Wrong period values in Text template for upload of Plan data (KP06/KEPM)

Hi,
We are facing an issue in the upload template in text format for Upload of Cost Centre Planning data (Transaction KP06) in ECC 6.0.
We have some User defined layouts for Excel upload of plan data. If we save the file as a text (tab delimited) file, the Period values above the Column"Period" do not correspond to the correct periods in ECC 6.0. for e.g. the values above Period 1, Period 2, Period 3 are shown as 6, 5, 4 instead of the correct values 1,2,3. These values are considered by the system for uploading the Planning value in the appropriate Periods and hence the values entered in the Column Period 1 in the text file are incorrectly uploaded by the system in Period 6 based on the values generated by the system in the text file.
However, we do not encounter this issue in the 4.6C system where the values are correctly shown.
We are facing a similar issue with the text upload template for Sales Planning data in CO-PA (Transaction KEPM), where the values generated by the system do not correspond to the correct period.
Regards,
Rajaram

Hi Christian,
Thanks for the quick reply, i followed your earlier reply in the below thread and resolved the issue. Thanks.
How to delete CO plan data
Hi Ajay,
Thank you, We are uplaoding through KP06, Menu -->Extras --> Excel Planning --> Upload.
Regards,
Raj

Similar Messages

  • Creating some sort of text template for multiple pictures

    Hello, I'm new to the forums and new to photoshop elements. Let me lay out the situation so you have a better idea of what I'm trying to do and why. I work at a real estate office and we are going to hang a tv on the wall and display a slideshow of our homes for sale and ontop of the pictures I am going to add text to each photo with information about the home. I want to be able to add text in the same proportions in the same spot on each photograph. Is there some automatic way of doing this? I will have to hand type different info on each photo. The pictures come from different cameras (each agent takes their own photos) with different resolutions and doing it one by one (ive done just a few out of over a hundred so far) I'm finding out that one size text works on one but when I try to use the same size font on the next photo it's either too big or too small, I guess this is because of the different resolutions of each camera. I know I may have rambled a bit here but if anyone can point me in the right direction I'd be thankful.
    If I need to clear up anything I've said let me know.
    Thanks

    I believe you responded to the wrong posting. Mine is titled "Transferring from MyPictures "
    Date: Thu, 17 Sep 2009 14:12:24 -0600
    From: [email protected]
    To: [email protected]
    Subject: Re: Creating some sort of text template for multiple pictures
    The font size is correlated with the resolution.
    Have you investigated use of Powerpoint to construct a continuous-loop presentation?
    "Self-running presentations are a great way to communicate information without having to have someone available to run a slide show. For example, you might want to set up a presentation to run unattended in a booth or kiosk at a trade show or convention. You can make most controls unavailable so that users can't make changes to the presentation. A self-running presentation restarts when it's finished and also when it's been idle on a manually advanced slide for longer than five minutes.
    When designing a self-running presentation, you'll want to keep the setting in mind — for example, whether the booth or kiosk will be in an unmonitored public place or whether supervision will be available. The answer will help you determine what elements you add to your presentation, how much control you give users, and what steps you need to take to prevent misuse.
    To set up a self-running show: open the presentation, click Set Up Show on the Slide Show menu, and then click Browsed at a kiosk (full screen). When you click this option, Loop continuously until "Esc" is automatically selected."
    >

  • Template for uploading account trial balance

    Hi,
                Is there any template for uploading trial balance of chart of accounts  in SAP Business One.
    Thanks in Advance.
    Thanks and Regards,
    Jai

    hi
    Go in Financial > Financial Reprt Template > Choose balance Sheet
    Create new template and Assign a Name
    Click on "Generate Std Chart Of Account"
    Update > Ok
    Same for other template
    Thanks
    Kevin

  • DTW template for uploading Intial Quantities

    hi,
    Can anybody of you tell me what is name of DTW template for uploading
    intial quantities ?
    Thanks,
    A.Jeyakanthan

    Thank you all for reply
    In oStocktaking
    template contains itemcode,warehouse & quantity.
    We also require price to uploaded with initial quantities,
    how to do it ?

  • CSV file template for Uploading PO confirmaiton

    Dear all,
    We have activated Badi for Upload PO confirmations for a supplier in SNC 7.0.
    Request if any of you can please let me know where can I find the CSV upload file template.
    Thanks,
    mahesh.

