VERSION 0 IS NOT DEFINED FOR FISACL YEAR 2007,

i am learning SAP PP and i hv ides 4.7,
now WHEN SAVING ORDER i.e DURING COST CALCULATION I GET A MESSAGE THAT VERSION 0 IS NOT DEFINED FOR FISACL YEAR 2007,
ON ANALYSING IT LEADS TO T.CODE OKEV BUT HERE SYSTEM DOES NOT PERMIT TO CHANGE THE VERSION, BUT IN ECC 5.0 IT ALLOWS ,
WHAT IS THE PROBLEM, CAN ANY ONE PL. HELP ME,
analysis of error gives following message:
Activation of the indicator is not permitted
Message no. KT253
Diagnosis
You activated an indicator (Plan, Actual, WIP/results analysis or Variance calculation ) in the basic settings for version 1 in controlling area 1000. However, a higher order of settings (general version definition) prevents you from setting this indicator in version 1.
Note
The following should be taken into account when maintaining a version:
In general version definition you decide whether a version is allowed for
•     Panning (with the Plan indicator)
•     Actual data update (with the Actual indicator)
Note: In Overhead Cost Controlling, actual data is updated in operational version 0.
Actual versions different from 0 are found at present only for delta versions in Activity Based Costing (CO-ABC), and when you work with parallel assesment ( additional versions):
•     A data version from results and WIP determination manages (indicator WIP)
•     Another version from variance determination manages (indicator Variance)
•     A version for exclusive use (field exclusive application)
You must maintain the version basic settings for each controlling area in which you want to update transaction data. General version definition restricts the settings possible for the controlling area:
•     If general version definition does not allow plan and/or actual data update for version, this applies to the version in all controlling areas. If plan and/or actual data updating is allowed for a version in general definition, this can be reset for each controlling area separately (unmark the plan or actual indicator).
•     Delta versions in ABC may not be used for parallel valuations in the actual; the same goes for versions with exclusive applications. In both cases, the valuation fields may not be maintained.
To set indicators WIP/Results- or Variance-determination the following conditions apply:
•     Both indicators may be set only during setup for the controlling area, when they are already established in the higher level general version definition
•     If either indicator is already active in the data bank, then the actual indicator may not be subsequently activated
•     If the actual indicator is inactive and either of these indicators is active, then the valuations in the corresponding versions and in version "000" must agree
•     If the actual indicator is active, then both indicators must be activated
Versions 0 and 1 are used regularly for various purposes by the system, which sets the following limitations/restrictions:
•     Version 0 must always be available. It cannot be used exclusively. The plan and actual indicators must always be active.
•     The actual indicator may not be activated in version 1.
If these conditions are violated during version maintenance, error messages are issued. There are three types of error message:
1. While maintaining the general version definition, you can only make changes if they do not violate the conditions outlined above.
2. While maintaining the basic settings in the controlling area, the entries must remain consistent with the higher level entries.
3. You want to maintain version 0 or 1. The restrictions outlined above apply.
Use the "Extras" menu option to display the structure of the entries in the complex data object version:
•     Select a version and choose Extras -> Version use.
The SAP System shows which controlling areas use this version.
•     Select Extras -> Versions in CO area
This displays all versions used in the current controlling area.
The subordinate entries in the hierarchy (settings for each fiscal year, strategic Activity-Based Costing: transactions for a delta versions) will also be shown for both cases.
Procedure
Do not activate the indicator, or change the higher order of settings in the general version definition.

Raj,
What are you trying to change?
To me you are not suppose to make any changes, you need to select the version "0" and then hit "Settings for each Fiscal year" subfolder.... here you copy the settings of 2006 and change the year to 2007. This should resolve the problem.
Regards,
Prasobh

Similar Messages

  • Version 0 is not defined for fiscal year 2012.

