<u>Requirement</u>
Creation of the purchase orders/Contracts should be allowed or blocked based on some vendor (classification) characteristics.
Purchase orders and contracts can be created for materials and services. For each line item (material/service) in Purchase order, the vendor characteristics should be checked. Further, each service item can have multiple service line items and check should be performed for each of these service line items.
<u>Transaction codes</u>
ME21, ME22, ME23, ME21N, ME22N, ME23N, ME31k, ME32k, ME33K
<u> Options tried out</u>
1. The PROCESS_ITEM method in the BADI ME_PROCESS_PO_CUST can be used to check the item data. The checks can be performed in this method. But, this BADI works only for enjoy transactions - ME21N, ME22N and ME23N.
2. The user exit EXIT_SAPMM06E_013 in the enhancement MM06E005 can be used. This user exit will be triggered on press of save for Purchase orders and contracts. However, the checks need to be performed for all the service line items also. The service line item details are not available (accessible) in the user-exit EXIT_SAPMM06E_013.
3. The user exit EXIT_SAPMM06E_013 in the enhancement MM06E005 can be used. This user exit will be triggered on press of save for Purchase orders and contracts. To check the service line items EXIT_SAPLMLSP_031 can be used. But the user exit EXIT_SAPLMLSP_031 does not work for contracts ME31k, ME32k, and ME33k.
<b>Is there a method to get the service line item details into the user-exit EXIT_SAPMM06E_013 so that i can continue with option 2 mentioned above. 
Please suggest any other method that will help solve this issue.</b>
Your help is highly appreciated.
regards,
prasad

Hi Prasad,
I am not sure if such exit would be available however I can suggest an alternative which will work just in case you are working on ECC 6.
From this release onwards we have a new technique call Enahncement-options which allows us to enehance the standard functionality. Look for any Enhancement-option avaiable on clicking save button by putting a break-point at run time on all 'Enhancement' statements. If anyone exits which i am sure will then you can do an implementation for the same and implement the required functionality.
Hope this helps and revert for more clarifications if any.
<b>Always reward points to useful suggestion.</b>
regards,
Vikas

Similar Messages

  • User based authorization to create Purchase Orders out of Purchase Req.?

    Hello,
    I have the following requiment for my client:
    User based authorization to create Purchase Orders out of Purchase Req.?
    I am told the same can be achieved using same standard menu path in IMG/Customizing.
    Please advise with the menu path and detials, Usefull answers will be rewarded.
    Thanks

    Using OMET Function Authorization, you can restrict users to create Purchase orders without Purchase Reqn.
    Using OMET trxn code Create one Function Authorixation Called pr and in General Parameters tab Select the Field Selection and in Possible reference Objects Tab Mark the With ref to Prs check box and save.
    Next, you've got to associate via SU01 
    Click Parameters, insert a new parameter id EFB to the authorization code. 
    Type in Parameters value you want e.g. XX 
    You have to assign the control for ALL the SAP buyers via thier SAP users id.
    Logoff and login again. Then try to create a Purchase Order without a reference.
    From Next time whenever you try to create with out referring PR it will not allow you to Save PO.
    Regards,
    Ashok