    Hi Mahesh,
    You can download the CSV file from Tools-->Download center(select purchase order confirmation.
    To create a purchase order confirmation, you enter X in the To Be Confirmed column of the schedule line. If the schedule line has an X, you can change the following data:
    ■Quantity
    ■Delivery date
    Note
    Depending on the system set-up, for example if you have set up Customizing for POs to allow shipping dates to be used instead of delivery dates, you can change the shipping date.
    End of the note.
    ■Confirmed price
    Note
    If you leave the Confirmed Price field empty in all schedule lines of an item, the requested price is used. If you enter a value in the Confirmed Price field of one of the schedule lines, or in more than one schedule line, but those values are the same, the system uses that value as the confirmed price for the item. However, if you enter two or more different confirmed price values in the schedule lines of an item, the system regards this as an error, and the item is not processed.
    End of the note.
    ■Confirmed MPN
    ■Confirmed Mfr
    ■To reject the PO item, you enter an X in the To Be Rejected column of the schedule line that has an X in the Requested column.
    Now upload this file in Tools->upload center.
    See the below link for more information.
    http://help.sap.com/saphelp_snc70/helpdata/EN/b4/79223dc5b54b36899ea4f731a712f6/frameset.htm
    Regards,
    Nikhil

  • Creating text file for upload to bank

    Post Author: kevin belyea
    CA Forum: General
    I'm creating a .rpt that requires specific formatting to be uploaded into banking software for automatic payment processing. There are a couple of specifics that I've been stumbling on. Here they are:
    1. I need to remove  the leading $ from a string. The string is displaying as $0000002233 which is correctly stated as a 10-character filed for the amount of $22.33
    2. Any idea on how to format a julian date? For example today's date would be displayed as 07282  (2007 282/365)
    Any help for this new poster would be appreciated.
    Kevin

    Post Author: kevin belyea
    CA Forum: General
    Thanks for the quick reply.
    The first solution worked great. - Thanks
    The second solution worked partially in that it returned the following value 00282. I would like to pickup the last two digits of the year (07). It looks like it is picking up the middle two characters. I tried a couple of variations of the formula but no luck. Any suggestions?
    Kevin

  • Creating an offline PDF template for upload and submit

    Hi Gurus,
    I'm very new to Adobe Interactive forms and will need your advise.
    From the tutorials, when we create a offline PDF application that can upload a PDF for submission, we were always given the sample template PDF file provided by the tutorial. (travelrequest.pdf)
    Now I need to create my own offline PDF template by myself so I can integrate to my WD program to include uploading the offline PDF template and submitting to backend.
    the offline PDF must be editable and save via acrobat reader.
    Any further notes or documentations that I can follow up to? Cos most of the doc I found doesn't teach me how to go about creating the PDF template for offline use in the first place...only the backend and WD integration which I already know.
    Please help! Thanks!
    ps: points will be generously awarded to answers.
    Regards,
    Jansen

    Hi Jansen,
    As far as I know the WAS 620 only supports to output your Forms and Scripts to PDF Format but they are not interactive.
    The Adobe Interactive Forms Solution is only available from WAS 640. You can design your forms either in ABAP transaction SFP or in NWDS(Netweaver Developer Studio) Form Designer.
    For craeting forms in WD ABAP, have a look at the links below:
    SAP Interactive Forms by Adobe
    http://help.sap.com/saphelp_nw2004s/helpdata/en/b7/64348655fb46149098d95bdca103d0/frameset.htm
    Web Dynpro ABAP
    http://help.sap.com/saphelp_nw2004s/helpdata/en/77/3545415ea6f523e10000000a155106/frameset.htm
    regards,
    harman

  • MOSS 2007 bulk upload tools for upload 80 gb data to library

    hi,
    i have created document library on MOSS 2007 , now i need to upload 80 gb data to library .
    please help.
    Thanks,
    Saidireddy

    Assuming you're migrating from the file system:
    - Windows Explorer view for simple scenarios (limited feedback if something goes wrong)
    - You can try if MS SyncToy supports 2007 (free tool, advanced features)
    - There are free community tools out there on TechNet gallery and CodePlex
    - Lastly, to do an Enterprise level migration you will need to use a commercial product such as DocAve or Quest
    So it depends on your needs and requirements
    Kind regards,
    Margriet Bruggeman
    Lois & Clark IT Services
    web site: http://www.loisandclark.eu
    blog: http://www.sharepointdragons.com

  • Method for uploading Customer Hierarchy Data

    hi experts,
    i have a requirement in which i need to upload Customer Hierarchy data into ECC system from CRM system.
    I need to know is there any method in LSMW by which i can do it?
    thanks,
    Ags.

    resolved..