    Hello Experts,
    While am tring to release  a work order, i am getting the below error.
    Version 0 is not defined for fiscal year 2012.
    Message no. GP626
    Diagnosis
    The version 0 is not defined in controlling area DE06 for the fiscal year 2012.
    You have to maintain the fiscal year-dependent version parameters for all actual versions for which multiple valuation is updated.
    System Response
    The version 0 cannot be used for fiscal year 2012.
    Procedure
    Maintain the fiscal year-dependent version parameters for the version 0.
    Execute function
    By this what i understood is we need to change the Settings for each fiscal year for the version 0 in controlling area DE06.
    i.e. we need to add the fiscal year 2012 in that.
    Is this correct????
    If yes what will be the impact of adding 2012 in that screen?
    i think its a soft config only.
    Please let me know the correct process
    Thanks in Advance,
    Satya

    Version 0 is not defined for fiscal year 2015.
    What to do next ? Please help with it.

  • Version  0 not defined for fiscal year...

    Dear Experts..
    Im trying to do an hiring action but system says Version  0 not defined for fiscal year...
    Could someone tell me wat could be the reason???
    Regards
    Shanthini

    Hi,
    Go to SPRO: Controlling -  General controlling - Org - Maintain versions
    On the right hand side select version 0 then select controlling area settings.
    Again select version 0 on the right hand side and select Settings for each fiscal year.
    Then maintain the settings for the relevant fiscal year.
    Regards,
    Dilek

  • Error saying 'Posting period 000 is not defined for fiscal year variant K4'

    Hi All,
       When I try to add a new entry in the transaction OB52, I get an error message saying 'Posting period 000 is not defined for fiscal year variant K4'. The entry that I add is,
    Variant           :  0001
    Account Type: +
    From Period    : 1
    Year               : 1995
    To Period        : 12
    Year               : 2010
    From Period2  : 13
    Year               : 2000
    To period2      : 16
    Year               : 2010
    Please let me know what customising needs to be done to solve this issue.
    Thanks a ton.
    Best Regards,
    Jeff

    Hi,
    Hava you checked in OB52 screen, by default 0001 posting period variant will be there for +, A, D, K, S account types.
    If it is already existed in your OB52 screen, you won't create one more record with the same name. You have to edit the existing 0001 posting period with new values.
    Thanks
    Chandra

  • Error: "posting period is not defined for fiscal year variant" in  FBICS3

    Hi,
    I got error  "posting period is not defined for fiscal year variant" when I execute t code FBICS3.
    I checked in OB29 &  t code FBIC010 & noted that the fiscal year variant had ben maintained.
    Please advice.

    HI,
    It was noted that the mentioned t code had been maintain but below mentioned error appear:
    Posting period  is not defined for fiscal year variant
    Message no. GU506
    Diagnosis
    You have tried to determine a posting date in fiscal year variant for period , fiscal year , but this period is not defined for the variant.
    Procedure
    You maintain fiscal year variants in table T009.
    It was referring to t code OB29. I have checked the detail, in OB29 also details maintain.
    Please advice why the error still prompt.

  • Fiscal year not defined for in Year

    Dear All
    I am trying BDC to record hiring action through PA40 for the purpose of mass hiring. While hiring process at 'Create Car & Conveyance allowance' screen a warning message appears "No automatic updation for pernr 12345 .Allowance grpg not found." I skipped it, then another error comes at  'Create Income From Other Sources' screen, that is "Fiscal year not defined for  in Year". In the description of this error I find 'Fiscal year not defined for  in Year'. I checked PA03 also, but I didn't find any clue there.
    Kindly enable me with your expert suggestions to go ahead.
    Best Regards,
    Anand Singh
    SAP HR Consultant

    HI,
    1. Allowance Grouping
    - Check the hiring date and Infotype 8 date.
    2. Income from other sources
    - Check the control record .
    Is it released for the year for which u r entering the data.
    Regards,
    Param

  • While creating sales order got error version "0" is not defined for company

    Hi,
    i got a error  while creating a sales order(va01) ,i got an error
    saying that "version 0(zero) is not defined for company code
    if there is any solution please provide....
    Thanks&regards
    kishore kumar