  • Procure-to-Pay Scenario. Create Purchase Order

    Hello Experts: I have a question regarding the Procure-to-Pay scenario and the Create PO functionality.
    we are in SRM 7.0, Classic Scenario and we try to implement the Procure-to-Pay functionality as it is described in OSS note 1263876 "SAP SRM: Configuration of Procure-to-Pay Scenario".
    Our idea is to transfer Purchase Requisitions from ECC6 to SRM using the CPPR application. But we will also take advantage of the integration with MM provided with this scenario.
    If you are familiar with this, you will already know that, using the harmonized role for operational purchaser (ERP/SRM) an end user can create Purchase Orders in the backend. Our question is related to this functionality.
    Using this role, the buyer can select Purchasing Documents under the detailed navigation area and, from there, he will have access to create Shopping carts, Purchase requisitions, Purchase Orders and Purchase order responses.
    If we select Create Purchase Order, the application "Purchase Order: New" gets opened. Here we have to select the system where we want to create the new PO: either SRM or ECC6. Our first question is: As we are running a Classic scenario, why are we asked to select between SRM and ECC6?. It should be only ECC6, shouldn't be?
    In any case, the SRM systems gets selected by default when we open "Purchase Order: New" appl. and bellow this field, you can see the PO types customized in SRM. If we change the system to ECC6 we see the following: "Number of purchase order types: 0" . So, no PO types are available. this is the second question: why do we have 0 PO types to be created when we select the ECC6 system? is there a missing customizing where we have to define which document types are vaialable to create POs in ECC6 from SRM Portal?.
    To summarize: only ECC6 should be proposed as system to create POs (as we are running a Classic Scenario) and there should be ECC6 PO types available to create such POs in the ECC6.
    Can you please tell us what is still missing in our configuration? Any help will be more than welcome
    Many thanks in advance for your valuable help
    Best regards
    Valentí

    The purpose of MRP run is to make sure that you always have enough stock.
    An order to cost center will not increase stock.
    Means: MRP is not able to create requisitions for cost center consumption. If you change a requisition created by MRP to be ordered to a cost center, then the next MRP run will create a new requisition to stock.

  • [Request] Special user-exit we need during creating purchase order

    Hi, Gurus!
    We need to make specific User-Exit during creating Purchase order.
    When user creates/change a PO document (ME21N/22N), SAP has to check the u2018CUSTOMERu2019 filed whether it is BLANK or NOT in Delivery Address tab at ITEM LEVEL.
    If there is no value in that field, system will automatically input right value with useru2019s business logic.
    Thatu2019s what we want to implement in the future.
    If you have any solution or recommendation for this, Please help us.
    I really appreciate your help in advance.
    Best Rgds;
    Ian

    For checking user exit - SMOD, you need to activate this exit via CMOD
    For Badi - SE18 to check & SE19 to implement
    Take the help of your abaper, give him / her your logic.
    Hope the above answers your query.
    Regards,
    Vivek

  • Search user-exit for create purchase order

    Hi all,
    i'm searching the user-exit (or BADI) for create purchase order.
    Thanks for help.

    Hi CECG,
    GOTO SMOD and press F4
    then Click on  Information system
    and in the Package name give as     ME
    and press enter.
    you will get all user exits for Purchase Orders
    Hope this solves your problem.
    Please reward points if found helpful.
    Thanks and regards,
    Rajeshwar.

  • User Exit for Purchase Order Release Strategy

    Hi,
    I am a little new to this, how do I search for a user exit for purchase order release strategy (TCode ME29N).
    Thanks in advance.
    Mick

