Xcelsius 2008 - Life cycle management

All,
We have developed Xcelsius 2008 dashboards (by QAAWS) which are published in BO XI 3.0 Enterprise Infoview. How do we promote Xcelsius dashboard from development to production? Do Import wizard help on this?
Below are the workflow that I think about:
1) Create QAAWS in both development and production
2) Create dashboard in Xcelsius 2008 in development through WSDL URL created in QAAWS
3) Publish the report in BO 3.0 Infoview.
4) Through Import Wizard, import dashboard from dev to prod.
My question is how do we map the imported dashbaord in production to production WSDL URL.
Please let me know the above approach for Xcelsius 2008 life cycle management is correct.
Thanks
Jai

Thanks Jon. So all I need to change Web Service URL from:
http://bodevserver:8080/dswsbobje/qaawsservices/queryasaservice
to
/dswsbobje/qaawsservices/FIAR?WSDL.
But how will this change to production server WSDL URL when this report moves to prod by import wizard?
Below is the work flow I did in QAAWS client:
1) Created 2 URL one for Dev and another for Prod
2) Created first URL in development through QAAWS client and deploy the same in prod by changing the prod server name.
For Dev --> http://bodevserver:8080/dswsbobje/qaawsservices/FIAR?WSDL
For Prod --> http://boprodserver:8080/dswsbobje/qaawsservices/FIAR?WSDL
I am still confused how these above 2 links helpful in Xcelsius to do life cycle managemnet without any mannual interpretation.
Thanks
Jai

Similar Messages

  • Error while executing transport in HANA's application life-cycle management

    Hi everyone,
    we're currently developing our HANA-based software and would like to use HANA's application life-cycle management: transporting our product from one system to another. Everything seems to be set up correctly: two different systems, correct privileges, a product comprising delivery units comprising packages as well as a transport route between the systems. However, the transport always fails with the following error (example for a transport of a single DU):
    [imdbhdb][HDB][2014.05.07 15:10.01.404][TransportService][0] Transport (delta) has been started for route ID: 1020 (Deliver Unit Transport)
    [hanaserver][HDB][2014.05.07 15:10.08.323][Other][0] Get end export timestamp for DU name: PERSISTENCE
    [hanaserver][HDB][2014.05.07 15:10.08.501][Other][12] Unable to retrieve end export timestamp: ReferenceError: assignment to undeclared variable errText
    [imdbhdb][HDB][2014.05.07 15:10.12.402][TransportService][0] There will be 1 delivery units which will be transported.
    [imdbhdb][HDB][2014.05.07 15:10.12.895][TransportService][12] Failed for DU: PERSISTENCE Vendor: LO Error: HTTP request failed. Status: 500. Error: Unable to retrieve end export time stamp.
    [imdbhdb][HDB][2014.05.07 15:10.12.917][TransportService][12] TransportServiceError: Error occurred while performing the transport.
    Does anyone know how to resolve this?
    Thanks so much in advance,
    Lukas

    Hi everyone,
    I am sorry I bothered you with this error. It was caused by me since I forgot to export a top-level file. This file must have defined a variable errText which other DUs depended on and could therefore not be activated.
    Now, the transport works perfectly well and I'm really happy with it.
    All the best
    Lukas

  • Business Partner Roles and Account Life Cycle management in IC

    Hi all,
    We have IC agents creating prospects but also back office people (i.e. sales staff) creating prospects. Back office staff uses account life cycle management to identify the prospect role. However, I noticed that the business partner role (prospect in this case) is not visible within the IC - during account creation - because the role is used within the account life cycle role exclusion group.
    I can always enhance the IC component to remove the filter on the BP Role. but question I have is why does SAP IC remove the roles from the role drop down list in the IC account creation screen and how did other people get around this?
    Thanks,
    John

    I am also looking for an answer on this. How did other people who work on Interaction Center get around this? How do you create accounts when IC removes the BP roles mentioned in the Exclusion group config in SPRO ?

