Where is the field release creation profile in scheduling agreement?

Dear experts,
I need to maintain release creation profile in Scheduling Agreement.
please let me know where can I find this field in ME31L
Regards,
Shashidhar

Found in More functions - Item details

Similar Messages

  • Mandatory creation profile on scheduling agreements

    Hello Gurus,
    I need to put a value on creation profile field on schedulling agreements. I have to choices:
         - Put the value on supplier data. It is a plant-dependant value i my client doesn't want to create this data.
         - Made it mandatory. This possibility doesn't appear through Scheduling Agreement -> Define Screen Layout at Document Level as usual in fields on Purchase docs.
    Anyone has an idea how made it mandatory (or de badi to change the value by code)
    Best regards,
    Nacho

    Dear Experts,
    I'm not getting any response regarding Creation profile which I posted last week.
    Can anybody explain me the use of Creation profile in Schedule line?
    From Standard SAP help documentation I'm not convince.
    Best Regards
    PKB

  • Creation Profile in Scheduling Agreement and Schedule LIne

    Dear Experts,
    Currently I'm working on Scheduling Agreement and Schedule Line.In standard SAP gives the provision of creation profile.I've gone through the SAP help documentation but I'm not clear on that.I've few doubts on creation profile.
    1. I've created a profile say XXXX for 14 days JIT and 6 months Forecast.And I maintain the same on Scheduling Agreement additional data.
    2.I'm creating delivery schedule respect ot Scheduling agrrement.
    3. I maintain the aggregation horiozon in creation profile as 10 days daily aggregation for JIT and 120 days for monthly aggregation for forecast.
    4.I run MRP for the header material and I maintain the necessary SA number in Source list.
    5. After MRP run I'm not getting the respective schedule lines for JIT and Forecast.
    6. What is the use of creation profile in Scheduling Agrrement and schedule line and is it determine ant schedule lines after MRP run.
    Please clarify me on creaion profile.
    Thanks in advance
    PKB

    Dear Experts,
    I'm not getting any response regarding Creation profile which I posted last week.
    Can anybody explain me the use of Creation profile in Schedule line?
    From Standard SAP help documentation I'm not convince.
    Best Regards
    PKB

  • Creation Profile in Scheduling Agreement

    Dear Experts,
    Currently I'm working on Scheduling Agreement and Schedule Line.In standard SAP gives the provision of creation profile.I've gone through the SAP help documentation but I'm not clear on that.I've few doubts on creation profile.
    1. I've created a profile say XXXX for 14 days JIT and 6 months Forecast.And I maintain the same on Scheduling Agreement additional data.
    2.I'm creating delivery schedule respect ot Scheduling agrrement.
    3. I maintain the aggregation horiozon in creation profile as 10 days daily aggregation for JIT and 120 days for monthly aggregation for forecast.
    4.I run MRP for the header material and I maintain the necessary SA number in Source list.
    5. After MRP run I'm not getting the respective schedule lines for JIT and Forecast.
    6. What is the use of creation profile in Scheduling Agrrement and schedule line and is it determine ant schedule lines after MRP run.
    Please clarify me on creaion profile.
    Thanks in advance
    PKB

    Dear Experts,
    I'm not getting any response regarding Creation profile which I posted last week.
    Can anybody explain me the use of Creation profile in Schedule line?
    From Standard SAP help documentation I'm not convince.
    Best Regards
    PKB

  • Significance of release creation profile

    Hi all,
    Can anyone explain with example the use and significance of release creation profiles in outline aggrement
    Thnks
    Gan