    Hi
    Check the following Exits and BADI for Pur Requisition
    Enhancement
    MEVME001 WE default quantity calc. and over/ underdelivery tolerance
    MM06E001 User exits for EDI inbound and outbound purchasing documents
    MM06E003 Number range and document number
    MM06E004 Control import data screens in purchase order
    MM06E005 Customer fields in purchasing document
    MM06E007 Change document for requisitions upon conversion into PO
    MM06E008 Monitoring of contr. target value in case of release orders
    MM06E009 Relevant texts for "Texts exist" indicator
    MM06E010 Field selection for vendor address
    MM06E011 Activate PReq Block
    MMAL0001 ALE source list distribution: Outbound processing
    MMAL0002 ALE source list distribution: Inbound processing
    MMAL0003 ALE purcasing info record distribution: Outbound processing
    MMAL0004 ALE purchasing info record distribution: Inbound processing
    MMDA0001 Default delivery addresses
    MMFAB001 User exit for generation of release order
    MRFLB001 Control Items for Contract Release Order
    AMPL0001 User subscreen for additional data on AMPL
    LMEDR001 Enhancements to print program
    LMELA002 Adopt batch no. from shipping notification when posting a GR
    LMELA010 Inbound shipping notification: Transfer item data from IDOC
    LMEQR001 User exit for source determination
    LMEXF001 Conditions in Purchasing Documents Without Invoice Receipt
    LWSUS001 Customer-Specific Source Determination in Retail
    M06B0001 Role determination for purchase requisition release
    M06B0002 Changes to comm. structure for purchase requisition release
    M06B0003 Number range and document number
    MEQUERY1 Enhancement to Document Overview ME21N/ME51N
    MELAB001 Gen. forecast delivery schedules: Transfer schedule implem.
    MEFLD004 Determine earliest delivery date f. check w. GR (only PO)
    MEETA001 Define schedule line type (backlog, immed. req., preview)
    ME590001 Grouping of requsitions for PO split in ME59
    M06E0005 Role determination for release of purchasing documents
    M06E0004 Changes to communication structure for release purch. doc.
    M06B0005 Changes to comm. structure for overall release of requisn.
    M06B0004 Number range and document number
    Business Add-in
    ME_PROCESS_REQ_CUST Enhancements for Processing Enjoy PReqs: Customer
    ME_PROCESS_REQ Enhancements for Processing Enjoy PReqs: Internal
    ME_PROCESS_PO_CUST Enhancements for Processing Enjoy Purchase Order: Customer
    ME_PROCESS_PO Enhancements for Processing Enjoy Purchase Order: Intern.
    ME_PROCESS_COMP Processing of Component Default Data at Time of GR: Custome
    ME_PO_SC_SRV BAdI: Service Tab Page for Subcontracting
    ME_PO_PRICING_CUST Enhancements to Price Determination: Customer
    ME_PO_PRICING Enhancements to Price Determination: Internal
    ME_INFOREC_SEND Capture/Send Purchase Info Record Changes - Internal Use
    ME_HOLD_PO Hold Enjoy Purchase Orders: Activation/Deactivation
    ME_GUI_PO_CUST Customer's Own Screens in Enjoy Purchase Order
    ME_FIELDSTATUS_STOCK FM Account Assignment Behavior for Stock PR/PO
    ME_DP_CLEARING Clearing (Offsetting) of Down Payments and Payment Requests
    ME_PURCHDOC_POSTED Purchasing Document Posted
    SMOD_MRFLB001 Control Items for Contract Release Order
    EXTENSION_US_TAXES Extended Tax Calculation with Additional Data
    ARC_MM_EKKO_WRITE BAdI: Enhancement of Scope of Archiving (MM_EKKO)
    ARC_MM_EKKO_CHECK BAdI: Enhancement of Archivability Check (MM_EKKO)
    MM_EDI_DESADV_IN Supplementation of Delivery Interface from Purchase Order
    MM_DELIVERY_ADDR_SAP Determination of Delivery Address
    ME_WRF_STD_DNG PO Controlling Reminder: Extension to Standard Reminder
    ME_TRIGGER_ATP Triggers New ATP for Changes in EKKO, EKPO, EKPV
    ME_TRF_RULE_CUST_OFF BADI for Deactivation of Field T161V-REVFE
    ME_TAX_FROM_ADDRESS Tax jurisdiction code taken from address
    ME_REQ_POSTED Purchase Requisition Posted
    ME_REQ_OI_EXT Commitment Update in the Case of External Requisitions
    ME_RELEASE_CREATE BAdI: Release Creation for Sched.Agrmts with Release Docu.
    ME_DEFINE_CALCTYPE Control of Pricing Type: Additional Fields
    ME_CHANGE_OUTTAB Enrich ALV Output Table in Purchasing
    ME_CHANGE_CHARACTER Customer-Specific Characteristics for Product Allocation
    ME_CCP_DEL_DURATION Calc. of Delivery Duration in CCP Process (Not in Standard)
    ME_CCP_BESWK_AUTH_CH BAdI for authorization checks for procuring plant
    ME_CCP_ACTIVE_CHECK BAdI to check whether CCP process is active
    ME_BSART_DET Change document type for automatically generated POs
    ME_BAPI_PR_CREATE_02
    ME_BAPI_PR_CREATE_01
    ME_BAPI_PO_CREATE_02
    ME_BAPI_PO_CREATE_01
    ME_BADI_DISPLAY_DOC BAdI for Internal Control of Transaction to be Invoked
    ME_ACTV_CANCEL_PO BAdI for Activating the Cancel Function at Header Level
    MEGUI_LAYOUT BAdI for Enjoy Purchasing GUI
    ME_CHECK_ALL_ITEMS Run Through Items Again in the Event of Changes in EKKO
    ME_COMMTMNT_REQ_RE_C Check of Commitment Relevance of Purchase Requisitions
    ME_COMMTMNT_REQ_RELE Check of Commitment Relevance of Purchase Requisitions
    ME_COMMTMNT_PO_REL_C Check for Commitment-Relevance of Purchase Orders
    ME_COMMTMNT_PO_RELEV Check for Commitment-Relevance of Purchase Orders
    ME_COMMITMENT_STO_CH BadI for checking if commitments for STOs are active
    ME_COMMITMENT_RETURN Commitment for return item
    ME_CIP_REF_CHAR Enables Reference Characteristics in Purchasing
    ME_CIP_ALLOW_CHANGE Configuration in Purchasing: Changeability Control
    ME_CIN_MM06EFKO Copy PO data for use by Country version India
    ME_CIN_LEINRF2V BADI for LEINRF03 excise_invoice_details
    ME_CIN_LEINRF2R BADI for CIN India - Delivery charges
    ME_CHECK_SOURCES Additional Checks in Source Determination/Checking
    ME_CHECK_OA Check BAdI for Contracts
    Reward points if useful
    Rgds,
    Naren

