Why Info record net price is 0

info record price is 20hkd/1pc in the past peried. as the price change, i have create a new price in current peried and save it(price is not 0). when i use me12 again and find  organazation data view price is 0. and click the condion but the price is not 0,
notes  685117  suggest use report RM06INP0 to Solution
in current peried  why happen this issue?

Hi,
The price in the info record (EINE-NETPR) does not always agree with the price that is taken from the info record when creating a purchase order. The most common cause is that the condition was updated by condition maintenance. This will not translate into a direct update of the net price in ME13 (display info record). If you want the net price to show exactly as the info record condition, then schedule report/program RM06INP0. This will do an update routine and synchronize prices.
Regards
Govind

Similar Messages

  • Report for displaying info record scale prices

    Hi all,
    Can any one provide me the sample code for a report  displaying info record scale prices.
    Thanks,
    Suresh

    Check t.code MEKP.

  • Mass upload for info records when price gets changes

    Dear All,
    How to do Mass upload for info records when price gets change.
    Regards,
    Bhargav

    Hi Bhargav,
    Please upload the present price (Map) by  LSMW . When you are doing the transactions  then automatically by selecting option info update price will be updated the  info record in Order Price history
    Regards
    M B Raju

  • Info record scales price bug

    Hi  all
       when i create a po and save, then change info record scales price (price is more than po price),  after change info record,
    user want to change the po Delivery Date, user use me22n change the po Delivery Date and save it. and find the po price is cath the changed info record price , so the po price is error. i send a messsage to sap, but sap said it is sap system behavior and not to change. i want to know any to have the same thing.
    james

    Thanks,
    In info record,close old price by setting to validity date as for ex.31.01.2010,
    new price by setting From validity date as 01.02.2010 to validity date 31.12.9999,
    purchase order is created on 02.02.2010,In po line item correct price(new) is flowing as per info record,
    but in conditions tab of purchase order both prices are flowing in condition type PB00,
    My question is What is reason for both prices will be flowing in condition type ?
    Jeyakanthan

  • Costing issue-Why Info record price is not read ?

    Hi,
    We have an issue while costing a Material procured externally.
    Valuation Variant >>> Priority 1-Info record price. >>Priority 2-Material Master valuation price.
    However, system is picking the price matained in the Material master.
    I have verified the validity of the info record and the Blocks on the Vendor and seems ok.
    Are there any specific checks need to carry out to know if the info record is a valid one.
    Any idea why system is picking Price from Material Master?
    Your help is appreciated.
    Kind Regards
    Umapathi G

    HI Umapathi
    Does any scheduling agreement exists for this info record
    refer this link.. This issue is pretty common these days and has been discussed many times in the forum
    CK11N- Material cost estimate with & without agreement
    Regards
    Ajay M

  • PO creation date and info record validy price relation.

    Dear Gurus,
    While creating a PO, when I change the PO creation date, price in the PO will change according to the validity start date based on the PIR.I believe thats the logic right? I have a scenario, I'm facing a problem that when I change the PO creation date between 2011 and 2012 period,  the price of the PO at times will not change according to the PIR validity start date. Is there any OSS note related to this issue or I'm missing out any logic?
    Validity periods
    Validity on        Validity to         Deletion Flag.   
    04.11.2011       31.12.2011              x
    01.01.2012       31.12.9999

    HI,
    By default, the pricing conditions are dependant on PO document date.
    But there are different options like, whether you want your pricing to be dependant on Delivery date of PO item or current date (sy-datum) or GR date etc.
    This filed is available in 2 places: 1. Vendor master>purchasing data> Pricing Date Control
    2. Info record>Purchasing data> Pr.Date Cat.
    Check in these 2 places and then simulate pricing by changing the corresponding date.

  • MM - Difference between Info Record and Price/Discounts/Others Conditions

    Hi All,
    In MM we use transactions like ME11 to maintain info record. In such transactions we can handle condition types PB00, RA00, FRB1, etc to specify price, discount and freight cost.
    But we also can use transactions like MEK1 to create conditions, or use transactions like MEKE to create discount conditions by vendor.
    What's the difference between ME11 and MEKE?
    Thanks + Best Regards
    Jerome

    Hi Jerome,
    ME11 is for vendor/material/purch org combination
    whereas MEKE is for vendor/purch organisation only. So it will be applicable for all materials supplied by the vendor.
    regards
    Anand.C
    Message was edited by:
            Anand Chidambaram

  • Info Record mass price changes

    rather than someone entering new validity periods and prices for several materials one by one is there a transaction i'm missing?  i expected it to be in memassin.  either for revisions or creations of new periods.  maybe eCATT is an alternative?  curious to see how others solved this.

    Hi
    The best way is LSMW only... But screen Control is difficult in LSMW. IF you have an ABAPer createa BDC Program
    Thanks & Regards
    Kishore

  • INFO RECORD PRICE UPDATING

    Hi guys,
    I have a semifinished good for which the std price is getting updated by Costing Run(PP). Now I want to release the P.O for the same price to Vendor.
    How it is possible to update the info record net price with Std price of the master record automaticaly.
    And I need to add the overhead cost by condition types and save the Info record.
    Please guide with your valuable inputs.
    Point shall be awarded.
    Thanks,
    Dhanu.

