis Component
    PI_BASIS 701 0007 SAPK-70107INPIBASIS Basis Plug-In
    ST-PI 2008_1_700 0003 SAPKITLRD3 SAP Solution Tools Plug-In
    SAP_BS_FND 701 0008 SAPK-70108INSAPBSFND SAP Business Suite Foundation
    SAP_BW 701 0007 SAPKW70107 SAP Business Warehouse
    SAP_AP 700 0021 SAPKNA7021 SAP Application Platform
    WEBCUIF 700 0008 SAPK-70008INWEBCUIF SAP WEBCUIF 700
    SAP_APPL 600 0018 SAPKH60018 Logistics and Accounting
    SAP_HR 604 0035 SAPKE60435 Human Resources
    EA-IPPE 400 0018 SAPKGPID18 SAP iPPE
    EA-APPL 600 0018 SAPKGPAD18 SAP Enterprise Extension PLM, SCM, Financials
    EA-DFPS 600 0018 SAPKGPDD18 SAP Enterprise Extension Defense Forces & Public Security
    EA-FINSERV 600 0018 SAPKGPFD18 SAP Enterprise Extension Financial Services
    EA-GLTRADE 600 0018 SAPKGPGD18 SAP Enterprise Extension Global Trade
    EA-HR 604 0035 SAPK-60435INEAHR SAP Enterprise Extension HR
    EA-PS 600 0018 SAPKGPPD18 SAP Enterprise Extension Public Services
    EA-RETAIL 600 0018 SAPKGPRD18 SAP Enterprise Extension Retail
    FINBASIS 600 0018 SAPK-60018INFINBASIS Fin. Basis
    ECC-DIMP 600 0018 SAPK-60018INECCDIMP DIMP
    ERECRUIT 600 0018 SAPK-60018INERECRUIT E-Recruiting
    FI-CA 600 0018 SAPK-60018INFICA FI-CA
    FI-CAX 600 0018 SAPK-60018INFICAX FI-CA Extended
    INSURANCE 600 0018 SAPK-60018ININSURANC SAP Insurance
    IS-CWM 600 0018 SAPK-60018INISCWM Industry Solution Catch Weight Management
    IS-H 600 0023 SAPK-60023INISH SAP Healthcare
    IS-M 600 0018 SAPK-60018INISM SAP MEDIA
    IS-OIL 600 0018 SAPK-60018INISOIL IS-OIL
    IS-PS-CA 600 0018 SAPK-60018INISPSCA IS-PUBLIC SECTOR CONTRACT ACCOUNTING
    IS-UT 600 0018 SAPK-60018INISUT SAP Utilities/Telecommunication
    LSOFE 600 0018 SAPK-60018INLSOFE SAP Learning Solution Front-End
    SEM-BW 600 0018 SAPKGS6018 SEM-BW: Strategic Enterprise Management
    ST-A/PI 01M_ECC600 0001 SAPKITAR7F Application Servicetools for ECC 600-605
    VIRSAHR 530_700 0012 SAPK-53312INVIRSAHR SAP GRC Access Controls 5.3 for 700 HR S
    VIRSANH 530_700 0014 SAPK-53314INVIRSANH SAP GRC Access Controls 5.3 for 700 HR a

  • Need your help to upgrade ECC 6.0 SPS 6 to Current

    Hi gurus,
    I know there are lots of document but not able to reach any decision. I am kind of confusion with what to do. I am thinking I will get my answer with the experts in this forum.
    Current environment: SAP ERP ECC 6.0 SPS 6 Kernel 700 release and level 179 windows NT x64 and MS SQL 8.00 179 level
    Requirement: update the environment to current.
    With research either can go from SPS 6 to SPS 17
    OR
    update to SPS13 and then upgrade to EHP4 (not quite sure about this)
    But if you go EHP4 might require hardware or memeory or other changes.
    Question:
    Detail Steps to
    What are the steps required and time to complete the upgrade going from SPS 6 to SPS 17?
    What are the steps required and time to complete the upgrade going from SPS 6 to EHP4?
    Everybody might say this depend on the data and other customization etc.
    But still there will be standard steps and time which will help me to complete the process.
    Please let me know the steps and process to complete this.
    what are the steps we need to adapt in order to Minimize System downtime.
    Thanks in Advance.
    Krish

    Krish,
    SAP Course ADM326 include the content for ECC enhancement package upgrade, probably it's worth to you to start from the training course if you hate to read guides in SAP service marketplace.
    Cheers,
    Denny

  • Install  ERP ECC 6.0 with EHP4 and JAVA stack (usage type)

    Hi all,
    I need to install ECC with EHP4 and also JAVA stack.
    I know that I have to install 2 stacks with different SID and oracle homes, firts I have to install ABAP stack and then the JAVA stack, but wich usage type should I choose for JAVA STACK?
    What I would like to have in my new installation would be the same usage type for JAVA stack like ERP 6.0 SR3 ABAP+JAVA stacks.
    What should I choose?
    Regards
    Thanks

    Hello,
    SAP ECC 6.0 allows ABAP and JAVA but EHP4 this feature is not.
    One thing I can suggest if you install ABAP stack first, it will initiates (even different SIDu2019s) the JAVA stack also.
    So JAVA stack having a protection with ABAP, because you know JAVA stack is a very sensitive and time consuming one when you want to start are stop.
    So you can do this sequence
    Suresh

  • ERROR in ADD-ON conflict phase while upgrading ECC 6.0 system

    Hi all,
    I am having ECC 6.0 system and am upgrading its SAP-APPL component to 603 patch level 03. I was having SAP-APPL 603 but at patch level 0, i checked for all dependencies and defined the queue in SPAM and it showed all green (OK) for SAP-APPL and so i started but i faced error in add-on coflict phase. It said CRT needed for ADD-ON FICAX release 603. I searched alot but i cant find it on market place. This conflict occured for SAP-APPL 603 patch level 01 it said either include CRT as mentioned above or remove SAP-APPL 60301. Please help me out.

    The conflict check detected conflicts between the Add-On FI-CAX release 603 and the OCS Package SAPKH60301.
    The conflict check detected conflicts between the Add-On FI-CAX release 603 and the OCS Package SAPKH60302.
    The conflict check detected conflicts between the Add-On FI-CAX release 603 and the OCS Package SAPKH60303.
    Check the support packs of components FI-CAX on Service Market place, I think FI-CAX is dependant on SAPKH603301 and others so you can check the import condidtions of FI-CAX on service marketplace and update FI-CAX first then only you would be able to update patch of SAPKH60301
    Regards
    Subhash

Maybe you are looking for