    Hi,
    Release Creation Profile
    Use: -
    The creation profile determines:
    - Which event triggers the creation of a scheduling agreement release (changes involving the lines of the overall schedule and/or the reaching of the next transmission date)
    - How the delivery dates are shown (aggregation and release horizon)
    - Whether
    Backlogs and Immediate Requirements are determined and shown in the scheduling agreement (SA) release Whether a tolerance check is carried out for SA releases that are created due to changes to the overall delivery schedule in the system
    Note: -
    The tolerance check is only carried out if lines of the overall schedule for an item have been changed and if you create SA releases using the release creation program (via Scheduling agreement ® Create SA release).
    Features: -
    A creation profile is defined on a plant-dependent basis and consists of the following areas:
    General parameters: -
    - Whether - and, if so, under what conditions - an SA release is generated (creation strategy).
    - Whether backlogs and immediate requirements are to be determined for the SA release type.
    - Whether or not the tolerance check is to be deactivated in the case of change documents created for SA releases with backlogs.
    Aggregation horizons: -
    - The Release Horizon for which released quantities are shown, and
    - The periods for which quantities may be aggregated.
    If your creation profile provides for aggregation, quantities and delivery dates set out in the lines of the overall delivery schedule stored in the system for a scheduling agreement are aggregated to form release schedule lines.
    If you use a creation profile without aggregation, or work without a creation profile, the schedule lines of the SA release correspond to the schedule lines of the overall delivery schedule for the scheduling agreement for the relevant period.
    Creation periodicity: -
    - Whether SA releases are to be created on a periodic basis (and, if so, at which frequency).
    Each time a scheduling agreement release is created, the system calculates the next creation date. Weekly and monthly releases are always created on a Monday (first workday of the period). The system takes the factory calendar as the basis for calculating the due dates for release creation.
    If you wish to create SA releases on a periodic basis, you should choose a creation strategy that includes Next date.
    Tolerance profile: -
    - Whether tolerances are are to be checked for scheduling agreement releases created as a result of changes to the overall delivery schedule. This allows you to specify that SA releases are only to be created following major changes to the overall delivery schedule.
    In the case of SA releases containing backlogs or immediate requirements, the system never checks tolerances.
    Activities: -
    You process creation profiles in Customizing for Purchasing under Scheduling Agreement ® Maintain Release Creation Profile for Scheduling Agreement with Release Documentation.
    You assign a creation profile to a scheduling agreement item in the Additional data.

  • Release creation profile

    Hi,
    Is there any other parameter (other than release aggregation of release creation profile) that influence FRC schedule ?
    I have a SA with FRC schedule aggregation crieteria as 40 days daily and 370 days monthly...but it transmits only 340 days in FRC.

    Hi,
    Are you using Scheduling Agreement LPA Type.Because only then while creating SA you enter the Release creation profile.
    Release Creation Profile
    Controls:
    The creation periodicity of the releases (scheduling agreement delivery schedules), i.e. the period in which releases against a scheduling agreement are created and transmitted to the vendor, and
    The way in which the quantities transmitted to the vendor are aggregated (starting from the current creation date of the release)
    Example:
    The creation periodicity for a scheduling agreement for which delivery schedule lines have been maintained over two years provides that releases are created weekly from 1.1. to 12.31 of the first year.
    The release quantities are to be aggregated as follows:
    For a period of 10 days starting from the current date of release creation, no aggregation; from the tenth to the thirtieth day, on a daily basis; and from the thirtieth day to the sixtieth day, on a monthly basis.
    Regards
    Arun

  • Purpose and use of release creation profile

    Hi all,
    Can anyone explain with example the use and significance of release creation profiles in outline aggrement
    with examples
    Thnks
    Gan

    Definition: release creation profile
    An instrument used to determine the period in which releases (types of delivery schedule) are generated against a scheduling agreement and transmitted to the vendor.
    The creation profile controls the creation periodicity of the releases, the aggregation of scheduled quantities starting from the day after release creation, and the implementation of a tolerance check to ensure that releases are only created in the case of major changes to the overall delivery schedule in the system.
    Example
    A release creation profile for a scheduling agreement for which delivery schedule lines have been entered over several years specifies that releases are transmitted weekly from 01.01 to 12.31 of the first year. The release quantities are to be aggregated as follows:
    For a period of 10 days starting from the current date of release creation: no aggregation. From the tenth to the thirtieth day: on a daily basis. From the thirtieth day to the sixtieth day: on a monthly basis.
    regards
    kunal

  • Schedule line Release with help of release creation profile.

    Hello,
    Is it possible to create the schedule line release for scehule line automaticaly by heuristcs run with the help of release creation profile of external procurement relationship ?
    We can release the schedule line in product view.
    What is other way release the schedule line?