  • Table for Cost center plan data by version

    Hello,
    I need to find out which tables in sap hold the cost centre and profit centre plan data by version.
    I am having trouble finding the tables if anyone can help?
    Thanks

    COEP     CO Object: Line Items (by Period)(costing document line item information)
    Orders, sales document items or cost centers can be described as object types. The connection of an object to its CO data is given by the general object number (OBJNR field in the CO tables, such as COEP-OBJNR). This field provides you with information about the object type and, if needed, about the object key (such as the order number).
    GLPCP   EC-PCA: Plan Line Items

  • Text template for PO text in material master

    Has anyone created a template that could be imported into the PO text in the material master? I am looking for a template that will prompt users to enter required information for a description.

    Suresh,
    Its a standared functionality, when you are copying the purchasing view, it has to copy the automatic PO check box also.
    There is no settings in system
    Regards,
    Manish

  • Dynamically update values in Text Lists for typed measures

    Hi,
    We have an alpha-numeric data column in our fact table. This is a data coulmn and we want to store its content as data value in one of the measures. The value in this column is highly dynamic and it is not restricted to a fixed set of values. To store the values we need to use typed measures, but is there way in which I can define the text list itself dynamically? Meaning, we will build the text list dynamically as and when the data comes in the fact table. Is this possible. We are using 11.1.2.1.
    Regards,
    Krishna

    I don't think we have a MaxL (I can be worng) to update Text Lists. You can try creating .slt file dynamically and then manually import them before data load.
    .slt will have entries like
    #MISSING NoData
    #OUTOFRANGE OutOfRange
    3 Bad
    2 Average
    1 Good
    Edited by: Celvin Kattookaran on Mar 21, 2013 12:33 PM

  • Long text problem while uploading Inspection plan through BDC.

    Hi,
    I am facing some problem while uploading the inspection plan. There are few MICs for which we are having long text, while uploading the inspection plan through BDC - some other long text is getting copied into the MIC's long text. After checking I came to know that in function module, read_text - some text which is stored in ABAP memory is getting copied into the inspection plan.
    I am working in SAP release 4.7. I have checked with SAP notes: 97419, but it is also not satisfying.
    Waiting for quick solution.
    Thanks in advance.
    Fahié

    Hi a®s,
    Thanks a lot for your kind reply.
    My requirement is I want to maintain long text for few MICs (which are not having long texts at MIC level) in inspection plan (QP01).
    When I am trying to manually assign the MIC's to inspection plan (QP01), long text is copied whereas I am not clicking the long text icon in (QP01). Long text is not maintained in MIC level, still some long text is copied to this MIC. This was also happening while uploading the inspection plan thro' BDC.
    I believe what you have mentioned about function module SAVE_TEXT cannot be used here since long text is already copied before we pass the long text. Also if we pass some long text, still apart from the long text what we have passed there is some other long text copied (extra long text).
    Waiting for quick solution.
    Thanks in advance.
    Fahié

  • Appraisal template for performance management plan

    Hi, I can see my performance management plans in the table per_perf_mgmt_plans. But in this table I can't see the appraisal template that is linked to the plan. Is there any table or view which shows this?
    Thanks

    Thanks for the answer but I actually would like to see it in a database table. In the per_perf_mgmt_plans table there is no mention of the appraisal template. Is there a table or view I can find this link between the plan and the appraisal template? Thanks

  • Program for uploading the PO data of known vendor in MM using the flat file

    hi friends,
                    I got problem while uploading PO data for a vendor.what are the possible ways of uploading data.
    Moderator message: please do your own research before asking.
    Edited by: Thomas Zloch on Jan 11, 2011 11:37 AM

    hi friends,
                    I got problem while uploading PO data for a vendor.what are the possible ways of uploading data.
    Moderator message: please do your own research before asking.
    Edited by: Thomas Zloch on Jan 11, 2011 11:37 AM