  • SRM 7.0 Create Purchase Order

    Hi  SRM Gurus,
    We  have upgraded from SRM 3.to SRM 7.0.
    Our scenario is Extended classic scenario.
    click  on create  Purchase order. Error message is displayed
    "table does not contain any data"
    I have checked in Define Transaction type for purchase order all the details are there.
    Define Transaction type is working for contract,Rfx ,and auction.
    It is not working for Purchase order. Which table to check
    Can you please give your inputs
    Regards
    G.Ganesh Kumar

    Hi Muthu/Viru
    Thanks for the suggestion
    I am in SRM 7.0
    This issue is resolved and I got another Issue
    I have tried to convert the  existing SC to a PO . it is not working.
    Created a shopping cart ,approved.
    Now I converted the SC to P.O. Now all the transaction types were appearing
    converted to P.O. but one issue " Please clear the price (or) Set the invoice expected indicator
    I could not able to find this in the P.O (SRM 7.0)
    Please help
    Regards
    G.Ganesh Kumar

  • User settings in Purchase Order.

    Hi,
    I am trying to do some user settings in PO.
    When I go to t.code ME21N and click on Default values - > More field.
    I changed the positions of Plant and Storage location as per my requiremnt and Save it. But that is not happening, when I go back and see the settings, I get the original setting.
    Why do it gets restored to the original setting.
    Please help me how to do the default settings.
    Thanks and regrads,
    Sheetal

    Even if you Set Default Plant & Stor Locn in Personal Settings The System will take the Reference Document Plant & Stor Locn.
    That is, If you are Creating Purchase Order with Reference to Some Other Document for Eg : PR then System will Default PR Values in to PO ME21N.
    If you want Your Default Values whcih you have set in Personal Settings come into PO then go to Personal Setting and Give Plant & Storage Location and Put Tick Mark aginst Always Propose Options.
    Always Propose
    Causes the system to adopt the default values maintained in the Personal Settings in the purchase order that is to be created.
    Use
    If you set the indicator, the default values maintained here are adopted in the new purchase order even if the system might be able to determine other default values (e.g. from a reference document). That is to say, the values maintained here take priority.
    If you do not set the indicator but have maintained default values in your Personal Settings, these values are considered only if the system cannot determine any other default values (e.g. from a reference document, contract, info record etc.)
    Read F1 Help on Always Propose for Clarifications.
    Regards,
    Ashok

  • Could not create Purchase Order Stock Transfer Order

    Hi Expert!
    Need your help.
    User could not make Could not create Purchase Order Stock Transfer Order for new plant 1075 & 1076 at P05 with error message Not posible to determine shipping data for material. Our new vendor are 510022060 for new plant 1075 and 510022061 for new plant 1076.
    The problem was caused by the missing STO setup for these two plant 1075 and 1076, as no customer code being referred.
    Now i got the customer number for these two plants but how to set it up in configuration? Please guide me step by step.