    Hi,
    Credit check is done to see if the customer has crossed his credit limit or not. Incase you want to forcefully release order we use [VKM1]. What is this got to do with the schedule lines??? Irrespective of whether the order is under credit hold or no the schedule line are determined the same way. Didnt understand the connection.
    Regards
    Nadarajah Pratheb

  • Re how to activate release creation profil

    Dear Sap experts, 
    please advise me how to activate release creation profile as i have already trasanction code
    OMSG but in which vendor gorup we have to go...
    Thanks
    Mohit

    You need to select 0001- vendor.
    To activate in ht e vendor master goto - purchasing view-extras-
    give the plant, check data retention at plant level, SAVE
    Now again goto purchasing view, extrasà alternate data,for a plant
    In default material data, u find this Release creation profile

  • Where can I find Firefox 7.0 to install? Is there a link maintained where all the firefox releases are available for users

    Hello Team,
    Is there a link maintained where all the firefox release and its patch are available for users to download & install

    You can get Firefox 7 here
    * http://releases.mozilla.org/pub/mozilla.org/firefox/releases/7.0.1/
    buit its reccomend to use Firefox 8

  • In transaction scase, where is the field 'status' stored ?

    Hi
    in transaction scase, where is the field 'status' stored (in Hdr. data), for a specific BP ?
    thx.
    Edited by: avijit saxena on Nov 12, 2008 10:10 PM

    table>srmprotocol>filter on [ACT_ID] 'attribute change'>choose colom 'arg_string'->filter on 'stat_orderno'

  • Where are the contents of GPnP profile stored?

    On my 3 node RAC setup using SCAN with GNS,
    I renamed GPnP profile on one node , stoppped clusterware on that node and tried to restart it. The c/w started and GPnP profile file was automatically recreated with name pending.xml. The moment I changed the value of ASM_DISKSTRING parameter using SQL, pending.xml was automatically renamed to profile.xml and ASM_DISKSTRING value was updated in it. I presumed that GPnPd copied the profile from one of the other nodes.
    Next I renamed the profile on all the nodes, stopped clusterware on one of the nodes and restarted it. But now again the same thing happened as earlier i.e. it was created as pending.xml and was renamed to profile.xml when updated via SQL. From where were the contents of the file read? Is it OLR?

    I am renaming ghome/gpnp/hostname/profile/peer/profile.xml
    Following post explains all I did:
    http://oracleinaction.blogspot.in/2013/01/LOSEGPNPPROFILE.html
    Pls also clarify why do we have gpnp profile in two locations?
    Edited by: user12288492 on Mar 18, 2013 8:32 PM

  • Where are the files that camera profiles install?

    I have downloaded from this link: http://labs.adobe.com/wiki/index.php/DNG_Profiles
    DNG profile editor 1.0 beta 2 and camera profiles beta 2.
    After installation of these camera profile on PC where are the files?
    I have searched but I don't find these!
    Please help me.

    Welcome to the discussions,
    Your music and movies should still be part of the iTunes library on your computer. See if your movies are listed in "movies" in the left window in iTunes.
    Photos you took with the phone are part of the last backup, if you did not sync after that. If you did, the data got overwritten.
    See what else is inside the backup and how to restore from it here: http://support.apple.com/kb/HT1766

  • Where are the daily released apps? The new page has them all mixed up.  Is there any way to see only what has been released each day like it was before?

    Since updating to ios6, the page with the newly released apps is gone, and replaced with something that has them all mixed together.  Is there any way to search for apps released each day?  I don't like the new setup, where it is categorized and you have to go through everything listed.

    Thank you.Ok say for e.g.
    500 video files imported in fcpx
    800 clips extracted from these obviously on the timeline and joined/compounded according to their content in say 15 layers according to 15 instruments used ,so now just to see the entire usable footage ....
    now one 7 minute song sequence has to be made where bits would be simultaneously taken from these 15 layers as all instruments are playing simultaneously
    these shots are not more than 2 secs each according to the beat........
    when I try to work with these 15 layers as well as the Final primary layer that I'm making in the same timeline my fcpx becomes slow
    but when I drag individual layer to individual timelines it is fine so that is the only option
    but now for every 2 second bit I have to go back to the 15 layered timeline and find one single suitable shot
    So I was wondering is there a way to be able to see these layers and clips on the timeline in the browser in a systematic fashion like the way we get with keywords  ?
    and keywords can only be used in the imported clips already in the browser ,and not after we drag it on the timeline.....
    Till now I think exporting and importing back is the only option ...but is there another work around ?

  • Error while selecting the fields in creation of Look-Up

    Hi Experts,
    I am getting following error message when writing a lookup.
    Unknown column name "/BIC/XXXXXX" until runtime, you cannot specify a field list.
    Would like to know whats the cause and how to solve it.
    Regards
    Shubh Karan

    I think you dont have a field named /BIC/XXXXXX in the table from which you are trying to fetch the data. Chech the spelling of the field name and table name.

Maybe you are looking for