  • Requirement of E-sourcing and e-CLM (contract life cycle management) in SRM

    Dear Experts,
    Does one need to install e-sourcing and eCLM (contract life cycle management) in SRM 7.0 to take the benefit of full functionality available in SRM 7.0?
    My understanding says that e-Sourcing and CLM are not must for SRM 7.0. They are basically available separately as on demand product who may not have SRM landscape.
    Any ideas shared will be highly appreciated.
    Reagrds,
    Ranjan

    Hi Ranjan -
    The answer is NO, you do not need E-Sourcing/CLM to install and work with the contract functionality in SRM 7.0.  These are completely different products / systems.  The contracts functionality in CLM is oriented toward contract authoring / qualitative information management about contracts, while the functionality in SRM is more oriented toward the quantitative contract information/execution of the contracts against orders.
    Hope this helps,
    Emily

  • Regarding SLCM (Student Life Cycle Management)

    Hi
    does any one working on Student Life Cycle Management(SLCM)
    can any one pls let me know what are the function modules present in the predefined business package and how to know what are the predefined functonalites given by sap.
    when i test the predefined Iviews i get an error for some of iview as student object id not found.
    can any one pls let me know about this
    Bye

    Ok Fine
    I have some points to share thise issue with u
    first thing is , iam using wrong application for the requirement.
    and even i use wrong apps some thing result should be show, as i said the error i got
    we raised an sap Oss for this, they provided the solution as stating that we are using the apps which are specific to the advisor but not for the students specially.
    So if u want to use those apps for student purpose we need to get that student object and pass in our application.
    for this purpose we need an abaper help who is well versed in the coding part.
    just modify the code of required application where u fetch the object id (BY Coding) in ithe intialization method,
    then the appication works fine
    this is the solution i got and all my apps are working fine now.
    Thanxs
    sandeep

  • What is life cycle management in netweaver architecture

    hi all,
    I am new to sap can any one help me by sending me links on life cycle management in NetWeaver architecture.

    http://www.sap.com/platform/netweaver/pdf/BWP_SB_Unified_Lifecycle_Management.pdf
    http://www.sap.com/solutions/business-suite/plm/pdf/BWP_Life_Cycle_Process_Support.pdf
    http://www.filetek.com/software/product_sheets/datasheet_SAP.pdf

  • Custom code life cycle management (CCLM)

    Hi Gurus ,
    At this moment i'm working on Custom code life cycle management concept in Solution Manager.
    If any one worked on this one previously can you please send me complete document.
    It's Urgent Plssssss
    Thanks in Advance...
    Vijay R.

    Hi Vijay,
    Check below links for CCLM
    how to guide
    https://service.sap.com/~sapidb/011000358700000426872012E
    1547234 - Technical configuration of Custom Code Lifecycle Management
    SAP Solution Manager WIKI - Custom Code Management - Solution Manager - SCN Wiki
    https://websmp206.sap-ag.de/~sapidb/011000358700000426872012E
    hope this helps
    Thanks
    Prakhar

  • Hyperion Life Cycle Management Utility - 9.3.1

    Hi Friends,
    Our environment is Hyperion System 9.3.1 on Windows box & repository in Oracle 10gR2 database.
    We are facing problem in exporting "x-brioquery" Repository Objects by using "Hyperion Life Cycle Managament Utility" :
    LCM utility is running without any error in log file but in "ExportedOutput" folder
    there is only one folder named "info".
    Resource folder is not getting created.
    Please guide us for the same.
    Kind Regards,
    Manmohan

    Apparently this is reported as a bug.

  • Automatic Life Cycle Management in OWB?

    Hello,
    i actally read a white paper (Integrated ETL and Modeling) about OWB. In this paper is a chapter about Life Cycle Management. This chapter sounds to me, that OWB automaticly detects changes in the source or target system and made a message to the programmer.
    In my OWB (10g) I detect changes when I deploy my mappings. So it could happen, that i worked a few days at my mappings, not knowing that sources or targets have changed. That is extreme painful!
    Is it possible I have overlook this feature of OWB?
    Regards Franz

    HI,
    when you feel like source tables got some changes,jus try to import again,then it will show you,whether the souce changed or unchanged.
    Regards
    naren

  • Content Life Cycle Management - Portal or NW Client.

    Hello GRC PC Experts,
    Kindly let us know whether Content Life Cycle Management is compatible on  Portal as front end.
    Or whether CLM is only compatible with NW Client.
    Please let us know.
    Thanks and regards
    Babu

    Hi,
    You need to integrate the system with portal
    system administration - system configuration and then add system.
    If you have sso then it is better.
    Then create new iview using templetes and then use SAP bsp iview templete and then select the system and then give the application name and start page of your BSP application.
    Thanks and Regards,
    gopal

  • Product life cycle management in sap

    Hi,
    is there any prescribed material for product life cycle management (PLM) IN SAP? can anyone refer  any institute name and where it is for learning SAP-PLM?