    Hi Crystal,
    The following customising need to be carried out for Inter Company Stock Transfer.
    Path : sproMaterials ManagementPurchasing-Purchase OrderSet up Stock Transport Order
    Define Shipping Data for Plants :
    For the Supplying plant (1) the Sales Org data to be maintained.
    For the Receiving plant (2) the Customer No to be maintained.
    Create Checking Rule - U can use existing one Eg : B
    Define Checking Rule : Use Standard one Eg :01 linked to B.
    Assign Delivery Type and Checking Rule -- For the Supplying Plant (1) and document type NB use the delviery type NLCC and Checking Rule B.
    Assign Document Type, One-Step Procedure, Underdelivery Tolerance :
    For the supplying Plant (1) and Receving Plant (1) ; assign the document type : NB.
    Points to be noted :
    The Material should exists in both the plants ( 1 & 2 ) with the sales view maintained . Note that the Loading grp / Transporting Grp is mantaory in Sales Views.
    The Vendor is to be assigned to the supplying Plant (1 ) in Purchasing View of Vendor Master.
    For that click on Extras - Add Purchasing data in Purchasing view of Vendor Master (XK02 )
    Do maintain the customer in Control data of Vendor Master.
    Do maintain the Vendor in Control data of Customer Master.
    Also note that shipping conditions are maintained in the Customer Master . The same can be found in Sales Area - Shipping Tab.
    Shipping Point determination :
    SPROLogistics ExecutionShippingBasic Shipping FunctionsShipping Point and Goods Receiving Point Determination--Assign Shipping Points ( For a particular Shipping condition/ Loading Grp /Plant - the shipping point is assigned ).
    Regards
    Ramesh Ch

  • Issue while creating Purchase order (ME21N)

    Hi Friends,
    Hope U Have a Good Day...
    My issue is while creating purchase order , I enter vendor and in org.data tab I enter Pur.Org,company code and purchase group. After entering these values if I check in communication tab, the sales person and telephone fields are filled with corresponding data.
    Now my requirement is after entering Pur.Org, Company code and purchase group, and if I go and check in Communication tab, these two fields ( sales person, telephone ) should be blank.
    Please help me in this issue...
    Thanks & Regards
      Ganesh Reddy

    Hi Ganesh,
    This is being fetched frm the vendor master and if u wan this field to be blank
    Then u hav to remove those data frm the vendor master .
    Put tat vendor, comp code n purchase org
    Then select pur org data alon - >chk in purch data
    u can find tat sales person n telp no being appeared in the PO
    lemme know if u hav any prob in getting tat .