    Go to TCODE:OKEQ
    1)select version 0 here and ext select settings for each fiscal year under controlling area settings
    2)give your controlling area XXXX and version 0 then enter
    3)select new entries maintain data for new year 2008.
    Hope this will give u
    Sri

  • I have a version of photoshop 7.0 which I have not used for some years. I would like to install it o

    I have a version of Photoshop 7.0 that I have not used for some years. I want to now install it on my computer which uses Windows XP. How do I go about it?
    Thanks

    You simply run the install program and hack in your serial number.
    Mylenium

  • Fiscal Period Variant Not defined for year 2010

    Hi All ,
      We are using a Planning area with a Fiscal year variant  in the storage bucket profile for DP. We are trying to copy the data from BW to the planning area which also has the same Fiscal year variant. All the settings in SPRO and the T009 tables are setup correctly for this fiscal year variant, still while using the TSCUBE transaction to copy the data from the cube to the planning area we enconter the above mentioned error. While investigating further we found a table /sapapo/T445C2 which assigns the infocube to the technical periods and this table is empty as of now,( A similar table is used in ECC for flexible planning which assings this value there ) , But  in BW side there is no such table. I am not sure if this is the reason for the error. Did anyone face a similar problem in the past . Kindly share your comments on the same.
    Regards
    Chirag

    Hi Kadam,
    Thank you for the reply. We already did check the notes , but that is not of relevance in this case, since the error is happening not only in APO but also in BI. The BI team found that the fiscal year variant defined for the year was 100 periods which is not possible since in a year if we make weekly periods the periods cannot exceed more that 53 to 64  hence the system was not creating any SID's they are trying to correct the error.
    Regards
    Chirag

  • My app went from working fine to: Id field not defined for cfc Path.to.my.ORMCfCPag when I restarted

    Hi everyone,
    I have a CF9 ORM problem that I haven't been able to figure out and thought I'd see if you had any idea. I have seen a few postings talking about a "similar" problem but none of them correctly resolved this particular issue. I appreciate any help you can offer.
    I recently created a CF9 app where I generated scripted ORM CFCs for my app using ColdFusion Builder. It worked great and my app was completely working. However, when I was adding some enhancements, I ran into an error when I restarted the CF app server. Here's the message I keep getting:
    "Id field not defined for cfc Path.to.my.ORMCfCPage. Either the table should have a PK column mapped to a cfc field OR at least one field should be specified as id."
    My App.cfc file only had orm enabled (no other mappings) when it was working. I've since tried specifying things like the cfc location etc. and it still hasn't helped.
    // MORE DETAILS:
    - When my app was working, I had moved it to 2 other servers. I had this error on both of those but not on my local copy. They all use the exact same database.
    - The last change I made before the error was adding a generator="identity" field to my generated ORM beans. Once I got the message, I tried changing it back and restarting again but still got the error.
    - I've also made sure all of the Adobe tags are in my web root (as suggested in a prior posting about this problem). I've search all over for a solution and nobody has a solution posted online that works so far.
    Do you have any idea why this is happening?
    Thanks!
    Jeff

    Quick thought and probably not relevant, but do you have this.ormsettings.savemapping set to true in your Application.cfc? I've fallen foul of this before - once CF has generated the hbmxml files and saved them to disk you can make all kinds of changes to your code which won't make a difference as it'll continue to read from the file versions, but only for certain properties and methods at times it seems.
    Long shot I know, but I found CF ORM to be a nightmare for seemingly random caching.

  • Fiscal year variant is not maintained for calendar year 2009

    Hi,
    After upgrade to BI 7.0 we are getting error: "Fiscal year variant & is not maintained for calendar year 2009" while opening a query through Bex Analyzer.
    Basically it is happening like when we open a particular query, the Variable selection screen comes up, then on clicking the exection button (after selection) it shows SYSTEM_FAILURE exception & clicking the details button, shows the message ""Fiscal year variant is not maintained for calendar year 2009"
    Please provide some information/resolution to this.
    Thanks,
    Shantanu.