    Hi,
    Please create Info record for the vendor in ME 11 with the standard price in the Material Master record
    Normally for purchasing info record for Semi finished goods only Moving average price is preffered.
    After creating the Info create P.O.
    G.Ganesh Kumar

  • Distinguish b/w Automatically created Info Record and created thru ME11

    Hi,
    How can we distinguish between Automatically created Info Record and manually created Info Record (By User through ME11 transaction).
    Where we can see the difference???
    Plz guide...

    Hi,
    In case of Automatically created Info record, Net price and Effective price fields will be blank where as in case of manual info record, you maintain the price under "conditions" manually and which gets updated in net price and effective price fields.
    Also Run Reports ME1M and ME1L, Info records with "Condition       No Price Found" are automaically created. And manual info records will have have "Condition XXX Amount"

  • Net price in Info record

    Dear All,
    I enter Net price when i create the Info record.
    When i want to display that info record,the given net price is not there and found to be zero.
    What is the reason?
    How do i get the price there?
    Regards

    Hi,
    If you have not maintained valid conditions in your Pur info record then price is picked from last purchase order through purchase order price history if customizing settings allow so (In your case if customizing settings allow and the net price 100 in the info record is not from valid conditions, price picked will be 250).
    In the price determination process in PO system always first looks for pur info records with valid conditions if not found then it looks for last PO price.
    There is also a parameter for default values for buyers called EVO. If you make settings in customizing for this parameter and tick the Chkbox for picking the last purchase order price in it and you attach this parameter to your user ID in the user-own data with PI value, then last PO price is picked as default value in the net price.
    You can refer the following link
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/75/ee130655c811d189900000e8322d00/frameset.htm
    Regards,
    Prithviraj

  • Info Record Vs Master Record Price

    Hi,
    I would like to know why in the project builder appears de master record price of a component instead of the price of the purchase requisition (info record price)?
    If I manually introduce the Info Record the price will be updated but would be possible to update the price automatically when the purchase requisition is created?
    Thanks,

    It is happening because of the settings in Valuation Variant. If you want to pick value from Purchase Info Record then change priority sequence in valuation variant, it will start from L.
    txn. OKKT

  • Net price in Inforecord

    I am trying to change the net price in inforecord. Currently it says 0.00 usd. The condition PB00 is maintained. 
    Even if i change the value to 300usd in PB00, still my net price field says 0 in inforecord.
    Why is the net price not changing, even after i change the PB00 condition type in info record? Any suggestions.
    Sylvia

    see explanation in OSS note 685117 - Net Price in Info Record or Contract is wrong
    and 392988 - Consulting: Prices in info record and RM06INP0
    you have to run report RM06INP0 for Info Records

  • PIR net price not follow the condition screen

    Hi all,
    I have a question regarding my pricing condition maintained in a PIR.
    In one of my PIR record, there is two validity line records in the pricing condition with the following date range and value:
    1 - 2008.04.01 to 2010.12.31 ==> PB00 is USD853,00/1 PC
    2 - 2011.01.01 to 2999.12.31 ==> PB00 is USD853,00/1 PC
    However, the strange thing is that in the Purchasing Org screen in the PIR, the NET price value is "879,00 per 1pc" even with the VALID-TO field value as "2999.12.31".
    May I know why the the Net price in this view not picking up the USD853? Something go wrong in the PIR?
    (in between the Pr Date Category is 2-delivery date).
    Please help.
    tuff

    Hi Jurgen,
    I am still a little bit confuse as of why in the Purchasing Org screen in the PIR, the NET price value is "879,00 per 1pc" even with the VALID-TO field value as "2999.12.31".
    Question1-
    Shouldn't the above field automatically pick-up what is maintained in the condition screen of the most latest pricing record which is the USD853,00 for the second line item I described previously?
    Question2 -
    What have caused the 879,00 being inserted into the Purchasing Org screen in the PIR, the NET price field? where is this USD879,00 coming from??
    Thanks and please help.
    Tuff

  • Purchasing Info Record and Source list

    Hi all,
          I am using purchasing info record along with a price for the vendor and material.  This would get the net price into the Purchase order.  Do i really need to create source list ?  What will source list do for me ?   Wouldn't having info record be sufficient ?
         Looking forward to hear your suggestions.
    Thank you.
    Joyce

    Hi Joyce,
    If you have not maintained valid conditions in your Pur info record then price is picked from last purchase order through purchase order price history if customizing settings allow so (In your case if customizing settings allow and the net price 100 in the info record is not from valid conditions, price picked will be 250).
    In the price determination process in PO system always first looks for pur info records with valid conditions if not found then it looks for last PO price.
    There is also a parameter for default values for buyers called EVO. If you make settings in customizing for this parameter and tick the Chkbox for picking the last purchase order price in it and you attach this parameter to your user ID in the user-own data with PI value, then last PO price is picked as default value in the net price.
    You can refer the following link
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/75/ee130655c811d189900000e8322d00/frameset.htm
    Source List -
    The source list is used in the administration of sources of supply. It specifies the allowed (and disallowed) sources of a material for a certain plant within a predefined period. Each source is defined by means of a source list record.
    The source list serves:
    To define a source of supply as "fixed". Such sources count as preferred sources over a certain period of time.(For example, the fixed vendor for material 1 is X for the first quarter and Yfor the second quarter of the year.)
    To define a source of supply as "blocked".(This means, for example, that contract 123 may not be used for a certain period of time.)
    As an aid in selecting the preferred source during the source determination process.(For example, the vendor A is determined as the source for an item of a requisition dated 15th June relating to material 1.)
    To block the external procurement of a material
    Regards,
    Rahul.