  • Update was terminated while creating purchase order from ME21N

    Hi Experts,
    We are getting this dump when try to create purchase order from ME21N;
    Our system ECC 6.0 and IS-AFS (Apparel & Footwear Solution) V600 component has installed,
    How can we prevent this error,
    Regards
    Here is the dump and sm21 log,
    Runtime Errors         LOAD_PROGRAM_NOT_FOUND
    Exception              CX_SY_PROGRAM_NOT_FOUND
    Date and Time          10.10.2008 10:22:03
    Short text
         Program "RMCMS431 " not found.
    What happened?
         There are several possibilities:
         Error in the ABAP Application Program
         The current ABAP program "SAPLMCS4" had to be terminated because it has
         come across a statement that unfortunately cannot be executed.
         or
         Error in the SAP kernel.
         The current ABAP "SAPLMCS4" program had to be terminated because the
         ABAP processor detected an internal system error.
    What can you do?
         Note down which actions and inputs caused the error.
         To process the problem further, contact you SAP system
         administrator.
        Using Transaction ST22 for ABAP Dump Analysis, you can look
        at and manage termination messages, and you can also
        keep them for a long time.
    Error analysis
        An exception occurred that is explained in detail below.
        The exception, which is assigned to class 'CX_SY_PROGRAM_NOT_FOUND', was not
         caught in
        procedure "TMC2F_FROUT_CALL" "(FORM)", nor was it propagated by a RAISING
         clause.
        Since the caller of the procedure could not have anticipated that the
        exception would occur, the current program is terminated.
        The reason for the exception is:
        On account of a branch in the program
        (CALL FUNCTION/DIALOG, external PERFORM, SUBMIT)
        or a transaction call, another ABAP/4 program
        is to be loaded, namely "RMCMS431 ".
        However, program "RMCMS431 " does not exist in the library.
        Possible reasons:
        a) Wrong program name specified in an external PERFORM or
           SUBMIT or, when defining a new transaction, a new
           dialog module or a new function module.
        b) Transport error
    How to correct the error
        Check the last transports to the R/3 System.
        Are changes currently being made to the program "SAPLMCS4"?
        Has the correct program been entered in table TSTC for Transaction "ME21N "?
        If the error occures in a non-modified SAP program, you may be able to
        find an interim solution in an SAP Note.
        If you have access to SAP Notes, carry out a search with the following
        keywords:
        "LOAD_PROGRAM_NOT_FOUND" "CX_SY_PROGRAM_NOT_FOUND"
        "SAPLMCS4" or "LMCS4F10"
        "TMC2F_FROUT_CALL"
        If you cannot solve the problem yourself and want to send an error
        notification to SAP, include the following information:
        1. The description of the current problem (short dump)
           To save the description, choose "System->List->Save->Local File
        (Unconverted)".
        2. Corresponding system log
           Display the system log by calling transaction SM21.
           Restrict the time interval to 10 minutes before and five minutes
        after the short dump. Then choose "System->List->Save->Local File
        (Unconverted)".
        3. If the problem occurs in a problem of your own or a modified SAP
        program: The source code of the program
           In the editor, choose "Utilities->More
        Utilities->Upload/Download->Download".
        4. Details about the conditions under which the error occurred or which
        actions and input led to the error.
        The exception must either be prevented, caught within proedure
        "TMC2F_FROUT_CALL" "(FORM)", or its possible occurrence must be declared in the
        RAISING clause of the procedure.
        To prevent the exception, note the following:
    sm21 log ;
    Transaction Canceled 00 671 ( LOAD_PROGRAM_NOT_FOUND 20081010102203saptest_TET_00 EYUCE 100
    Update terminated
    > Update key: F39796DD5421F1509233001E0BD601E0
    > Update module: MCE_STATISTICS_UPD_V2
    Run-time error "LOAD_PROGRAM_NOT_FOUND" occurred

    Please follow the oss note 800335
    V2 Update terminations in Purchasing transactions after upgrading or installing AFS 5.0 release.
    Other terms
    AFS, LIS, MIGO, ME22N, OLI3, S433, S431
    Reason and Prerequisites
    AFS Purchasing infostructure S431 is no longer used. S433 is the valid infostructure for the release AFS 5.0.
    Solution
    Please do the following.
    For customers upgrading to AFS 5.0 only:
    > Rebuild Infostructure S433.
    - Goto transaction: OLI3 (Statistical Set up of Infostructures)
    - Info structure to be compile: S433
    - Specify the 'Name of run'.
    - Execute.
    > Please also follow the instructions given below.
    For both Upgrade and Non-upgrade Customers:
    > Create the report 'ZDELS431'.
    - Transaction: SE38
    - Give Program name as ZDELS431.
    - Create (F5).
    - Title : 'Program to delete S431'.
    - Type  : 1 (Executable Program).
    - Status: T (Test Program).
    > Copy the program text from the note and paste in the program.
    > Save and activate the program.
    > Execute the report for all clients in Update mode.
      (Two check-boxes will appear: P_ALL_CL, P_UPDATE.
       Please check both of them).
    This report will delete all the references to infostructure S431.

  • User Exit for Purchase Order Line Items.

    I have been trying to search for a User Exit for Purchase Order Line Items and have been unable to do find anything.  I need to overwrite the Net Price and Pricing Condition on a certain type of material based upon the Pricing Condition for that Line Item which is on the Sales Document.  Any direction you can point me into would be greatly appreciated.  Thanks.