    HI,
    Please ensure that you have defined your fiscal year variant in OB29
    correctly.  It is necessary that:
      1.  the previous year has been maintained,
      2.  an entry for Dec 31 exists in each fiscal year,
      3.  the following fiscal year has been maintained.
    Hope this helps.
    Regards,
    Nitin

  • Error message TD427 (A text element is not defined for form J_1IEWT_CERT)

    Hello,
    Q> I assign the SAP script form J_1IEWT_CERT to 'SPRO=>Withholding Tax Certificates for Vendor and Customers' and was trying to see the print preveiw. But once I press printpreview button error comes "ELEMENT TITLEDET WINDOW TITLEDET IS NOT DEFINED FOR FORM J_1IEWT_CERT" and i can't see the printprview.
    Same thing I tried with the copy of J_1IEWT_CERT from 000 client to ZJ_1IEWT_CERT; but same error is coming.
    If i try the printpreview through SE71 it shows without error.
    Thank You.

    "test printing" via SE71 only prints what exists in the form. Here your form is missing TITLEDET window and element.
    The print program tries to print TITLEDET but it does not exist. Could you check SAP notes to get correct versions of print program and sapscript form.

  • Depreciation posting rules are not define for area 00 in company code

    Dear Expert,
    Would like to seek for help, when I run a customize report (AUC without PO not yet capitalized report the system prompt the error depreciation posting rules are not define for area 00 in company code only on the march 2011 on ward but before march 2011 the report is able to display as usual.
    Between., does SAP have the standard report to list the asset which is AUC and not yet capitalized?
    My version of SAP is ECC 6.0.
    Kindly advise.
    Regards,
    Karen

    Hi,
    Thank you for the prompt reply, why the system prompt the error depreciation posting rules are not define for area 00 in company code only on the march 2011 on ward but before march 2011 the report is able to display as usual?
    Please help.
    Regards,
    Karen

  • Goods Issue error - batches not defined for delivery item

    Hi,
    We are getting a Goods Issue error  u201CThe batches are not defined for delivery item 000010u201D.   We are only getting this error for a material that is being shipped against a particular third party sales scheduling agreement.  We went live in 2007 and we had no issues, but when we had to create a new Sched Agreement this year, for third party sales, we started to get this error.  However, if we re-activate the old scheduling agreement we do not get the error.  We have a batch job that executes the following steps:
    1.     VL06IG (collective goods receipt)
    2.     VL10 (collective delivery)
    3.     VL06O (collective GI)
    We have compared the 2 scheduling agreements and see no difference.  We are assuming it has something to do with how the scheduling agreement was setup, but are not sure.  Any suggestions on how to correct this problem would be much appreciated.
    Thanks in advance,
    Helen

    Dear Murali,
    The material has not changed at all.  I'm not sure what you mean by maintaining batches while receipt of the material.
    If I re-open the old scheduling agreement, we do not get the error message.  However, as soon as we use the new SD scheduling agreement, we get the error.  We are using the same material master on both scheduling agreements.
    Thanks,
    Helen

  • SFLIGHT is NOT defined for the current logical database.

    I have just started learning ABAP and bought an ABAP Objects book by Horst Keller. I have installed 4.6d mini sap and SAP GUI 6.4 on win XP Prof. I executed S_FLIGHT_MODEL_DATA_GENERATOR to load DB tables.
    (1). When I tried to check a sample program, I get an error message SFLIGHT is not defined for the current logical database.
    Here is the partial code:
    REPORT zbcb01f1 .
    TABLES: sflight, sbook.
    DATA: BEGIN OF sr OCCURS 100,
          carrid LIKE sbook-carrid,
          connid LIKE sbook-connid,
          fldate LIKE sbook-fldate,
          bookid LIKE sbook-bookid,
          order_date LIKE sbook-order_date,
          loccuram LIKE sbook-loccuram,
          END OF sr.
    GET sflight.   <---- Error is pointed here
    (2). I am also not getting Graphical Screen Painter when selecting Layout for a screen. Instead, I am getting alphanumeric editor.
    Someone please help me.  
    Raizak.