    Dear heeru
    Go through the links
    [Life cycle profile|http://help.sap.com/saphelp_46c/helpdata/en/08/2b2c8c50c711d3b478006094b9d648/frameset.htm]
    [Configuration Definition|http://help.sap.com/saphelp_46c/helpdata/en/74/7b601ac80811d3b4bc006094b9d648/frameset.htm]
    Thanks
    G. Lakshmipathi

  • Life Cycle Management BODI

    Hi folks,
    can anyone give me some hints how life cycle management is done in BODI?
    I want to connect a DB2 database via BODI with a BI. BI comes in 3 tier layer. Would you install 3 BODI server? And if so how do I "transport" the changes from one repository (Development) to another one (Production)?
    What is best practice for that?
    Unfortunately I didn't find any documents so far.
    Your help is very welcome.
    Best regards
    Michael

    This is what I have: https://wiki.sdn.sap.com:443/wiki/pages/viewpage.action?pageId=49414406

  • Life cycle manager setup

    Hi,
    I have just installed the Enterprise 4.0 platform and want to get started using the Life Cycle Manager.
    I have read the manual but still I wonder if it is possible to make sure that you can only transport objects from Development --> Test --> Production or can it just happen randomly from any system --> any system?
    I don't seem to be able to find an answer to this in the documentation.
    Any ideas?
    Kim Johannsen

    Hi John
    It is still possible to connect directly from DEV to PROD if you want to do so. I realize that you for each LCM enviroment can specify the origin system which to some extent ensure that you don't  move object to the wrong system, but the destination can still be any environment.
    My conclusion is that you just have to be careful and think about what you are doing
    /Kim

  • CMC: Security: Life Cycle Manager (LCM) missing under "Appication" Security

    Hello there,
    I am trying to set up security for the Life Cycle Manager (LCM). LCM has been installed on the BO 3.1 DEV_System with version SP2, FP4, by another company.
    I am using the procedure described in the (my opinion very well written) article:
    http://wiki.sdn.sap.com/wiki/display/BOBJ/FromDEVtoQAtoPRODusingLifeCycleManager
    The problem is, in the CMC security, under "Application" ("Anwendung") security, I cant see the "life cycle manager",
    Hence, e.g. I cant grant access to "Application"->"Life Cycle Manager"->"Create Job". I am using an Admin user with full rights.
    The life cycle manager does show up however under "Content" ("Inhalt") security, but I guess this concerns other security settings bc granting access to all of "Content"->"Life Cycle Manager" and "Content"->"Life Cycle Manager Job" still didnt allow end-user to create jobs.
    Did anybody stumble accross the same or has an explanation or solution?
    I think this is either a installation or configuration issue (are there any additional settings after intallation needed in other places in order to display security "Application"->"Life Cycle Manager" security in CMC and be able to grant end-users the appropriate rights) ?
    Thanks a lot for your help!

    Hi there,
    thanks... meanwhile, I found a SAP note that describes exactly the problem:
    1443784
    Advice is to even delete the whole workfolders for all webapps (.../localhost/catalina/...) and deployfolder and after that, start tomcat again.
    This also seemed to deploy all the webapps again, also, date from the deployed files indicates they really got redeployed.
    But: Still the same behaviour, no LCM in CMC-Security under "Applications" .
    Since everything got deployed again guess already the files that are deployed are not containing the right information!
    Maybe, during installation, they didnt get updated somehow.
    So, guess only solution will be to completely uninstalling LCM, reinistall it and cross finger that this time, the files will get updated.
    I already tried uninstalling FP 2.4, reinstalled it, no improvement (although it says it is updating CMCApp and CMCAppAction during installation - maybe the necessary updates are already done during isntallation of SP0/SP1/SP2).
    When trying to uninstall SP2 after FP 2.4 is uninstalled, get an error "missing .dll" - it is a mess, but I will keep on fighting
    If anybody has a clue how to specifically change specific files under CMCApp and CMCActionApp directly (dont know if that is possible though...) so that LCM App is displayed correctly in CMC Security->Application , would also be an acceptable workaround .

  • What is (sdlc) software developement life cycle management in hyperion esssbase and planning ?

    what is (sdlc) software developement life cycle management in hyperion esssbase and planning ?

    SDLC is a high-level concept (https://en.wikipedia.org/wiki/Systems_development_life_cycle) not a feature of a particular software package, so I'm really not sure what you're asking.
    If you're asking about the somewhat related topic of moving changes through environments, look at About Lifecycle Management.

Maybe you are looking for