    Thanks for pointing me in the right direction.  I was able to create my first BADI using the PROCESS_ITEM method.  The following link was also very helpful: Re: BADI ME_PROCESS_PO_CUST Method:PROCESS_ITEM

  • Program for Creating Purchase Order with reference to purchase requisition

    Hi ,
    I need to Create purchase Order with reference to  Purchase requisition,
    in my case i need to automize the Process which is happening in MD04,
    Can you please suggest me ?
    Thanks ,
    Murali

    Hi,
    Plz check this link. It will be helpful to you.
    Purchase order creation with reference to PR
    We can also create the PO Using the BAPI_PO_CREATE1 function module.
    In this function module fill up the all necessary Details.
    With details in Item Table we haveto give the Fields PREQ_NO and PREQ_ITEM for each item .
    then it will creates the PO with PREQ.
    Thanks & Regards,
    Sarita Singh Rathour
    Edited by: Sarita Rathour on Aug 3, 2009 7:01 AM

  • Workflow issue when create Purchase Order automaticlly based on Sales Order

    dear experts,
    I got a problem when create purchase order automatically once the Sales Order created, the field ERNAE of the Purchase Order creatd is WF-BATCH, but we want this field to be the user log in the system, like John. Smith
    it seems this is a configuration issue, but i am not familar with workflow, do you experts have any solutions?
    thank you in advance.
    Hongtao

    thank you for you reply my friend.
    yes, i mean the PO creator.
    I just create a SO in VA01, then change the Schedule line category from CN to CP, then SAVE, then Confirm the Delivery Proposal. after all this, the PO will be created automatically by Workflow. Because when I display the PO via ME23N, it displays [Standard PO XXXXX  created by Workflow-System] on the top of the screen.
    But i do not know which workflow is trigered to create the PO. and i tried SWEL like you said, there is no record listed.
    do you have any other suggestions? thank you so much, friend.

  • Create purchase order automatically from Sales order.

    Hi,
    I have ticked  Create purchase order automatically check box in item category TAS and TAB but still not able to generate Purchase Order automatically.???
    any clue.
    thanks/ashu

    You need to have your prerequisites in place for the automated creation of the purchase requisition before the purchase order can be raised:
    You may already have done this, but check that your material has the purchasing information on it (trxn MM02, purchasing tab), that a purchasing information record exists for that material and vendor in that purchasing org (trxn ME12), check that a source list exists as well (trxn ME02). If you have created the source list or purchasing info record after the sales order has been created then you will need to go into trxn ME56 to assign them manually. That should release the PO to be created.
    In standard 3rd party, the PO is created using ME59 (prog RM06BB20), which can be run as a batch job.
    Jon

Maybe you are looking for

  • How can I get the audio only from a home made video

    I have several home videos saved on my iPhone and I am wondering if I can get the audio off of the videos to make an audio CD. I have a PC. Windows 7

  • ITunes 9.0.2 crashes/hangs when syncing

    I bought a 64GB iPod Touch this October, and at first all was well. Since I updated iTunes I have no longer been able to sync my iPod. I'm running iTunes 9.0.2 now, and it works fine until I connect my iPod, at which point iTunes hangs. I don't even

  • Need a query to run Open AP Invoices by "As Of" Date

    Need the "As Of" Date criteria for the query.  I would like to run a list of Open AP Invoices by a specific date: AP Invoices that were OPEN as of the inputted date. (ex. Open invoices as of March 31, 2015 - may have been paid after March 31, 2015 bu

  • Is there a way to NOT add "_X4" to the pdf file name after batch processing conversion?

    whenever i convert a pdf file to a certain profile in batch processing, the pdf file duplicates with the other one having an "_x4" in the filename. i already tried removing in fixups (preflight) but i can't. do you have any ideas? thanks!

  • Can't seem to enable voice chat anymore

    hello folks i just upgraded to an audigy but now when my friend and i try to initiate voice chat through x-fire and msn we can't hear each other at all, where we had no problems before... i've got a p4 3.6ghz with gb of ram and i've disabled my onboa