    Hi Raizak,
    the easiest way is to go to service.sap.com/notes and enter the note number. For this time I've copied the 2 notes below.
    Best regards,
    Christian
    Symptom
    The Graphical Layout Editor of the Screen Painter either does not start or terminates.Error message 37527 is displayed in the session in which the call was made (Graphical Layout Editor not available.
    Additional key words
    () EUNOTE, EUSCREENPAINTER, 37 527
    Cause and prerequisites
    This note comprises all the common causes for error message 37527 and provides you with information on how to systematically trouble shoot the problem.
    1. Windows32 or UNIX/motif?
    As of Release 4.6B there is only the program version for 32bit Windows (NT, 95, 98, 2000 ff.).Up to Release 4.6A there was also a version for UNIX/Motif.All of the more current notes (with the exception of Note 45490) refer only to the Windows version.
    2. Termination at the start or during use?
    The following diagnostic steps refer to the causes of the errors which prevent the Graphical Layout Editor from starting. However, there are also known error causes, which result in the program terminating when the application is being used and which also produce the 37527 error message. This affects -
    Rel.4.6C/D: Termination when attempting to read texts in the logon language -> Note 375494
    Crash after transferring program and dictionary fields. Termination after transferring program and dictionary fields -> Note 189245
    Release 3.1I: Termination after inputting field text -> Note 113318
    3. Is the SAPGUI installation correct?
    The Graphical Layout Editor is automatically installed during the standard installation of the SAPGUI.If you chose a non-standard installation, then you should have explicitely selected its installation (component "Development Tools - Graphical Screen Painter").
    The program executable is called gneux.exe.During the SAPGUI installation it is placed in the same directory as the SAPGUI programms (for example, front.exe) (usually C:\Program Files\SAPpc\sapgui). The following belong to the program:
    - An additonal executable gnetx.exe (RFC starter program)
    - the DLL eumfcdll.dll
    - various eusp* data files (that is, the names all begin with eusp.)
    You can check the completeness of the program installation by starting the program gneux.exe locally in the SAPGUI directory (for example, by double-clicking on the program name in the Explorer window).The Layout Editor is displayed with German texts and an empty drawing area for the pseudo screen EUSPDYND 0000.
    If the installation is not complete, an error dialog box provides information regarding the cause of the error, for example, sometimes the DLL eumfcdll.dll is missing after reinstalling the SAPGUI. For example, the eumfcdll.dll DLL was sometimes missing after the SAPGUI was reinstalled.
    4. System link defined and okay?
    The Graphical Layout Editor is a separate program which is started by the Screen Painter Transaction (SE51) on the Frontend machine.
    Up to Release 3.0F, the programs communicated with each other via the graphics log of the SAPGUIs (gmux).The definition of the environment variable SAPGRAPH may be the cause for the program not being being found where it is.
    As of Release 3.1 G, the programs use a separate RFC link which is set up in addition to the SAPGUI's RFC link.Missing or incorrect definitions of the RFC destination EU_SCRP_WN32 or problems with the creation of the RFC link are the most frequent causes for error message 37527 being displayed.Below you can find the correct settings for the RFC destination EU_SCRP_WN32 (under "Solution").Note 101971 lists all the possible causes for problems with the RFC link set-up. Attention:The Graphical Layout Editor may not be operated through a firewall (for example between the SAP and the customer system) because this does not allow an additional RFC connection in addition to the SAPGUI.
    Solution
    ad 1 UNIX/Motif
    Note 45490 describes possible errors resulting from an incorrect program installation under UNIX/Motif (up to Release 4.6A).
    ad 2 Termination when using
    The above-mentioned notes may contain options for solving individual problems.However, you usually have to replace the program with an corrected version.You can do this either by downloading a patch from sapservX or by installing a more current SAPGUI.The patch is mentioned in the respective note.
    ad 3 Installation
    You either need to reinstall the SAPGUI or manually copy the missing file into the SAPGUI directory.In both cases you should make sure beforehand that a Graphical Layout Editor is no longer running.To do this you can either remove all processes gneux.exe from the process list by using a tool such as Task Manager (on WindowsNT) or exit the Graphical Layout Editor from the Screen Painter Transaction menu via Edit -> Cancel Graphical Screen Painter). Attention:For each session or system an individial Layout Editor process may exist so that, if need be, several processes should be cancelled.
    ad 4 System link
    Up to Release 3.0F:you can either delete the environment variable SAPGRAPH or copy all the files of the Graphical Layout Editor into the directory which is specified by SAPGRAPH.
    As of Release 3.1G:you can use Transaction SM59 to check the RFC destination EU_SCRP_WN32 (expand the TCP/IP connections, select destination EU_SCRP_WN32).If the destination is missing, then you should create it with the following settings:
    - Connection type "T" (start of an external program via ...)
    - Activation type "Start"
    - Start on "Front-end workstation"
    - Front-end workstation program "gnetx.exe" (caution! NOT gneux.exe)
    - Description (optional) "Graph. Screen Painter (Windows32)
      Start Program gneux.exe using the gnetx.exe starter program."
    If you want to start the program from a different directory than the SAPGUI standard directory, then replace the default value under Frontend work station by the complete path name for program gnetx.exe.Transaction SM59 also allows you to check the RFC connection via the pushbutton "Test connection").In this case the system attempts to localize and start the program gnetx.exe.If there are errors, a message is displayed regarding the possible causes (for example, gateway problem, timeout problem or the like).Note 101971 provides a detailed explanation of the problems involved with an RFC connection set-up.As the Graphical Screen Painter requires a functional RFC connection as of Release 3.1G, contact the System Administrator or create an message on the topic Middleware (BC-MID-RFC) if you encounter RFC problems.
    If the program gnetx.exe can be found and started, the banner dialog box with logo, release data and version number is displayed briefly.As the Layout Editor itself is not started, the error cause must be in the installation of the Layout Editor program gneux.exe if the connection test was successful.
    Release 4.5A to 4.6B: Use with Releases <3.1G>.
    The Graphical Layout Editor is downward-compatible as regards the system connection, that is, an RFC-based Layout Editor for example from Release 4.6C can also be used on a non-RFC-based Screen Painter, for example of Release 3.0F.However, the releases mentioned above have a program error which causes a crash due to memory violation in the start phase of the program.Note 197328 describes the solution by installation of the corrected program version.
    Important: Trace file dev_euspNNN!
    If none of the diagnosis steps leads to the cause of the error and to the solution of the problem via the corresponding note, then you should add the contents of the trace files dev_euspNNN (NNN = process number) to the message for SAP, if possible.You can find this file in the current directory of the SAP System, for example under Windows NT in C:\Winnt\Profiles\<user>\SAPworkdir.If several such trace files can be found there, make sure that you use the file which matches the termination time with respect to date and time of creation.In most cases the ERROR message in the last lines of this trace file provides an important note on the cause of the error.
    Source code corrections
    Symptom
    The graphic layout editor of the Screen Painter cannot be started (RFC version).
    Other terms
    () EUNOTE, EUSCREENPAINTER
    Reason and Prerequisites
    This is generally caused by the fact that the RFC connection between the frontend graphics layout editor and the calling screen painter program at the backend cannot be set up.
    Possibility 1: Route permission denied
    In the trace file dev_eusp<Process Id> of the graphics layout editor you find the entry "ERROR in RFCMgr_accept: not accepted", and in the RFC trace file dev_rfc.trc you have an entry of the form "ERROR route permission denied (<Front-Id> to <BackId>,<Service>)".
    If there is a firewall between frontend computer and application
    server, you need to decide whether the port for the RFC of the graphical layout editor can be released here (see Solution 1 below).
    In case no firewall exists between the frontend computer and the application server, in its route permission table, the SAProuter contains either no entry for the frontend computer, on which the graphics layout editor is started, or the entry says that the link is saved by a password.Since the connection is denied, the graphics editor processes exits again, and the screen painter switches to the alphanumeric layout editor.
    Possibility 2: Service 'sapgw<ServiceId>' unknown
    In the trace file dev_eusp<ProzessId> of the graphics layout editor you have the entry "ERROR in RFCMgr_accept: not accepted", and in the RFC trace file dev_rfc.trc you have an entry of the form "ERROR service 'sapgw<ServiceId>' unknown".
    The service sapgw<ServiceId> (for example, sapgw00) is not known on one of the computers participating in the RFC communication because the corresponding entry is missing in its service file. The affected computer can be the frontend computer or the gateway computer.
    Possibility 3: The system parameter gw/cpic_timeout value is too low
    This system parameter determines how many seconds the gateway is waiting for the RFC connection to be set up.In case of a high network load, the default value of 20 seconds is too small with the result that the connection cannot be created on time.Here the graphics layout editor process also exits with the trace file entry "ERROR in RFCMgr_accept: not accepted".
    Possibility 4: System parameter abap/no_sapgui_rfc set
    The profile parameter abap/no_sapgui_rfc of the system is set (that is, it has a value not equal to space or 0).This prevents the program of the graphics layout editor from being started with RFC at the frontend.
    Possibility 5: Unnecessary authorization check
    The error message "No RFC authorization for user xxxxxx" is generated although the check of the RFC authorization was deactivated by profile parameter auth/rfc_authority_check (value = space or 0). The problem is caused by a program error, that ignores the value of the profile parameter let during the call of the RFC authorization check (see Note 93254). This error can occur as of Release 4.5.
    Solution
    ad 1) If a Firewall is installed between frontend computer and the application server, you need to decide whether the port for the RFC link of the graphical layout editor shall be released in the firewall. This is port 33nn, where nn is the 2-digit system number of the SAP application server. As of Release 3.1G, the graphical layout editor needs an RFC link for communication with the application server in addition to the already existing linkof the SAP GUIs. Such a second link is not allowed by the firewall in general because it would contradict the security concept (password protection, logging of the connection).
    If no firewall exists, you should check whether the frontend computer can be added to the route permission table or whether the password option can be removed from out of the available entry.
    For details refer to chapter 4.4 of the attached Note 30289.
    ad 2) Include service sapgw<ServiceId> in the service file.
    Refer to Note 52959 for details.
    ad 3) Increase value for system parameter gw/cpic_timeout. 60 seconds should be sufficent as a timeout limit.
    ad 4) Set the system parameter abap/no_sapgui_rfc to space or 0
    Start the application server so that the new parameter value comes into effect.
    ad 5) Import the Support Package specified in the attachment for the release in question or implement the advance correction in the source code as described in the attached correction instructions.
    As a workaround, assign RFC authorizations as described in Note 93254.

Maybe you are looking for

  • I want to install a learn software that runs normally in windows?

    I am trying to instal a lern software for my kid on a mac that runs only on windows. is there a possibilty to download it and make it run?

  • Oracle Report Server with Weblogic crash

    Hello, I am using Report Server 6i on WinNT and the web server used is WebLogic 6.0.. The reports generated are of HTMLCSS format or PDF format. Cud U please send the replies for the below queries at the earliest.. 1.The data in the generated report

  • Using PCard, Procurement Card, Purchasing Card

    Client wants to use pcards as part of the procurement process. They are planning on implementing ECC. If we use standard Preq and PO functionality, can we use Pcards? If so, what is the process flow? Are Pcards only an SRM functionality?

  • Email from Lightroom 5

    Hi since I started to use Outlook 365 on my Mac running latest OS I have been unable to email images from Lightroom 5 through Outlook. The only option I get is to send it through Entourage which dose not do anything. If anyone has had this problem an

  • Reg: Variable value not updating

    Hi experts, I am new to bi -publisher and i am in Learning Stage. My problem:- Steps Followed 1. I am declaring a variable globally using below syntax:- *<?variable:LLP;number(15)?>* 2.Then in my Rtf i am calling for loop for lines 3. In For Loop, i